Monthly Local Let Maintenance Report For Paris District As Of Apr 10, 2015 Page 5 Of 6

Last Update: Friday, April 10, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHUNT
Highway SH0011
From VARIOUS ROADWAYS IN
To HUNT COUNTY
CSJ 6280-56-001
Proj ID RMC - 628056001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 216822.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 72
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ANTHONY SERVICES (INACTIVE)
SUBCONTRACTOR(S) FOR CCSJ: 6280-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12140108
Totals 216822.00 0.00 0.00 0.0

CountyRAINS
Highway US0069
From VARIOUS ROADWAYS IN
To RAINS COUNTY
CSJ 6280-57-001
Proj ID RMC - 628057001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 138834.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 58
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
C & C MOWING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6280-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12140109
Totals 138834.00 0.00 0.00 0.0

CountyFANNIN
Highway US0082
From VARIOUS ROADWAYS IN
To FANNIN COUNTY
CSJ 6280-58-001
Proj ID RMC - 628058001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 225886.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 96
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
GANT CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6280-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12140110
Totals 225886.00 0.00 0.00 0.0

CountyLAMAR
Highway US0082
From VARIOUS ROADWAYS IN
To LAMAR COUNTY
CSJ 6280-59-001
Proj ID RMC - 628059001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 199717.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 74
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RICKEY BAIRD
SUBCONTRACTOR(S) FOR CCSJ: 6280-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12140111
Totals 199717.00 0.00 0.00 0.0

CountyDELTA
Highway SH0024
From VARIOUS ROADWAYS IN
To DELTA COUNTY
CSJ 6280-60-001
Proj ID RMC - 628060001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 103026.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 52
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
GANT CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6280-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12140112
Totals 103026.00 0.00 0.00 0.0

CountyRED RIVER
Highway US0082
From VARIOUS ROADWAYS IN
To RED RIVER COUNTY
CSJ 6280-61-001
Proj ID RMC - 628061001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 183339.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 71
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RICKEY BAIRD
SUBCONTRACTOR(S) FOR CCSJ: 6280-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12140113
Totals 183339.00 0.00 0.00 0.0

CountyLAMAR
Highway US0082
From VARIOUS LOCATIONS IN LAMAR AND
To DELTA COUNTIES
CSJ 6280-71-001
Proj ID RMC - 628071001
Work Type ON CALL TREE TRIMMING / REMOVAL
 
0.001 174524.00 31931.00 31931.00 18.2
Work Order 01-20-15
Work Began 00-00-00
Work Completed  
Time Computed 02-09-15
Contract Working Days 175
Addl Days Granted 0
Working Days Charged 6
Percent Time Used 3
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6280-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12140115
Totals 174524.00 31931.00 31931.00 18.2

CountyRED RIVER
Highway US0082
From VARIOUS ROADWAYS
To IN RED RIVER COUNTY
CSJ 6280-88-001
Proj ID SUP - 628088001
Work Type PICNIC AREA MAINTENANCE
 
0.001 22835.00 1770.00 7200.00 31.5
Work Order 11-12-14
Work Began 11-17-14
Work Completed  
Time Computed 11-17-14
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 135
Percent Time Used 36
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6280-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11140131
Totals 22835.00 1770.00 7200.00 31.5

CountyLAMAR
Highway US0271
From VARIOUS LOCATIONS IN
To LAMAR AND RED RIVER COUNTIES
CSJ 6281-30-001
Proj ID RMC - 628130001
Work Type HIGH EDGE REMOVAL
 
0.001 189782.40 0.00 0.00 0.0
Work Order 02-17-15
Work Began 00-00-00
Work Completed  
Time Computed 03-03-15
Contract Working Days 34
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONE STAR BARRIER SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6281-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01150104
Totals 189782.40 0.00 0.00 0.0

CountyGRAYSON
Highway US0082
From VARIOUS LOCATIONS IN GRAYSON AND
To FANNIN COUNTIES
CSJ 6282-62-001
Proj ID RMC - 628262001
Work Type ON CALL TREE TRIMMING & REMOVAL
 
0.001 297900.00 9307.00 22841.50 7.6
Work Order 01-30-15
Work Began 02-09-15
Work Completed  
Time Computed 02-16-15
Contract Working Days 175
Addl Days Granted 0
Working Days Charged 14
Percent Time Used 8
Contractor(s)
DEKALB TREE SPECIALIST
SUBCONTRACTOR(S) FOR CCSJ: 6282-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01150105
Totals 297900.00 9307.00 22841.50 7.6

CountyHOPKINS
Highway IH0030
From VARIOUS LOCATIONS
To IN HOPKINS COUNTY
CSJ 6282-67-001
Proj ID SUP - 628267001
Work Type PICNIC AREA MAINTENANCE
 
0.001 28676.00 1923.00 5161.00 17.9
Work Order 01-12-15
Work Began 01-15-15
Work Completed  
Time Computed 01-15-15
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 76
Percent Time Used 20
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6282-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12140131
Totals 28676.00 1923.00 5161.00 17.9

CountyLAMAR
Highway US0271
From VARIOUS LOCATIONS THROUGHOUT
To ENTIRE PARIS DISTRICT
CSJ 6282-69-001
Proj ID RMC - 628269001
Work Type ON CALL LARGE SIGN MAINTENANCE
 
0.001 232875.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 254
Addl Days Granted 0
Working Days Charged 2
Percent Time Used 0
Contractor(s)
LONE STAR BARRIER SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6282-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02150104
Totals 232875.00 0.00 0.00 0.0

CountyLAMAR
Highway US0271
From VARIOUS LOCATIONS IN
To LAMAR AND RED RIVER COUNTIES
CSJ 6283-01-001
Proj ID RMC - 628301001
Work Type BACKFILLING PAVEMENT EDGES
 
0.001 369158.88 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-20-15
Work Began 00-00-00
Work Completed  
Time Computed 04-22-15
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ANCHOR CONTRACTING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6283-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02150101
Totals 369158.88 0.00 0.00 0.0

CountyHOPKINS
Highway IH0030
From ALONG IH30 IN HUNT, HOPKINS, AND
To FRANKLIN COUNTIES
CSJ 6283-06-001
Proj ID RMC - 628306001
Work Type REMOVAL AND DISPOSAL OF DEBRIS
 
0.001 272376.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-18-15
Work Began 00-00-00
Work Completed  
Time Computed 05-08-15
Contract Working Days 254
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MORTON ENTERPRISE
SUBCONTRACTOR(S) FOR CCSJ: 6283-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02150103
Totals 272376.00 0.00 0.00 0.0

CountyLAMAR
Highway US0082
From VARIOUS LOCATIONS
To IN LAMAR AND RED RIVER COUNTIES
CSJ 6283-22-001
Proj ID RMC - 628322001
Work Type CLEAN EXISTING BRIDGE JOINTS
 
0.001 38301.31 750.00 750.00 1.9
Work Order 03-16-15
Work Began 03-23-15
Work Completed  
Time Computed 03-30-15
Contract Working Days 16
Addl Days Granted 0
Working Days Charged 2
Percent Time Used 12
Contractor(s)
REYNOLDS & KAY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6283-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02150102
Totals 38301.31 750.00 750.00 1.9

CountyLAMAR
Highway US0082
From VARIOUS LOCATIONS
To IN PARIS DISTRICT
CSJ 6283-23-001
Proj ID RMC - 628323001
Work Type ILLUMINATION MAINTENANCE
 
0.001 187351.25 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-17-15
Work Began 00-00-00
Work Completed  
Time Computed 04-08-15
Contract Working Days 261
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6283-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02150106
Totals 187351.25 0.00 0.00 0.0

CountyGRAYSON
Highway US0075
From GRAYSON CO AREA OFFIC
To AND MAINT COMPLEX
CSJ 6283-92-001
Proj ID SUP - 628392001
Work Type JANITORIAL MAINTENANCE
 
0.001 30576.06 4574.28 4574.28 14.9
Work Order 02-27-15
Work Began 03-01-15
Work Completed  
Time Computed 03-01-15
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 31
Percent Time Used 8
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6283-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02150131
Totals 30576.06 4574.28 4574.28 14.9

CountyHOPKINS
Highway IH0030
From HOPKINS COUNTY MAINT OFFICE
To AREA/MAINT OFFICES
CSJ 6283-93-001
Proj ID SUP - 628393001
Work Type JANITORIAL MAINTENANCE
 
0.001 14782.16 0.00 1515.36 10.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-02-15
Work Began 00-00-00
Work Completed  
Time Computed 03-01-15
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 31
Percent Time Used 8
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6283-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01150131
Totals 14782.16 0.00 1515.36 10.2

CountyGRAYSON
Highway US0075
From VARIOUS LOCATIONS ALONG US 75
To AND US 82 IN GRAYSON COUNTY
CSJ 6285-23-001
Proj ID RMC - 628523001
Work Type HIGH EDGE REMOVAL
 
0.001 240962.75 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONE STAR BARRIER SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6285-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03150102
Totals 240962.75 0.00 0.00 0.0

CountyGRAYSON
Highway US0377
From VARIOUS LOCATIONS IN
To GRAYSON COUNTY
CSJ 6285-24-001
Proj ID RMC - 628524001
Work Type HIGH EDGE REMOVAL
 
0.001 237443.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6285-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03150103
Totals 237443.00 0.00 0.00 0.0