Monthly State Let Construction Report For Pharr District As Of Nov 20, 2014 Page 2 Of 3

Last Update: Thursday, November 20, 2014
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHIDALGO
Highway US 281
From FM 907
To FM 493
CSJ 0220-01-029
Proj ID C 220-1-29
Work Type REHAB & WIDEN PAVEMENT (SUPER 2)
 
5.024 6266718.83 0.00 6248092.96 99.9
CountyHIDALGO
Highway US 281
From FM 493
To FM 88
CSJ 0220-01-030
Proj ID C 220-1-30
Work Type REHAB & WIDEN PAVEMENT (SUPER 2)
 
4.353 4903240.81 0.00 4889179.09 99.7
Work Order 05-13-11
Work Began 06-07-11
Work Completed  
Time Computed 05-29-11
Contract Working Days 400
Addl Days Granted 0
Working Days Charged 543
Percent Time Used 135
Contractor(s)
LIBERTY MUTUAL INSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0220-01-029
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (1.60%)
PAVEMENT MARKINGS INC. (2.26%)
HIGHWAY TECHNOLOGIES, INC. (0.25%)
TREV-CORT TRUCKING INC ( 11.96%)
EXTERIOR DESIGNS (0.92%)
CABCOS CONTRACTORS LLC (3.69%)
LONE STAR TRAFFIC SERVICE, INC.(0.37%)
JAVELINA CONSTRUCTION SOUTH, INC.(1.03%)
DUSTROL, INC.(0.20%)
LAREDO STRIPING INC. (0.24%)
SOIL-TECH, INC.(0.65%)
VALLEY INFRASTRUCTURE, INC.(2.13%)
Contract # 04113210
Totals 11169959.64 0.00 11137272.05 99.9

CountyCAMERON
Highway US 281
From 0.05 MI W OF FM 1479
To 0.24 MI EAST OF FM 506
CSJ 0220-03-028
Proj ID STP 2015(037)
Work Type REHAB & WIDEN EXIST ROADWAY SUPER 2
 
3.863 7709997.35 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 400
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ASAGO, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0220-03-028
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143009
Totals 7709997.35 0.00 0.00 0.0

CountyBROOKS
Highway US 281
From BUS 281 NORTH SIDE
To BROOKS COUNTY LINE
CSJ 0255-03-026
Proj ID HP 2009(663)ES
Work Type GR., STRS., AND SURF
 
4.133 40039527.43 -1110.83 43876625.66 99.9
CountyBROOKS
Highway US 281
From SH 285
To BROOKS COUNTY LINE
CSJ 0255-03-031
Proj ID RW 255-3-31
Work Type ACQUISITION, UTILITIES AND RELOCATI
 
0.001 1792061.65 0.00 2106080.62 99.9
CountyBROOKS
Highway US 281
From BUS 281 NORTH SIDE
To BUS 281 SOUTH SIDE
CSJ 0255-14-001
Proj ID STP 2009(664)ES
Work Type GR., STRS., AND SURF
 
2.062 25860723.89 19712.01 25522158.69 98.6
Work Order 07-14-09
Work Began 08-18-09
Work Completed  
Time Computed 07-30-09
Contract Working Days 720
Addl Days Granted 167
Working Days Charged 1,211
Percent Time Used 136
Contractor(s)
ZURICH AMERICAN INSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0255-03-026
HIGHWAY TECHNOLOGIES, INC. (0.46%)
LEAL CONSTRUCTION, INC.(3.11%)
MENDEZ EXCAVATION(0.27%)
RHYNER CONSTRUCTION SERVICES, INC. (0.15%)
SUNBELT EXPRESS SERVICES, INC. (0.77%)
EXTERIOR DESIGNS (0.76%)
W. W. FOUNDATION DRILLING, LTD.(2.75%)
LAREDO STRIPING INC. (0.64%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.04%)
CHICO TRUCKING CO., INC. (1.38%)
J & P TRUCKING AND HAULING (6.05%)
CABCOS CONTRACTORS LLC (1.64%)
STAR OPERATIONS, INC.(3.55%)
CRAWFORD YANT(0.16%)
CERTIFIED PLACERS LLC(0.47%)
RGV ALLIANCE CONSTRUCTION, L.L.C.(1.28%)
SOUTH TEXAS INDUSTRIAL COATINGS, L.L.C.(0.05%)
MORRIS CONSTRUCTION, INC.(0.31%)
CORTEZ TRUCKING TRANSPORT(1.82%)
DOUG'S DRIP IRRIGATION (0.16%)
G & E ESCOBEDO CONSTRUCTION, INC.(0.02%)
ADVANCED PUMPING CONCEPTS, INC.(0.08%)
JAVELINA CONSTRUCTION SOUTH, INC.(0.15%)
LAND SOLUTIONS CONSTRUCTION, LLC (0.14%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.25%)
D S TEXAS ICON CONSTRUCTION, LLC (0.01%)
DUSTROL, INC.(0.07%)
TEXAS CORDIA CONSTRUCTION, LLC (2.55%)
PIERCE CONSTRUCTION AND CONTRACT HAULING (1.53%)
GUERRA CONSTRUCTION COMPANY(0.30%)
HIGHWAY BARRICADES AND SERVICES, LLC (0.30%)
D & C CONCRETE CUTTING, INC. (0.00%)
TEXAS CURB CUT, INC.(HUB)(0.01%)
HURRICANE FENCE COMPANY(0.28%)
Contract # 05093023
Totals 67692312.97 18601.18 71504864.97 99.9

CountyBROOKS
Highway US 281
From US 281 @ FM 755
To .
CSJ 0255-05-034
Proj ID C 255-5-34
Work Type CONSTRUCT OVERPASS
 
1.373 13828828.39 22762.10 13863980.24 99.9
Work Order 10-24-12
Work Began 01-03-13
Work Completed  
Time Computed 11-09-12
Contract Working Days 238
Addl Days Granted 0
Working Days Charged 454
Percent Time Used 190
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0255-05-034
CABCOS CONTRACTORS LLC (5.36%)
CERTIFIED PLACERS LLC(0.24%)
COWBELL TRAFFIC SERVICES, INC. (0.04%)
D S TEXAS ICON CONSTRUCTION, LLC (0.23%)
FOREMOST PAVING, INC.( 25.22%)
GUERRA CONSTRUCTION COMPANY(0.85%)
HIGHWAY TECHNOLOGIES, INC. (0.82%)
PRIMATE CONSTRUCTION, INC. (0.11%)
S & S BRIDGE PAINTING, INC.(0.05%)
STAR OPERATIONS, INC.(1.98%)
WEBBER BARRIER SERVICES, INC.(0.51%)
W. W. FOUNDATION DRILLING, LTD.(1.40%)
HIGHWAY BARRICADES AND SERVICES, LLC (0.18%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.58%)
Contract # 08123006
Totals 13828828.39 22762.10 13863980.24 99.9

CountyHIDALGO
Highway US 281
From FM 162
To FM 490
CSJ 0255-07-128
Proj ID STP 2012(793)MM
Work Type RECONST MAINLANES & ADD FRONT RDS
 
2.372 12040791.34 124432.59 9812673.16 82.0
CountyHIDALGO
Highway US 281
From FM 2812
To FM 162
CSJ 0255-07-129
Proj ID C 255-7-129
Work Type RECONST MAINLANES & ADD FRONT RDS
 
2.173 7776379.96 315551.82 5059959.48 65.0
Work Order 10-18-12
Work Began 11-05-12
Work Completed  
Time Computed 11-03-12
Contract Working Days 400
Addl Days Granted 0
Working Days Charged 456
Percent Time Used 114
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0255-07-128
STAR OPERATIONS, INC.(0.59%)
LAREDO STRIPING INC. (3.21%)
HIGHWAY BARRICADES AND SERVICES, LLC (1.30%)
WEST TEXAS RUMBLE STRIP(0.03%)
D S TEXAS ICON CONSTRUCTION, LLC (0.95%)
ANDERSON COLUMBIA CO., INC.( 27.10%)
CERTIFIED PLACERS LLC(0.19%)
PRIMATE CONSTRUCTION, INC. (0.05%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.00%)
M & M INDUSTRIAL PAINTING(0.05%)
NORTH TEXAS REBAR, LLC (0.06%)
GULF COAST CONTRACTORS, INC. (0.07%)
Contract # 08123207
Totals 19817171.30 439984.41 14872632.64 75.4

CountyKENEDY
Highway US 77
From 0.87 MI S OF LA PARRA AVE
To 0.71 MI N OF LA PARRA AVE
CSJ 0327-02-050
Proj ID NH 2012(626)
Work Type CONSTRUCT OVERPASS
 
1.578 10282198.94 0.00 10481453.33 99.9
Work Order 08-10-12
Work Began 09-10-12
Work Completed  
Time Computed 08-27-12
Contract Working Days 340
Addl Days Granted 30
Working Days Charged 360
Percent Time Used 97
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0327-02-050
HIGHWAY BARRICADES AND SERVICES, LLC (0.69%)
TEXAS DIAMOND CONSTRUCTION (1.68%)
LAREDO STRIPING INC. (1.88%)
SOIL-TECH, INC.(1.12%)
MCALLEN CONSTRUCTION, INC. ( 21.52%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (2.04%)
RIO GRANDE REBAR PLACING, LTD. (0.30%)
WEBBER BARRIER SERVICES, LLC.(0.53%)
HOUSTON SAWING & DRILLING(0.05%)
SCOTT DERR PAINTING CO, LLC(0.07%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.04%)
COWBELL TRAFFIC SERVICES, INC. (0.07%)
HURRICANE FENCE COMPANY(0.62%)
Contract # 06123223
Totals 10282198.94 0.00 10481453.33 99.9

CountyKENEDY
Highway US 77
From KLEBERG/KENEDY COUNTY LINE
To 12.298 MI S OF KLEBERG/ KENEDY CL
CSJ 0327-02-051
Proj ID NH 2014(021)
Work Type MILL & OVERLAY N.B. & S.B. ROADWAYS
 
12.298 7854465.72 68958.59 8209836.25 100.0
CountyKENEDY
Highway US 77
From 11.700 MI S OF KLEBERG/KENNEDY CL
To 12.28 MI S OF KLEBERG/KENEDY CL
CSJ 0327-03-046
Proj ID NH 2014(021)
Work Type MILL & OVERLAY N.B. & S.B. ROADWAYS
 
0.580 218933.50 0.00 206366.50 100.0
Work Order 01-06-14
Work Began 01-30-14
Work Completed 10-03-14
Time Computed 01-27-14
Contract Working Days 160
Addl Days Granted 0
Working Days Charged 137
Percent Time Used 85
Contractor(s)
TEXAS SAI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0327-02-051
A BROTHERS MILLING, LLC(1.28%)
HIGHWAY BARRICADES AND SERVICES, LLC (3.44%)
SOIL-TECH, INC.(0.28%)
WEST TEXAS RUMBLE STRIP(0.20%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (1.31%)
Contract # 09133209
Totals 8073399.22 68958.59 8416202.75 100.0

CountyWILLACY
Highway US 77
From FM 1018
To 0.3 MILES N OF FM 498
CSJ 0327-10-053
Proj ID NH 1102(173)
Work Type CONSTRUCT MAINLANES
 
3.335 11158184.54 -1027.07 10765548.91 98.8
CountyWILLACY
Highway US 77
From 0.3 MILES N OF FM 498
To FM 3168
CSJ 0327-10-054
Proj ID NH 1102(173)
Work Type CONSTRUCT OVERPASS AND MAINLANES
 
4.399 14602597.36 2827.13 13986065.95 95.7
Work Order 08-30-11
Work Began 09-09-11
Work Completed  
Time Computed 09-15-11
Contract Working Days 473
Addl Days Granted 15
Working Days Charged 582
Percent Time Used 119
Contractor(s)
LIBERTY MUTUAL INSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0327-10-053
STAR OPERATIONS, INC.(2.01%)
HIGHWAY BARRICADES AND SERVICES, LLC (2.04%)
CABCOS CONTRACTORS LLC (2.33%)
HIGHWAY TECHNOLOGIES, INC. (0.60%)
LONE STAR TRAFFIC SERVICE, INC.(0.10%)
PRIMATE CONSTRUCTION, INC. (0.06%)
HURRICANE FENCE COMPANY(1.24%)
SHINN & GREGORY, INC.(0.84%)
CERTIFIED PLACERS LLC(0.24%)
SOUTH TEXAS PAINTING COMPANY (0.15%)
EXTERIOR DESIGNS (0.98%)
GUERRA CONSTRUCTION COMPANY(0.67%)
MCALLEN CONSTRUCTION, INC. ( 16.81%)
SOIL-TECH, INC.(0.84%)
LAREDO STRIPING INC. (1.22%)
RIO GRANDE REBAR PLACING, LTD. (0.08%)
D S TEXAS ICON CONSTRUCTION, LLC (0.33%)
TEXAS CORDIA CONSTRUCTION, LLC (0.50%)
FOUR-B PAVING, INC.(0.21%)
SCOTT DERR PAINTING CO, LLC(0.05%)
Contract # 07113201
Totals 25760781.90 1800.06 24751614.86 97.1

CountyCAMERON
Highway SH 100 ETC
From 0.138 MI EAST OF US 77
To FM 803
CSJ 0331-01-040
Proj ID STP 2014(023)
Work Type SEAL COAT
 
58.978 2737444.27 1116.00 2670494.08 97.5
Work Order 01-06-14
Work Began 07-26-14
Work Completed  
Time Computed 01-22-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 50
Percent Time Used 83
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0331-01-040
INTERSTATE BARRICADES & MARKINGS, INC. ( 13.58%)
CHEROKEE SERVICES(0.22%)
Contract # 09133010
Totals 2737444.27 1116.00 2670494.08 97.5

CountyCAMERON
Highway SH 100
From IH 69E
To FM 803
CSJ 0331-01-042
Proj ID STP 2015(038)HESG
Work Type TEXTURIZE SHOULDERS
 
3.392 65580.80 0.00 0.00 0.0
CountyCAMERON
Highway SH 100
From 0.52 MI E OF FM 1847
To 3.63 MI E OF FM 1847
CSJ 0331-01-043
Proj ID STP 2015(039)HESG
Work Type TEXTURIZE SHOULDERS
 
3.076 64141.20 0.00 0.00 0.0
CountyWILLACY
Highway SH 186
From CR 465
To RM 564 + 0.9
CSJ 0433-05-024
Proj ID STP 2015(040)HESG
Work Type TEXTURIZE SHOULDERS
 
12.629 147103.86 0.00 0.00 0.0
CountyZAPATA
Highway SH 16
From JIM HOGG CL
To 20TH ST.
CSJ 0517-07-042
Proj ID STP 2015(041)HESG
Work Type TEXTURIZE SHOULDERS
 
22.280 259922.58 0.00 0.00 0.0
Work Order 10-10-14
Work Began 00-00-00
Work Completed  
Time Computed 10-26-14
Contract Working Days 85
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0331-01-042
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143019
Totals 536748.44 0.00 0.00 0.0

CountyCAMERON
Highway SH 100 ETC
From 1.5 MI WEST OF FM 510
To HARDING BLVD. (1.7 MI E OF FM 510)
CSJ 0331-02-050
Proj ID STP 2014(363)HESG
Work Type CENTERLINE TEXTURING
 
81.251 740429.05 257221.90 260721.90 35.2
Work Order 02-13-14
Work Began 00-00-00
Work Completed  
Time Computed 03-03-14
Contract Working Days 220
Addl Days Granted 0
Working Days Charged 23
Percent Time Used 10
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0331-02-050
STAR OPERATIONS, INC.(7.29%)
Contract # 01143005
Totals 740429.05 257221.90 260721.90 35.2

CountyHIDALGO
Highway FM 681
From FM 681 (N) @ FM 2221
To SH 107
CSJ 0669-01-043
Proj ID STP 2013(039)MM
Work Type WIDEN TO 4 LANE DIVIDED URBAN
 
1.784 12345193.52 251024.93 5411572.99 43.8
CountyHIDALGO
Highway FM 2221
From 0.25 MI W OF SH 364 (LA HOMA)
To .25 MI W OF MOOREFIELD RD
CSJ 0862-01-037
Proj ID STP 2013(040)MM
Work Type WIDEN TO 4 LANE DIVIDED
 
0.574 2333144.96 0.00 174575.00 7.4
CountyHIDALGO
Highway FM 2221
From 0.25 MI W OF MOOREFIELD RD
To FM 681
CSJ 0862-01-047
Proj ID STP 2013(039)MM
Work Type WIDEN TO 4 LANE DIVIDED URBAN
 
0.338 2162777.75 78188.50 301014.10 13.9
Work Order 08-19-13
Work Began 09-04-13
Work Completed  
Time Computed 09-04-13
Contract Working Days 540
Addl Days Granted 0
Working Days Charged 42
Percent Time Used 7
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0669-01-043
GO UNDERGROUND, LIMITED LIABILITY COMPANY( 20.85%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.29%)
SOIL-TECH, INC.(1.94%)
PAVEMENT MARKINGS INC. (1.01%)
VALLEY INFRASTRUCTURE, INC.( 10.14%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (2.76%)
Contract # 06133203
Totals 16841116.23 329213.43 5887162.09 34.9

CountyCAMERON
Highway SH 550
From 0.70 MI N OF FM 3248
To OLD PORT ISABEL RD
CSJ 0684-01-066
Proj ID STP 2009(662)ES
Work Type CONST TOLLED MNLNS & FRTGE ACCESS
 
1.060 8113949.40 0.00 8305236.05 100.0
CountyCAMERON
Highway SH 550
From OLD PORT ISABEL RD, ON NEW LOC
To SH 48
CSJ 3622-01-001
Proj ID STP 2009(662)ES
Work Type CONSTR TOLLED M.L. & FRT ACCESS
 
2.866 26047792.00 0.00 25877046.38 100.0
Work Order 05-13-10
Work Began 08-02-10
Work Completed 08-15-14
Time Computed 05-29-10
Contract Working Days 390
Addl Days Granted 67
Working Days Charged 655
Percent Time Used 143
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 3622-01-001
BOOTHE BROTHERS PAVING COMPANY, INC. (0.47%)
CHICO TRUCKING CO., INC. (1.68%)
STAR OPERATIONS, INC.(3.75%)
GUERRA CONSTRUCTION COMPANY(0.68%)
CERTIFIED PLACERS LLC(0.54%)
HIGHWAY TECHNOLOGIES, INC. (0.34%)
JAVALINA CONSTRUCTION SOUTH, INC.(0.03%)
LONE STAR TRAFFIC SERVICE, INC.(0.10%)
HJC FARMS, INC.(0.21%)
WEBBER BARRIER SERVICES, INC.(3.17%)
WRANGLER CONTRACTING (0.25%)
MCALLEN CONSTRUCTION, INC. ( 11.45%)
ROVAN MARINE, LLC(5.85%)
SOIL-TECH, INC.(0.23%)
S & S PAINTING (0.31%)
PRIMATE CONSTRUCTION, INC. (0.06%)
HURRICANE FENCE COMPANY(0.22%)
CORRPRO COMPANIES, INC.(0.07%)
CABCOS CONTRACTORS LLC (0.82%)
R & M CONCRETE & FENCING (0.07%)
BORING & TUNNELING COMPANY OF AMERICA, INC.(0.17%)
ROVAN, LLC (3.28%)
FOREMOST PAVING, INC.(0.36%)
EROSION PREVENTION PRODUCTS(0.26%)
TEXAS DIAMOND CONSTRUCTION (0.05%)
Contract # 03103002
Totals 34161741.40 0.00 34182282.43 100.0

CountyHIDALGO
Highway FM 88
From SH 107, SOUTH
To 0.25 MI N OF MILE 16 N
CSJ 0698-03-084
Proj ID STP 2012(699)MM
Work Type WIDEN TO 4 LANE DIVIDED
 
0.249 2681776.78 11673.42 957025.35 35.6
CountyHIDALGO
Highway FM 88
From SH 107, SOUTH
To 0.25 MI. N. OF MIE 16 N
CSJ 0698-03-086
Proj ID RW 0698-3-86
Work Type ROW ACQUISITION
 
0.249 467213.71 72321.08 489214.74 99.9
Work Order 01-03-13
Work Began 04-09-13
Work Completed  
Time Computed 01-19-13
Contract Working Days 164
Addl Days Granted 0
Working Days Charged 157
Percent Time Used 95
Contractor(s)
IOC COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0698-03-084
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (4.44%)
VALLEY STRIPING CORP.(1.43%)
Contract # 09123235
Totals 3148990.49 83994.50 1446240.09 45.9

CountyHIDALGO
Highway FM 493
From CHAMPION ST.
To US 281
CSJ 0863-01-047
Proj ID HP 2014(907)
Work Type RECONSTRUCT & ADD SHOULDERS
 
5.681 11333645.32 0.00 0.00 0.0
CountyHIDALGO
Highway FM 493
From BUSINESS 83
To CHAMPION AVE
CSJ 0863-01-053
Proj ID HP 2014(907)
Work Type OVERLAY
 
0.768 579679.56 0.00 0.00 0.0
Work Order 09-09-14
Work Began 00-00-00
Work Completed  
Time Computed 09-25-14
Contract Working Days 480
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0863-01-047
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143208
Totals 11913324.88 0.00 0.00 0.0

CountyHIDALGO
Highway FM 494
From SUNSET LANE
To COLORADO ST
CSJ 0864-01-065
Proj ID STP 2013(897)MM
Work Type SIGNAL RETIMING & ADD LANES @ US 83
 
1.710 787777.77 13149.92 788394.14 99.9
Work Order 01-06-14
Work Began 04-07-14
Work Completed  
Time Computed 01-22-14
Contract Working Days 80
Addl Days Granted 0
Working Days Charged 51
Percent Time Used 63
Contractor(s)
IOC COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0864-01-065
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. ( 11.91%)
VALLEY STRIPING CORP.( 10.98%)
Contract # 08133238
Totals 787777.77 13149.92 788394.14 99.9

CountyHIDALGO
Highway CS
From MILE 2 WEST, FROM MILE 12 NORTH
To .44 MI NORTH OF US 83
CSJ 0921-02-170
Proj ID HP 2008(128)
Work Type RECONSTRUCT & WIDEN TO 2 LN RDWY
 
4.750 4729717.44 332090.79 1413334.25 29.8
CountyHIDALGO
Highway CS
From ON MILE 2 NORTH,.44 MI N OF US 83
To US 83
CSJ 0921-02-307
Proj ID HP 2008(128)
Work Type RECONSTRUCT & WIDEN TO 2 LN RDWY
 
0.440 744320.06 0.00 101200.00 13.5
Work Order 06-26-13
Work Began 12-09-13
Work Completed  
Time Computed 07-12-13
Contract Working Days 480
Addl Days Granted 6
Working Days Charged 101
Percent Time Used 20
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-170
GO UNDERGROUND, LIMITED LIABILITY COMPANY( 12.90%)
SOIL-TECH, INC.(6.29%)
PAVEMENT MARKINGS INC. (0.92%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (1.48%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (1.68%)
Contract # 04133203
Totals 5474037.50 332090.79 1514534.25 27.6

CountyHIDALGO
Highway CS
From ON MCCOLL, ORANGEWOOD
To DICKER RD
CSJ 0921-02-171
Proj ID HP 2008(134)
Work Type CONSTR 2 LN RDWY W / 4 LA TRANS
 
3.000 4309680.38 4987.51 3671337.05 90.2
CountyHIDALGO
Highway CS
From ON MCCOLL, ORANGEWOOD
To DICKER RD
CSJ 0921-02-288
Proj ID HP 1102(318)
Work Type ROW ACQ.; UTL. ADJ.
 
3.000 849420.66 0.00 641277.75 75.4
Work Order 08-25-11
Work Began 10-11-11
Work Completed  
Time Computed 09-10-11
Contract Working Days 320
Addl Days Granted 0
Working Days Charged 518
Percent Time Used 161
Contractor(s)
CONTINENTAL CASUALTY COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-171
HIGHWAY TECHNOLOGIES, INC. (0.69%)
SOIL-TECH, INC.(1.28%)
WEBBER-BALKE FOUNDATION COMPANY, INC.(1.74%)
PAVEMENT MARKINGS INC. (0.98%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (3.99%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (3.56%)
VALLEY INFRASTRUCTURE, INC.( 33.21%)
Contract # 07113251
Totals 5159101.04 4987.51 4312614.80 87.8

CountyHIDALGO
Highway VA
From US CUSTOMS PORT OF ENTRY EXIT
To US 281
CSJ 0921-02-173
Proj ID BOR 2002(632)
Work Type CONSTRUCT BSIF
 
1.350 20116428.45 22932.43 17471345.09 87.0
Work Order 08-25-11
Work Began 10-18-11
Work Completed  
Time Computed 09-10-11
Contract Working Days 380
Addl Days Granted 115
Working Days Charged 517
Percent Time Used 104
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-173
BULLARD CONSTRUCTION, INC. ( 19.38%)
HIGHWAY TECHNOLOGIES, INC. (1.61%)
HURRICANE FENCE COMPANY(0.96%)
METTLER TOTLEDO(5.03%)
NORTH TEXAS REBAR, LLC (0.54%)
ROVAN, LLC (3.33%)
SOIL-TECH, INC.(1.21%)
STAR OPERATIONS, INC.( 19.28%)
TSI LABORATORIES SOUTH,INC.(0.04%)
RGV ALLIANCE CONSTRUCTION, LLC (0.54%)
FOREMOST PAVING, INC.(9.34%)
CONTINENTAL REFRIGERATION(1.12%)
M & A PAINTING SERVICE, INC. (0.39%)
L & G CONCRETE CONSTRUCTION, INC.(3.86%)
SOUTHERN STEEL FABRICATORS (4.27%)
CANTU"S PLUMBING (0.88%)
METRO ELECTRIC, INC. (1.81%)
ROUND ROCK INDUSTRIAL EQUIPMENT COMPANY, INC.(0.07%)
INTERTECH FLOORING (0.33%)
WEIGHT AND TEST SOLUTIONS, INC.(0.70%)
RGV ALLIANCE CONSTRUCTION, LLC (0.12%)
MCALLEN PEST CONTROL (0.03%)
THE CABINET SHOP (0.24%)
PRIME CONSTRUCTION (0.10%)
TAYLOR LIGHTNING PROTECTION(0.14%)
TAMU, DBA CONSTRUCTION SPECIALTIES (0.37%)
T & D SOLUTIONS, LTD (0.87%)
Contract # 07113207
Totals 20116428.45 22932.43 17471345.09 87.0

CountyHIDALGO
Highway CS
From CITY OF EDINBURG, EISENHOWER ELEM
To & MEMORIAL MIDDLE SCHOOL
CSJ 0921-02-258
Proj ID STP 1102(186)SRS
Work Type SIDEWALK, CROSSWALK, BIKE RACKS
 
13.043 2667755.20 5420.00 2703004.23 99.9
Work Order 11-09-12
Work Began 12-03-12
Work Completed  
Time Computed 11-25-12
Contract Working Days 240
Addl Days Granted 0
Working Days Charged 230
Percent Time Used 95
Contractor(s)
ASAGO, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-258
STAR OPERATIONS, INC.( 17.31%)
VALLEY STRIPING CORP.(3.07%)
ACE DRILLING, INC. (0.43%)
Contract # 09123221
Totals 2667755.20 5420.00 2703004.23 99.9

page 1 | page 2 | page 3