Monthly State Let Construction Report For Pharr District As Of Aug 10, 2015 Page 2 Of 4

Last Update: Monday, August 10, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyBROOKS
Highway SH 285
From FM 2191
To KLEBERG/BROOKS CL
CSJ 0102-07-044
Proj ID STP 1502(583)
Work Type REHABILITATE ROADWAY
 
4.839 12283376.69 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 359
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TEXAS SAI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0102-07-044
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08153013
Totals 12283376.69 0.00 0.00 0.0

CountyHIDALGO
Highway US 281
From FM 88
To FM 1015
CSJ 0220-01-025
Proj ID NH 2015(293)
Work Type REHAB AND WIDEN EXISTING ROADWAY
 
2.146 4739753.21 247815.79 1420486.15 29.9
Work Order 01-05-15
Work Began 03-01-15
Work Completed  
Time Computed 01-21-15
Contract Working Days 398
Addl Days Granted 0
Working Days Charged 111
Percent Time Used 27
Contractor(s)
IOC COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0220-01-025
HIGHWAY BARRICADES AND SERVICES, LLC (2.11%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (5.68%)
GULF COAST CONTRACTORS, INC. (0.60%)
Contract # 11143213
Totals 4739753.21 247815.79 1420486.15 29.9

CountyHIDALGO
Highway US 281
From FM 907
To FM 493
CSJ 0220-01-029
Proj ID C 220-1-29
Work Type REHAB & WIDEN PAVEMENT (SUPER 2)
 
5.024 6266718.83 0.00 6249417.76 99.9
CountyHIDALGO
Highway US 281
From FM 493
To FM 88
CSJ 0220-01-030
Proj ID C 220-1-30
Work Type REHAB & WIDEN PAVEMENT (SUPER 2)
 
4.353 4903240.81 0.00 4889179.09 99.7
Work Order 05-13-11
Work Began 06-07-11
Work Completed  
Time Computed 05-29-11
Contract Working Days 400
Addl Days Granted 0
Working Days Charged 543
Percent Time Used 135
Contractor(s)
LIBERTY MUTUAL INSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0220-01-029
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (1.60%)
PAVEMENT MARKINGS INC. (2.26%)
HIGHWAY TECHNOLOGIES, INC. (0.25%)
TREV-CORT TRUCKING INC ( 11.96%)
EXTERIOR DESIGNS (0.92%)
CABCOS CONTRACTORS LLC (3.69%)
LONE STAR TRAFFIC SERVICE, INC.(0.37%)
JAVELINA CONSTRUCTION SOUTH, INC.(1.03%)
DUSTROL, INC.(0.20%)
LAREDO STRIPING INC. (0.24%)
SOIL-TECH, INC.(0.65%)
VALLEY INFRASTRUCTURE, INC.(2.13%)
Contract # 04113210
Totals 11169959.64 0.00 11138596.85 99.9

CountyCAMERON
Highway US 281
From 0.24 MI E OF FM 506
To .099 MI E OF HIDALGO/CAMERON CL
CSJ 0220-03-027
Proj ID STP 2015(380)
Work Type REHABILITATE & WIDEN ROADWAY
 
2.789 5229348.79 2500.00 402542.00 7.6
Work Order 01-28-15
Work Began 03-04-15
Work Completed  
Time Computed 02-13-15
Contract Working Days 380
Addl Days Granted 0
Working Days Charged 50
Percent Time Used 13
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0220-03-027
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (1.02%)
LAREDO STRIPING INC. (3.35%)
PAVEMENT MARKINGS INC. (2.49%)
SOIL-TECH, INC.(1.38%)
VALLEY INFRASTRUCTURE, INC.(8.38%)
Contract # 12143006
Totals 5229348.79 2500.00 402542.00 7.6

CountyCAMERON
Highway US 281
From 0.05 MI W OF FM 1479
To 0.24 MI EAST OF FM 506
CSJ 0220-03-028
Proj ID STP 2015(037)
Work Type REHAB & WIDEN EXIST ROADWAY SUPER 2
 
3.863 7709997.35 502538.13 1117724.30 14.4
Work Order 11-25-14
Work Began 03-23-15
Work Completed  
Time Computed 12-11-14
Contract Working Days 400
Addl Days Granted 0
Working Days Charged 40
Percent Time Used 10
Contractor(s)
ASAGO, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0220-03-028
HIGHWAY BARRICADES AND SERVICES, LLC (1.78%)
GO UNDERGROUND, LIMITED LIABILITY COMPANY(6.01%)
Contract # 09143009
Totals 7709997.35 502538.13 1117724.30 14.4

CountyBROOKS
Highway US 281
From BUS 281 NORTH SIDE
To BROOKS COUNTY LINE
CSJ 0255-03-026
Proj ID HP 2009(663)ES
Work Type GR., STRS., AND SURF
 
4.133 40039527.43 0.00 44078451.46 99.9
CountyBROOKS
Highway US 281
From SH 285
To BROOKS COUNTY LINE
CSJ 0255-03-031
Proj ID RW 255-3-31
Work Type ACQUISITION, UTILITIES AND RELOCATI
 
0.001 1792061.65 0.00 2122790.25 99.9
CountyBROOKS
Highway US 281
From BUS 281 NORTH SIDE
To BUS 281 SOUTH SIDE
CSJ 0255-14-001
Proj ID STP 2009(664)ES
Work Type GR., STRS., AND SURF
 
2.062 25860723.89 0.00 25741877.43 99.5
Work Order 07-14-09
Work Began 08-18-09
Work Completed  
Time Computed 07-30-09
Contract Working Days 720
Addl Days Granted 167
Working Days Charged 1,211
Percent Time Used 136
Contractor(s)
ZURICH AMERICAN INSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0255-03-026
HIGHWAY TECHNOLOGIES, INC. (0.46%)
LEAL CONSTRUCTION, INC.(3.11%)
MENDEZ EXCAVATION(0.27%)
RHYNER CONSTRUCTION SERVICES, INC. (0.15%)
SUNBELT EXPRESS SERVICES, INC. (0.77%)
EXTERIOR DESIGNS (0.76%)
W. W. FOUNDATION DRILLING, LTD.(2.75%)
LAREDO STRIPING INC. (0.64%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.04%)
CHICO TRUCKING CO., INC. (1.38%)
J & P TRUCKING AND HAULING (6.05%)
CABCOS CONTRACTORS LLC (1.64%)
STAR OPERATIONS, INC.(3.55%)
CRAWFORD YANT(0.16%)
CERTIFIED PLACERS LLC(0.47%)
RGV ALLIANCE CONSTRUCTION, L.L.C.(1.28%)
SOUTH TEXAS INDUSTRIAL COATINGS, L.L.C.(0.05%)
MORRIS CONSTRUCTION, INC.(0.31%)
CORTEZ TRUCKING TRANSPORT(1.82%)
DOUG'S DRIP IRRIGATION (0.16%)
G & E ESCOBEDO CONSTRUCTION, INC.(0.02%)
ADVANCED PUMPING CONCEPTS, INC.(0.08%)
JAVELINA CONSTRUCTION SOUTH, INC.(0.15%)
LAND SOLUTIONS CONSTRUCTION, LLC (0.14%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.25%)
D S TEXAS ICON CONSTRUCTION, LLC (0.01%)
DUSTROL, INC.(0.07%)
TEXAS CORDIA CONSTRUCTION, LLC (2.55%)
PIERCE CONSTRUCTION AND CONTRACT HAULING (1.53%)
GUERRA CONSTRUCTION COMPANY(0.30%)
HIGHWAY BARRICADES AND SERVICES, LLC (0.30%)
D & C CONCRETE CUTTING, INC. (0.00%)
TEXAS CURB CUT, INC.(HUB)(0.01%)
HURRICANE FENCE COMPANY(0.28%)
Contract # 05093023
Totals 67692312.97 0.00 71943119.14 99.9

CountyBROOKS
Highway US 281
From 448 FT E OF BUS 281
To US 281
CSJ 0255-04-085
Proj ID STP 2015(579)
Work Type DRAINAGE IMPROVEMENTS
 
0.305 1269572.61 0.00 16110.88 1.2
Work Order 03-26-15
Work Began 00-00-00
Work Completed  
Time Computed 04-26-15
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CLORE CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0255-04-085
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02153231
Totals 1269572.61 0.00 16110.88 1.2

CountyBROOKS
Highway US 281
From US 281 @ FM 755
To .
CSJ 0255-05-034
Proj ID C 255-5-34
Work Type CONSTRUCT OVERPASS
 
1.373 13828828.39 0.00 14289526.18 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-24-12
Work Began 01-24-13
Work Completed  
Time Computed 11-09-12
Contract Working Days 238
Addl Days Granted 0
Working Days Charged 454
Percent Time Used 190
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0255-05-034
CABCOS CONTRACTORS LLC (5.36%)
CERTIFIED PLACERS LLC(0.24%)
COWBELL TRAFFIC SERVICES, INC. (0.04%)
D S TEXAS ICON CONSTRUCTION, LLC (0.23%)
FOREMOST PAVING, INC.( 25.22%)
GUERRA CONSTRUCTION COMPANY(0.85%)
HIGHWAY TECHNOLOGIES, INC. (0.82%)
PRIMATE CONSTRUCTION, INC. (0.11%)
S & S BRIDGE PAINTING, INC.(0.05%)
STAR OPERATIONS, INC.(1.98%)
WEBBER BARRIER SERVICES, INC.(0.51%)
W. W. FOUNDATION DRILLING, LTD.(1.40%)
HIGHWAY BARRICADES AND SERVICES, LLC (0.18%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.58%)
TEXAS HIGHWAY SYSTEMS, INC.(0.06%)
Contract # 08123006
Totals 13828828.39 0.00 14289526.18 99.9

CountyHIDALGO
Highway US 281
From FM 162
To FM 490
CSJ 0255-07-128
Proj ID STP 2012(793)MM
Work Type RECONST MAINLANES & ADD FRONT RDS
 
2.372 12040791.34 45702.36 11495861.78 96.9
CountyHIDALGO
Highway US 281
From FM 2812
To FM 162
CSJ 0255-07-129
Proj ID C 255-7-129
Work Type RECONST MAINLANES & ADD FRONT RDS
 
2.173 7776379.96 118142.70 7120517.26 91.5
Work Order 10-18-12
Work Began 01-15-13
Work Completed  
Time Computed 11-03-12
Contract Working Days 400
Addl Days Granted 0
Working Days Charged 541
Percent Time Used 135
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0255-07-128
STAR OPERATIONS, INC.(0.59%)
LAREDO STRIPING INC. (3.21%)
HIGHWAY BARRICADES AND SERVICES, LLC (1.30%)
WEST TEXAS RUMBLE STRIP(0.03%)
D S TEXAS ICON CONSTRUCTION, LLC (0.95%)
ANDERSON COLUMBIA CO., INC.( 27.10%)
CERTIFIED PLACERS LLC(0.19%)
PRIMATE CONSTRUCTION, INC. (0.05%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.00%)
M & M INDUSTRIAL PAINTING(0.05%)
NORTH TEXAS REBAR, LLC (0.06%)
GULF COAST CONTRACTORS, INC. (0.07%)
Contract # 08123207
Totals 19817171.30 163845.06 18616379.04 94.8

CountyWILLACY
Highway US 77
From FM 1018
To 0.3 MILES N OF FM 498
CSJ 0327-10-053
Proj ID NH 1102(173)
Work Type CONSTRUCT MAINLANES
 
3.335 11158184.54 2800.00 11004273.31 99.9
CountyWILLACY
Highway US 77
From 0.3 MILES N OF FM 498
To FM 3168
CSJ 0327-10-054
Proj ID NH 1102(173)
Work Type CONSTRUCT OVERPASS AND MAINLANES
 
4.399 14602597.36 0.00 14002153.63 95.8
Work Order 08-30-11
Work Began 09-09-11
Work Completed  
Time Computed 09-15-11
Contract Working Days 473
Addl Days Granted 49
Working Days Charged 601
Percent Time Used 115
Contractor(s)
LIBERTY MUTUAL INSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0327-10-053
STAR OPERATIONS, INC.(2.01%)
HIGHWAY BARRICADES AND SERVICES, LLC (2.04%)
CABCOS CONTRACTORS LLC (2.33%)
HIGHWAY TECHNOLOGIES, INC. (0.60%)
LONE STAR TRAFFIC SERVICE, INC.(0.10%)
PRIMATE CONSTRUCTION, INC. (0.06%)
HURRICANE FENCE COMPANY(1.24%)
SHINN & GREGORY, INC.(0.84%)
CERTIFIED PLACERS LLC(0.24%)
SOUTH TEXAS PAINTING COMPANY (0.15%)
EXTERIOR DESIGNS (0.98%)
GUERRA CONSTRUCTION COMPANY(0.67%)
MCALLEN CONSTRUCTION, INC. ( 16.81%)
SOIL-TECH, INC.(0.84%)
LAREDO STRIPING INC. (1.22%)
RIO GRANDE REBAR PLACING, LTD. (0.08%)
D S TEXAS ICON CONSTRUCTION, LLC (0.33%)
TEXAS CORDIA CONSTRUCTION, LLC (0.50%)
FOUR-B PAVING, INC.(0.21%)
SCOTT DERR PAINTING CO, LLC(0.05%)
Contract # 07113201
Totals 25760781.90 2800.00 25006426.94 97.9

CountyCAMERON
Highway SH 100
From FM 803
To FM 1575
CSJ 0331-01-041
Proj ID STP 1502(467)
Work Type OVERLAY
 
1.643 639879.46 0.00 0.00 0.0
CountyCAMERON
Highway SS 206
From ON HARRISON AVE, FROM COMMERCE ST.
To BUS 77
CSJ 1425-03-056
Proj ID NH 1502(466)
Work Type MILL & OVERLAY
 
1.004 264339.02 0.00 0.00 0.0
CountyCAMERON
Highway SS 206
From ON TYLER AVE., FROM COMMERCE ST.
To BUS 77
CSJ 1425-03-057
Proj ID NH 1502(466)
Work Type MILL & OVERLAY
 
0.956 234898.11 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 39
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
IOC COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0331-01-041
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07153213
Totals 1139116.59 0.00 0.00 0.0

CountyCAMERON
Highway SH 100
From IH 69E
To FM 803
CSJ 0331-01-042
Proj ID STP 2015(038)HESG
Work Type TEXTURIZE SHOULDERS
 
3.392 65580.80 457.32 62952.80 95.9
CountyCAMERON
Highway SH 100
From 0.52 MI E OF FM 1847
To 3.63 MI E OF FM 1847
CSJ 0331-01-043
Proj ID STP 2015(039)HESG
Work Type TEXTURIZE SHOULDERS
 
3.076 64141.20 -493.40 63342.20 98.7
CountyWILLACY
Highway SH 186
From CR 465
To RM 564 + 0.9
CSJ 0433-05-024
Proj ID STP 2015(040)HESG
Work Type TEXTURIZE SHOULDERS
 
12.629 147103.86 145.20 124199.61 84.4
CountyZAPATA
Highway SH 16
From JIM HOGG CL
To 20TH ST.
CSJ 0517-07-042
Proj ID STP 2015(041)HESG
Work Type TEXTURIZE SHOULDERS
 
22.280 259922.58 0.00 259138.62 99.6
Work Order 10-10-14
Work Began 12-05-14
Work Completed  
Time Computed 10-27-14
Contract Working Days 85
Addl Days Granted 0
Working Days Charged 63
Percent Time Used 74
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0331-01-042
BRYDL CONTRACTING, INC.( 13.55%)
Contract # 09143019
Totals 536748.44 109.12 509633.23 94.9

CountyCAMERON
Highway SH 100 ETC
From 1.5 MI WEST OF FM 510
To HARDING BLVD. (1.7 MI E OF FM 510)
CSJ 0331-02-050
Proj ID STP 2014(363)HESG
Work Type CENTERLINE TEXTURING
 
81.251 740429.05 131.13 725227.29 97.9
Work Order 02-13-14
Work Began 09-26-14
Work Completed  
Time Computed 03-03-14
Contract Working Days 220
Addl Days Granted 0
Working Days Charged 97
Percent Time Used 44
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0331-02-050
STAR OPERATIONS, INC.(7.29%)
BRYDL CONTRACTING, INC.( 31.07%)
Contract # 01143005
Totals 740429.05 131.13 725227.29 97.9

CountyHIDALGO
Highway SH 107
From BUS 281
To US 281
CSJ 0342-01-087
Proj ID STP 2014(254)
Work Type OVERLAY
 
0.862 531025.62 309114.30 309114.30 58.2
CountyHIDALGO
Highway SH 107
From RAIL ROAD TRACKS
To US 281 SQUARE
CSJ 0528-01-107
Proj ID STP 2014(254)
Work Type OVERLAY
 
0.303 135280.47 0.00 0.00 0.0
CountyHIDALGO
Highway FM 2220
From US 83
To BUS 83
CSJ 2094-01-053
Proj ID STP 2014(254)
Work Type OVERLAY
 
0.923 403673.46 0.00 0.00 0.0
CountyHIDALGO
Highway FM 2220
From BUS 83
To FM 1924
CSJ 2094-01-054
Proj ID STP 2014(254)
Work Type OVERLAY
 
2.882 1397798.22 0.00 0.00 0.0
Work Order 02-24-15
Work Began 00-00-00
Work Completed  
Time Computed 03-27-15
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
IOC COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0342-01-087
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (4.73%)
HIGHWAY BARRICADES AND SERVICES, LLC (7.22%)
Contract # 01153213
Totals 2467777.77 309114.30 309114.30 12.5

CountyCAMERON
Highway FM 106
From @ RIO HONDO LIFT BRIDGE
To .
CSJ 0630-02-041
Proj ID BR 1502(468)
Work Type BRIDGE REHABILITATION
 
0.100 12406043.30 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 651
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
PCL CIVIL CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0630-02-041
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07153019
Totals 12406043.30 0.00 0.00 0.0

CountyHIDALGO
Highway FM 681
From FM 681 (N) @ FM 2221
To SH 107
CSJ 0669-01-043
Proj ID STP 2013(039)MM
Work Type WIDEN TO 4 LANE DIVIDED URBAN
 
1.784 12345193.52 152164.50 6096641.19 49.3
CountyHIDALGO
Highway FM 2221
From 0.25 MI W OF SH 364 (LA HOMA)
To .25 MI W OF MOOREFIELD RD
CSJ 0862-01-037
Proj ID STP 2013(040)MM
Work Type WIDEN TO 4 LANE DIVIDED
 
0.574 2333144.96 0.00 210725.00 9.0
CountyHIDALGO
Highway FM 2221
From 0.25 MI W OF MOOREFIELD RD
To FM 681
CSJ 0862-01-047
Proj ID STP 2013(039)MM
Work Type WIDEN TO 4 LANE DIVIDED URBAN
 
0.338 2162777.75 0.00 423938.34 19.6
Work Order 08-19-13
Work Began 09-04-13
Work Completed  
Time Computed 09-04-13
Contract Working Days 540
Addl Days Granted 0
Working Days Charged 42
Percent Time Used 7
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0669-01-043
GO UNDERGROUND, LIMITED LIABILITY COMPANY( 20.85%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.29%)
SOIL-TECH, INC.(1.94%)
PAVEMENT MARKINGS INC. (1.01%)
VALLEY INFRASTRUCTURE, INC.( 10.14%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (2.76%)
Contract # 06133203
Totals 16841116.23 152164.50 6731304.53 39.9

CountyHIDALGO
Highway FM 88
From SH 107, SOUTH
To 0.25 MI N OF MILE 16 N
CSJ 0698-03-084
Proj ID STP 2012(699)MM
Work Type WIDEN TO 4 LANE DIVIDED
 
0.249 2681776.78 7677.04 2066808.58 81.5
CountyHIDALGO
Highway FM 88
From SH 107, SOUTH
To 0.25 MI. N. OF MIE 16 N
CSJ 0698-03-086
Proj ID RW 0698-3-86
Work Type ROW ACQUISITION
 
0.249 467213.71 0.00 581195.41 99.9
Work Order 01-03-13
Work Began 04-09-13
Work Completed  
Time Computed 01-19-13
Contract Working Days 164
Addl Days Granted 0
Working Days Charged 288
Percent Time Used 175
Contractor(s)
IOC COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0698-03-084
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (4.44%)
VALLEY STRIPING CORP.(1.43%)
Contract # 09123235
Totals 3148990.49 7677.04 2648003.99 87.9

CountyHIDALGO
Highway FM 493
From CHAMPION ST.
To US 281
CSJ 0863-01-047
Proj ID HP 2014(907)
Work Type RECONSTRUCT & ADD SHOULDERS
 
5.681 11333645.32 678400.00 797086.89 7.0
CountyHIDALGO
Highway FM 493
From BUSINESS 83
To CHAMPION AVE
CSJ 0863-01-053
Proj ID HP 2014(907)
Work Type OVERLAY
 
0.768 579679.56 0.00 0.00 0.0
Work Order 09-09-14
Work Began 07-13-15
Work Completed  
Time Computed 09-25-14
Contract Working Days 480
Addl Days Granted 0
Working Days Charged 46
Percent Time Used 9
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0863-01-047
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.32%)
PAVEMENT MARKINGS INC. (1.32%)
LAREDO STRIPING INC. (1.35%)
SOIL-TECH, INC.(4.05%)
Contract # 07143208
Totals 11913324.88 678400.00 797086.89 6.6

CountyHIDALGO
Highway CS
From MILE 2 WEST, FROM MILE 12 NORTH
To .44 MI NORTH OF US 83
CSJ 0921-02-170
Proj ID HP 2008(128)
Work Type RECONSTRUCT & WIDEN TO 2 LN RDWY
 
4.750 4729717.44 167136.74 2832298.89 59.8
CountyHIDALGO
Highway CS
From ON MILE 2 NORTH,.44 MI N OF US 83
To US 83
CSJ 0921-02-307
Proj ID HP 2008(128)
Work Type RECONSTRUCT & WIDEN TO 2 LN RDWY
 
0.440 744320.06 0.00 155950.00 20.9
Work Order 06-26-13
Work Began 12-16-13
Work Completed  
Time Computed 07-12-13
Contract Working Days 480
Addl Days Granted 6
Working Days Charged 252
Percent Time Used 51
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-170
GO UNDERGROUND, LIMITED LIABILITY COMPANY( 12.90%)
SOIL-TECH, INC.(6.29%)
PAVEMENT MARKINGS INC. (0.92%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (1.48%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (1.68%)
Contract # 04133203
Totals 5474037.50 167136.74 2988248.89 54.5

CountyHIDALGO
Highway CS
From ON MCCOLL, ORANGEWOOD
To DICKER RD
CSJ 0921-02-171
Proj ID HP 2008(134)
Work Type CONSTR 2 LN RDWY W / 4 LA TRANS
 
3.000 4309680.38 0.00 3873911.59 94.9
CountyHIDALGO
Highway CS
From ON MCCOLL, ORANGEWOOD
To DICKER RD
CSJ 0921-02-288
Proj ID HP 1102(318)
Work Type ROW ACQ.; UTL. ADJ.
 
3.000 849420.66 0.00 779870.87 91.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-25-11
Work Began 10-11-11
Work Completed  
Time Computed 09-10-11
Contract Working Days 320
Addl Days Granted 0
Working Days Charged 518
Percent Time Used 161
Contractor(s)
CONTINENTAL CASUALTY COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-171
HIGHWAY TECHNOLOGIES, INC. (0.69%)
SOIL-TECH, INC.(1.28%)
WEBBER-BALKE FOUNDATION COMPANY, INC.(1.74%)
PAVEMENT MARKINGS INC. (0.98%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (3.99%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (3.56%)
VALLEY INFRASTRUCTURE, INC.( 33.21%)
Contract # 07113251
Totals 5159101.04 0.00 4653782.46 94.4

page 1 | page 2 | page 3 | page 4