Monthly State Let Construction Report For Pharr District As Of May 10, 2016 Page 2 Of 4

Last Update: Tuesday, May 10, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyBROOKS
Highway SH 285
From FM 2191
To KLEBERG/BROOKS CL
CSJ 0102-07-044
Proj ID STP 1502(583)
Work Type REHABILITATE ROADWAY
 
4.839 12283376.69 419637.15 2011035.90 16.3
Work Order 11-10-15
Work Began 01-28-16
Work Completed  
Time Computed 12-30-15
Contract Working Days 359
Addl Days Granted 0
Working Days Charged 63
Percent Time Used 17
Contractor(s)
TEXAS SAI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0102-07-044
HIGHWAY BARRICADES AND SERVICES, LLC (0.49%)
WEST TEXAS RUMBLE STRIP(0.03%)
HUDSON, INC. (1.01%)
PAVEMENT MARKINGS INC. (1.18%)
J & P TRUCKING AND HAULING (4.67%)
CEDOSCA CONSTRUCTION, LLC(2.23%)
Contract # 08153013
Totals 12283376.69 419637.15 2011035.90 16.3

CountyHIDALGO
Highway US 281
From FM 88
To FM 1015
CSJ 0220-01-025
Proj ID NH 2015(293)
Work Type REHAB AND WIDEN EXISTING ROADWAY
 
2.146 4739753.21 320677.33 3137916.01 66.2
Work Order 01-05-15
Work Began 03-01-15
Work Completed  
Time Computed 01-21-15
Contract Working Days 398
Addl Days Granted 0
Working Days Charged 301
Percent Time Used 75
Contractor(s)
IOC COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0220-01-025
HIGHWAY BARRICADES AND SERVICES, LLC (2.11%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (5.68%)
GULF COAST CONTRACTORS, INC. (0.60%)
Contract # 11143213
Totals 4739753.21 320677.33 3137916.01 66.2

CountyCAMERON
Highway US 281
From 0.24 MI E OF FM 506
To .099 MI E OF HIDALGO/CAMERON CL
CSJ 0220-03-027
Proj ID STP 2015(380)
Work Type REHABILITATE & WIDEN ROADWAY
 
2.789 5229348.79 415602.76 2689096.49 51.4
Work Order 01-28-15
Work Began 03-04-15
Work Completed  
Time Computed 02-13-15
Contract Working Days 380
Addl Days Granted 0
Working Days Charged 195
Percent Time Used 51
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0220-03-027
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (1.02%)
LAREDO STRIPING INC. (3.35%)
PAVEMENT MARKINGS INC. (2.49%)
SOIL-TECH, INC.(1.38%)
VALLEY INFRASTRUCTURE, INC.(8.38%)
Contract # 12143006
Totals 5229348.79 415602.76 2689096.49 51.4

CountyCAMERON
Highway US 281
From 0.05 MI W OF FM 1479
To 0.24 MI EAST OF FM 506
CSJ 0220-03-028
Proj ID STP 2015(037)
Work Type REHAB & WIDEN EXIST ROADWAY SUPER 2
 
3.863 7709997.35 288207.71 3236207.11 41.9
Work Order 11-25-14
Work Began 03-23-15
Work Completed  
Time Computed 03-23-15
Contract Working Days 400
Addl Days Granted 0
Working Days Charged 227
Percent Time Used 56
Contractor(s)
ASAGO, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0220-03-028
HIGHWAY BARRICADES AND SERVICES, LLC (1.78%)
GO UNDERGROUND, LIMITED LIABILITY COMPANY(6.01%)
Contract # 09143009
Totals 7709997.35 288207.71 3236207.11 41.9

CountyCAMERON
Highway US 281
From FM 1421
To FM 3248
CSJ 0220-04-035
Proj ID STP 2016(428)
Work Type CONSTRUCT RURAL 4 LANE
 
5.428 12496309.81 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-31-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 460
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0220-04-035
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01163044
Totals 12496309.81 0.00 0.00 0.0

CountyBROOKS
Highway US 281
From 448 FT E OF BUS 281
To US 281
CSJ 0255-04-085
Proj ID STP 2015(579)
Work Type DRAINAGE IMPROVEMENTS
 
0.305 1269572.61 0.00 401040.46 31.5
Work Order 03-26-15
Work Began 02-01-16
Work Completed  
Time Computed 04-26-15
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 10
Percent Time Used 11
Contractor(s)
CLORE CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0255-04-085
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02153231
Totals 1269572.61 0.00 401040.46 31.5

CountyBROOKS
Highway US 281
From US 281 @ FM 755
To .
CSJ 0255-05-034
Proj ID C 255-5-34
Work Type CONSTRUCT OVERPASS
 
1.373 13828828.39 0.00 14647326.18 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-24-12
Work Began 01-24-13
Work Completed  
Time Computed 11-09-12
Contract Working Days 238
Addl Days Granted 116
Working Days Charged 354
Percent Time Used 100
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0255-05-034
CABCOS CONTRACTORS LLC (5.36%)
CERTIFIED PLACERS LLC(0.24%)
COWBELL TRAFFIC SERVICES, INC. (0.04%)
D S TEXAS ICON CONSTRUCTION, LLC (0.23%)
FOREMOST PAVING, INC.( 25.22%)
GUERRA CONSTRUCTION COMPANY(0.85%)
HIGHWAY TECHNOLOGIES, INC. (0.82%)
PRIMATE CONSTRUCTION, INC. (0.11%)
S & S BRIDGE PAINTING, INC.(0.05%)
STAR OPERATIONS, INC.(1.98%)
WEBBER BARRIER SERVICES, INC.(0.51%)
W. W. FOUNDATION DRILLING, LTD.(1.40%)
HIGHWAY BARRICADES AND SERVICES, LLC (0.18%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.58%)
TEXAS HIGHWAY SYSTEMS, INC.(0.06%)
Contract # 08123006
Totals 13828828.39 0.00 14647326.18 99.9

CountyHIDALGO
Highway US 281
From 0.315 MI N OF SH 186
To BROOKS/HIDALGO C.L.
CSJ 0255-06-065
Proj ID NH 1502(262)
Work Type SMA / OVERLAY (NB & SB LANES)
 
15.520 16635027.86 0.00 0.00 0.0
CountyHIDALGO
Highway US 281
From SH 186
To .315 MI N OF SH 186
CSJ 0255-07-132
Proj ID NH 1502(262)
Work Type SMA / OVERLAY (NB & SB LANES)
 
0.315 261169.91 0.00 0.00 0.0
Work Order 11-24-15
Work Began 00-00-00
Work Completed  
Time Computed 12-24-15
Contract Working Days 280
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TEXAS SAI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0255-06-065
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10153029
Totals 16896197.77 0.00 0.00 0.0

CountyHIDALGO
Highway US 281
From FM 162
To FM 490
CSJ 0255-07-128
Proj ID STP 2012(793)MM
Work Type RECONST MAINLANES & ADD FRONT RDS
 
2.372 12040791.34 0.00 11593898.63 97.7
CountyHIDALGO
Highway US 281
From FM 2812
To FM 162
CSJ 0255-07-129
Proj ID C 255-7-129
Work Type RECONST MAINLANES & ADD FRONT RDS
 
2.173 7776379.96 3533.00 7392438.01 95.0
Work Order 10-18-12
Work Began 01-15-13
Work Completed  
Time Computed 11-03-12
Contract Working Days 400
Addl Days Granted 0
Working Days Charged 541
Percent Time Used 135
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0255-07-128
STAR OPERATIONS, INC.(0.59%)
LAREDO STRIPING INC. (3.21%)
HIGHWAY BARRICADES AND SERVICES, LLC (1.30%)
WEST TEXAS RUMBLE STRIP(0.03%)
D S TEXAS ICON CONSTRUCTION, LLC (0.95%)
ANDERSON COLUMBIA CO., INC.( 27.10%)
CERTIFIED PLACERS LLC(0.19%)
PRIMATE CONSTRUCTION, INC. (0.05%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.00%)
M & M INDUSTRIAL PAINTING(0.05%)
NORTH TEXAS REBAR, LLC (0.06%)
GULF COAST CONTRACTORS, INC. (0.07%)
Contract # 08123207
Totals 19817171.30 3533.00 18986336.64 96.7

CountyWILLACY
Highway US 77
From FM 1018
To 0.3 MILES N OF FM 498
CSJ 0327-10-053
Proj ID NH 1102(173)
Work Type CONSTRUCT MAINLANES
 
3.335 11158184.54 1811133.91 12815407.22 99.9
CountyWILLACY
Highway US 77
From 0.3 MILES N OF FM 498
To FM 3168
CSJ 0327-10-054
Proj ID NH 1102(173)
Work Type CONSTRUCT OVERPASS AND MAINLANES
 
4.399 14602597.36 0.00 14002153.63 95.8
Work Order 08-30-11
Work Began 09-09-11
Work Completed  
Time Computed 09-15-11
Contract Working Days 473
Addl Days Granted 128
Working Days Charged 601
Percent Time Used 100
Contractor(s)
LIBERTY MUTUAL INSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0327-10-053
STAR OPERATIONS, INC.(2.01%)
HIGHWAY BARRICADES AND SERVICES, LLC (2.04%)
CABCOS CONTRACTORS LLC (2.33%)
HIGHWAY TECHNOLOGIES, INC. (0.60%)
LONE STAR TRAFFIC SERVICE, INC.(0.10%)
PRIMATE CONSTRUCTION, INC. (0.06%)
HURRICANE FENCE COMPANY(1.24%)
SHINN & GREGORY, INC.(0.84%)
CERTIFIED PLACERS LLC(0.24%)
SOUTH TEXAS PAINTING COMPANY (0.15%)
EXTERIOR DESIGNS (0.98%)
GUERRA CONSTRUCTION COMPANY(0.67%)
MCALLEN CONSTRUCTION, INC. ( 16.81%)
SOIL-TECH, INC.(0.84%)
LAREDO STRIPING INC. (1.22%)
RIO GRANDE REBAR PLACING, LTD. (0.08%)
D S TEXAS ICON CONSTRUCTION, LLC (0.33%)
TEXAS CORDIA CONSTRUCTION, LLC (0.50%)
FOUR-B PAVING, INC.(0.21%)
SCOTT DERR PAINTING CO, LLC(0.05%)
Contract # 07113201
Totals 25760781.90 1811133.91 26817560.85 99.9

CountyCAMERON
Highway SH 100
From FM 803
To FM 1575
CSJ 0331-01-041
Proj ID STP 1502(467)
Work Type OVERLAY
 
1.643 639879.46 33766.71 659589.97 99.9
CountyCAMERON
Highway SS 206
From ON HARRISON AVE, FROM COMMERCE ST.
To BUS 77
CSJ 1425-03-056
Proj ID NH 1502(466)
Work Type MILL & OVERLAY
 
1.004 264339.02 12034.31 300195.48 99.9
CountyCAMERON
Highway SS 206
From ON TYLER AVE., FROM COMMERCE ST.
To BUS 77
CSJ 1425-03-057
Proj ID NH 1502(466)
Work Type MILL & OVERLAY
 
0.956 234898.11 6639.59 250089.98 99.9
Work Order 08-13-15
Work Began 00-00-00
Work Completed  
Time Computed 09-13-15
Contract Working Days 39
Addl Days Granted 0
Working Days Charged 36
Percent Time Used 92
Contractor(s)
IOC COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0331-01-041
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.66%)
PAVEMENT MARKINGS INC. (4.98%)
Contract # 07153213
Totals 1139116.59 52440.61 1209875.43 99.9

CountyCAMERON
Highway SH 100
From 4.0 EAST OF FM 1847
To 6.27 MI EAST OF FM 1847
CSJ 0331-01-044
Proj ID NH 1502(584)
Work Type INSTALL WILDLIFE CROSSINGS
 
2.253 2561306.50 0.00 0.00 0.0
CountyCAMERON
Highway SH 100
From 6.27 MI EAST OF FM 1847
To 1.75 MILES WEST OF FM 510
CSJ 0331-02-052
Proj ID NH 1502(584)
Work Type INSTALL WILDLIFE CROSSINGS
 
4.818 3778680.75 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 340
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0331-01-044
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03163031
Totals 6339987.25 0.00 0.00 0.0

CountyHIDALGO
Highway SH 107
From BUS 281
To US 281
CSJ 0342-01-087
Proj ID STP 2014(254)
Work Type OVERLAY
 
0.862 531025.62 135.36 492884.15 95.7
CountyHIDALGO
Highway SH 107
From RAIL ROAD TRACKS
To US 281 SQUARE
CSJ 0528-01-107
Proj ID STP 2014(254)
Work Type OVERLAY
 
0.303 135280.47 0.00 144433.31 99.9
CountyHIDALGO
Highway FM 2220
From US 83
To BUS 83
CSJ 2094-01-053
Proj ID STP 2014(254)
Work Type OVERLAY
 
0.923 403673.46 13004.06 402870.02 99.8
CountyHIDALGO
Highway FM 2220
From BUS 83
To FM 1924
CSJ 2094-01-054
Proj ID STP 2014(254)
Work Type OVERLAY
 
2.882 1397798.22 1641.44 1348919.00 96.5
Work Order 02-24-15
Work Began 09-09-15
Work Completed  
Time Computed 03-27-15
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 80
Percent Time Used 133
Contractor(s)
IOC COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0342-01-087
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (4.73%)
HIGHWAY BARRICADES AND SERVICES, LLC (7.22%)
Contract # 01153213
Totals 2467777.77 14780.86 2389106.48 97.4

CountyHIDALGO
Highway SH 107
From FLOODWAY
To FM 1015
CSJ 0342-02-049
Proj ID STP 2016(059)
Work Type REHAB EXISTING ROADWAY
 
2.609 2525668.22 0.00 2370522.53 93.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-13-15
Work Began 01-04-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 117
Addl Days Granted 0
Working Days Charged 84
Percent Time Used 71
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0342-02-049
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (1.36%)
SOIL-TECH, INC.(0.81%)
VALLEY INFRASTRUCTURE, INC.(1.06%)
PAVEMENT MARKINGS INC. (4.61%)
HIGHWAY BARRICADES AND SERVICES, LLC (2.25%)
Contract # 09153022
Totals 2525668.22 0.00 2370522.53 93.8

CountyHIDALGO
Highway SH 107
From FM 2993
To 0.303 MI WEST OF GLASSCOCK RD.
CSJ 0528-01-100
Proj ID STP 2016(429)
Work Type REHABILITATE EXISTING ROADWAY
 
1.736 2081790.96 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-26-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 200
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0528-01-100
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03163229
Totals 2081790.96 0.00 0.00 0.0

CountyHIDALGO
Highway SH 336
From TRENTON RD.
To SH 107
CSJ 0621-01-100
Proj ID STP 2016(276)MM
Work Type MEDIANS WITH LANDSCAPING
 
2.807 842320.03 0.00 0.00 0.0
CountyHIDALGO
Highway SH 336
From TRENTON RD.
To SH 107
CSJ 0621-01-105
Proj ID STP 2016(277)
Work Type OVERLAY
 
2.807 1004003.43 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-14-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 160
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
IOC COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0621-01-100
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11153022
Totals 1846323.46 0.00 0.00 0.0

CountyCAMERON
Highway SH 345
From FM 1561
To FM 3462
CSJ 0630-01-051
Proj ID STP 1602(085)HES
Work Type SAFETY TREAT FIXED OBJECTS
 
3.277 296534.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 80
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
VALLEY INFRASTRUCTURE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0630-01-051
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05163025
Totals 296534.00 0.00 0.00 0.0

CountyCAMERON
Highway FM 106
From @ RIO HONDO LIFT BRIDGE
To .
CSJ 0630-02-041
Proj ID BR 1502(468)
Work Type BRIDGE REHABILITATION
 
0.100 12406043.30 0.00 59040.00 0.4
Work Order 10-30-15
Work Began 00-00-00
Work Completed  
Time Computed 11-30-15
Contract Working Days 651
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
PCL CIVIL CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0630-02-041
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07153019
Totals 12406043.30 0.00 59040.00 0.4

CountyHIDALGO
Highway FM 681
From FM 681 (N) @ FM 2221
To SH 107
CSJ 0669-01-043
Proj ID STP 2013(039)MM
Work Type WIDEN TO 4 LANE DIVIDED URBAN
 
1.784 12345193.52 4500.00 6171552.19 49.9
CountyHIDALGO
Highway FM 2221
From 0.25 MI W OF SH 364 (LA HOMA)
To .25 MI W OF MOOREFIELD RD
CSJ 0862-01-037
Proj ID STP 2013(040)MM
Work Type WIDEN TO 4 LANE DIVIDED
 
0.574 2333144.96 0.00 210725.00 9.0
CountyHIDALGO
Highway FM 2221
From 0.25 MI W OF MOOREFIELD RD
To FM 681
CSJ 0862-01-047
Proj ID STP 2013(039)MM
Work Type WIDEN TO 4 LANE DIVIDED URBAN
 
0.338 2162777.75 0.00 423938.34 19.6
Work Order 08-19-13
Work Began 09-04-13
Work Completed  
Time Computed 09-04-13
Contract Working Days 540
Addl Days Granted 0
Working Days Charged 42
Percent Time Used 7
Contractor(s)
FOREMOST PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0669-01-043
GO UNDERGROUND, LIMITED LIABILITY COMPANY( 20.85%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.29%)
SOIL-TECH, INC.(1.94%)
PAVEMENT MARKINGS INC. (1.01%)
VALLEY INFRASTRUCTURE, INC.( 10.14%)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (2.76%)
Contract # 06133203
Totals 16841116.23 4500.00 6806215.53 40.4

CountyHIDALGO
Highway FM 88
From SH 107, SOUTH
To 0.25 MI N OF MILE 16 N
CSJ 0698-03-084
Proj ID STP 2012(699)MM
Work Type WIDEN TO 4 LANE DIVIDED
 
0.249 2681776.78 0.00 2572050.54 99.9
CountyHIDALGO
Highway FM 88
From SH 107, SOUTH
To 0.25 MI. N. OF MIE 16 N
CSJ 0698-03-086
Proj ID RW 0698-3-86
Work Type ROW ACQUISITION
 
0.249 467213.71 0.00 586195.36 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-03-13
Work Began 04-09-13
Work Completed  
Time Computed 01-19-13
Contract Working Days 164
Addl Days Granted 0
Working Days Charged 379
Percent Time Used 231
Contractor(s)
IOC COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0698-03-084
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (4.44%)
VALLEY STRIPING CORP.(1.43%)
SOIL-TECH, INC.(0.07%)
Contract # 09123235
Totals 3148990.49 0.00 3158245.90 99.9

page 1 | page 2 | page 3 | page 4