AVERAGE LOW BID UNIT PRICE - CONSTRUCTION - SAN ANTONIO DISTRICT

Last Update: Tuesday, May 5, 2015
ITEMS 100 2001 TO 193 2009
Items Items Bid Code Range
0100 - 0193
0216 - 0275
0310 - 0360
0400 - 0496
0500 - 0560
0610 - 0690
0730 - 0780
1014 - 1127
2063 - 2316
3127 - 3285
4007 - 4670
5261 - 5957
6001 - 6900
7027 - 7421
8020 - 8998
100 2001 - 193 2009
Item No Description Units April 30, 2015 Twelve Month Moving Usage
Quantity Avg Bid Quantity Avg Bid
100 2001 PREPARING ROW AC     109.000 615.77982 2
100 2002 PREPARING ROW STA     5,361.750 611.35393 24
100 2003 PREPARING ROW (TREE) (5" TO 12" DIA) EA     2.000 500.00000 1
100 2004 PREPARING ROW (TREE) (12" TO 24" DIA) EA     4.000 1,050.00000 1
100 2009 PREPARING ROW (TREE) (6" TO 24" DIA) EA     5.000 1,400.00000 1
100 2011 PREPARING ROW (TREE) (24" TO 36" DIA.) EA     11.000 1,155.00000 1
100 2012 PREP ROW (TREE) (18" - 36" DIA.) EA     17.000 1,500.00000 1
100 2013 PREP ROW (TREE) (2" TO 12" DIA) EA     14.000 700.00000 1
100 2016 PREPARING ROW (TREE) (36" TO 48" DIA) EA     1.000 1,575.00000 1
100 6002 PREPARING ROW STA 571.100 339.83999 972.100 220.27839 2
104 2009 REMOVING CONC (RIPRAP) SY     16,702.000 10.22639 12
104 2011 REMOVING CONC (MEDIANS) SY     2,485.200 15.36099 3
104 2014 REMOVING CONC (FOUNDATIONS) CY     5.900 40.00000 1
104 2015 REMOVING CONC (SIDEWALKS) SY     1,523.000 8.06435 4
104 2017 REMOVING CONC (DRIVEWAYS) SY     4,567.400 12.31891 7
104 2021 REMOVING CONC (CURB) LF     23,075.000 3.69167 9
104 2023 REMOVING CONC (CTB) LF     695.000 31.00000 1
104 2024 REMOVING CONC (RETAINING WALLS) SY     45.000 9.00000 1
104 2027 REMOVING CONC (APPR SLAB) SY     28.000 94.00000 1
104 2028 REMOVING CONC (MISC) SY     561.000 8.00000 1
104 2029 REMOVING CONC (CURB OR CURB & GUTTER) LF     7,237.000 10.00000 1
104 2031 REMOVING CONC (HEADWALL) CY     44.000 100.00000 1
104 2032 REMOVING CONC (WHEELCHAIR RAMP) SY     12.000 59.98000 1
104 2036 REMOVING CONC (SIDEWALK OR RAMP) SY     1,009.000 11.96135 3
104 2037 REMOVE CONC (RAIL) LF     1,227.635 55.00000 1
104 2040 REMOVING CONC (PAVERS) SY     399.000 6.01003 2
104 2044 REMOVING CONC (FLUME) SY     435.000 5.55000 1
104 2054 REMOVING CONCRETE (MOW STRIP) LF     4,380.000 8.34817 2
105 2014 REMOVING STAB BASE & ASPH PAV (7" - 12") SY     978.000 20.00000 1
105 2016 REMOVING STAB BASE & ASPH PAV (16") SY     24,888.000 6.25000 1
105 2018 REMOVING STAB BASE AND ASPH PAV (7") SY     9,060.700 6.50000 1
105 2030 REMOVING STAB BASE & ASPH PAV (8" - 14") SY     4,803.000 2.44000 1
105 2037 REMOVING STAB BASE AND ASPH PAV (0" - 16" SY     426.000 12.00000 1
105 2039 REMOVE STAB BASE AND ASPH PAV (6" - 20") SY     15,781.000 6.59616 2
105 2049 REMOVING STAB BASE & ASPH PAV (4" - 22") SY     845.000 10.47000 1
110 2001 EXCAVATION (ROADWAY) CY     504,745.550 9.81865 24
110 2002 EXCAVATION (CHANNEL) CY     11,438.400 21.13312 4
110 2003 EXCAVATION (SPECIAL) CY     6,619.000 19.17037 3
110 6001 EXCAVATION (ROADWAY) CY 11,331.000 18.95000 11,331.000 18.95000 1
110 6003 EXCAVATION (SPECIAL) CY 800.900 32.76000 800.900 32.76000 1
112 2001 SUBGRADE WIDENING (ORD COMP) STA     166.580 265.00000 1
112 6001 SUBGRADE WIDENING (ORD COMP) STA     401.000 325.00000 1
132 2001 EMBANKMENT (FINAL) (ORD COMP) (TY A) CY     3,522.000 5.11349 2
132 2002 EMBANKMENT (FINAL) (DENS CONT) (TY A) CY     358.000 16.00000 1
132 2003 EMBANKMENT (FINAL) (ORD COMP) (TY B) CY     121,178.300 6.26684 19
132 2004 EMBANKMENT (FINAL) (DENS CONT) (TY B) CY     5,580.000 18.36989 2
132 2005 EMBANKMENT (FINAL) (ORD COMP) (TY C) CY     49,668.000 16.00000 1
132 2007 EMBANKMENT (FINAL) (ORD COMP) (TY D) CY     128.000 50.00000 1
132 2008 EMBANKMENT (FINAL) (DENS CONT) (TY D) CY     15.000 16.00000 1
132 6003 EMBANKMENT (FINAL) (ORD COMP) (TY B) CY 3,740.000 15.21000 3,740.000 15.21000 1
134 6002 BACKFILL (TY B) STA     401.000 115.00000 1
150 2001 BLADING STA     520.300 221.85259 2
150 2002 BLADING HR     160.000 107.16875 5
158 2003 SPEC EXCAV WORK (HYD EXCAVATOR) HR     80.000 134.91950 2
160 2003 FURNISHING AND PLACING TOPSOIL (4") SY     27,374.000 .72281 2
160 6003 FURNISHING AND PLACING TOPSOIL (4") SY 61,694.000 1.48000 61,694.000 1.48000 1
161 2002 COMPOST MANUF TOPSOIL (BOS) (4") SY     592,679.000 1.49661 8
161 2005 COMPOST MANUF TOPSOIL (PB) (4") SY     58,256.000 4.20553 3
161 2011 GENERAL USE COMPOST (1") SY     2,112.000 .93000 1
161 2014 COMPOST MANUF TOPSOIL (BOS OR PB) (4") SY     5,649.000 4.00000 1
161 2022 GENERAL USE COMPOST (4") SY     40,642.000 2.43659 2
162 2002 BLOCK SODDING SY     18,497.000 4.21884 5
164 2001 BROADCAST SEED (PERM) (RURAL) (SANDY) SY     118.000 4.46000 1
164 2003 BROADCAST SEED (PERM) (RURAL) (CLAY) SY     151,255.000 .15709 6
164 2007 BROADCAST SEED (PERM) (URBAN) (CLAY) SY     27,926.000 .13840 4
164 2009 BROADCAST SEED (TEMP) (WARM) SY     11,530.000 .28505 2
164 2011 BROADCAST SEED (TEMP) (COOL) SY     36,776.000 .15802 3
164 2021 CELL FBR MLCH SEED (PERM) (RURAL) (SANDY) SY     1,514.000 .55000 1
164 2023 CELL FBR MLCH SEED (PERM) (RURAL) (CLAY) SY     79,666.000 .29408 4
164 2027 CELL FBR MLCH SEED (PERM) (URBAN) (CLAY) SY     25,862.000 .26000 1
164 2029 CELL FBR MLCH SEED (TEMP) (WARM) SY     20,550.000 .33335 4
164 2031 CELL FBR MLCH SEED (TEMP) (COOL) SY     20,550.000 .33335 4
164 2033 DRILL SEEDING (PERM) (RURAL) (SANDY) SY     720,394.000 .12093 5
164 2035 DRILL SEEDING (PERM) (RURAL) (CLAY) SY     295,870.000 .15227 3
164 2039 DRILL SEEDING (PERM) (URBAN) (CLAY) SY     11,624.000 .19000 1
164 2041 DRILL SEEDING (TEMP) (WARM) SY     384,277.000 .11555 4
164 2043 DRILL SEEDING (TEMP) (COOL) SY     384,277.000 .11555 4
164 2045 STRAW OR HAY MULCHING SY     348,456.000 .35393 2
164 2051 DRILL SEED (TEMP) (WARM OR COOL) SY     400,195.000 .07181 4
164 6023 CELL FBR MLCH SEED (PERM) (RURAL) (CLAY) SY     53,333.000 .20000 1
164 6031 CELL FBR MLCH SEED (TEMP) (COOL) SY     26,661.000 .20000 1
164 6035 DRILL SEEDING (PERM) (RURAL) (CLAY) SY 61,694.000 .12000 61,694.000 .12000 1
168 2001 VEGETATIVE WATERING MG     32,545.798 17.16553 28
168 6001 VEGETATIVE WATERING MG 962.430 12.00000 2,295.430 13.74216 2
169 2001 SOIL RETENTION BLANKETS (CL 1) (TY A) SY     148,974.000 .92784 8
169 2002 SOIL RETENTION BLANKETS (CL 1) (TY B) SY     411,333.000 1.02182 7
169 2003 SOIL RETENTION BLANKETS (CL 1) (TY C) SY     61,788.000 1.39778 2
169 2006 SOIL RETENTION BLANKETS (CL 2) (TY F) SY     5,553.000 1.76000 1
169 2007 SOIL RETENTION BLANKETS (CL 2) (TY G) SY     405.000 2.50000 1
169 6001 SOIL RETENTION BLANKETS (CL 1) (TY A) SY 61,694.000 .95000 61,694.000 .95000 1
170 2001 IRRIGATION SYSTEM LS     2.000 114,265.00000 2
192 2003 PLANT MATERIAL (3 - GAL) EA     89.000 25.00000 1
192 2004 PLANT MATERIAL (5 - GAL) EA     14,212.000 24.37841 2
192 2005 PLANT MATERIAL (15 - GAL) EA     2,121.000 117.56719 2
192 2013 MULCH SY     47,248.000 3.84515 2
192 2035 PLANT MATERIAL (MIN 4' HT) (B & B) EA     52.000 300.00000 1
192 2049 PLANT MATERIAL (MIN 4' TRNK HT) (PALM) EA     111.000 314.95495 2
192 2063 PLANT BED PREP (TYPE I) SY     40,642.000 1.84511 2
192 2064 PLANT BED PREP (TYPE II) SY     4,995.000 1.72517 2
192 2079 PLANT MATERIAL (MIN 2' TR HT) (PALM) EA     8.000 300.00000 1
193 2001 PLANT MAINTENANCE MO     54.000 2,111.11111 2
193 2004 PLANT REPLACEMENT (3 - GAL) EA     2.000 25.00000 1
193 2005 PLANT REPLACEMENT (5 - GAL) EA     20.000 32.50000 2
193 2007 IRRIGATION SYSTEM OPER AND MAINT MO     54.000 777.77778 2
193 2009 PLANT REPLACEMENT (15 GAL) EA     10.000 132.50000 2