AVERAGE LOW BID UNIT PRICE - CONSTRUCTION - SAN ANTONIO DISTRICT

Last Update: Friday, October 31, 2014
ITEMS 100 2001 TO 193 2009
Items Items Bid Code Range
0100 - 0193
0216 - 0275
0310 - 0360
0400 - 0496
0500 - 0560
0610 - 0690
0730 - 0780
1014 - 1127
2063 - 2316
3127 - 3285
4007 - 4670
5261 - 5957
6006 - 6900
7419 - 7421
8020 - 8998
100 2001 - 193 2009
Item No Description Units October 31, 2014 Twelve Month Moving Usage
Quantity Avg Bid Quantity Avg Bid
100 2001 PREPARING ROW AC     109.000 615.77982 2
100 2002 PREPARING ROW STA 61.500 920.00000 3,706.600 895.17187 20
100 2003 PREPARING ROW (TREE) (5" TO 12" DIA) EA     2.000 500.00000 1
100 2009 PREPARING ROW (TREE) (6" TO 24" DIA) EA     5.000 1,400.00000 1
100 2012 PREP ROW (TREE) (18" - 36" DIA.) EA 17.000 1,500.00000 17.000 1,500.00000 1
100 2013 PREP ROW (TREE) (2" TO 12" DIA) EA 14.000 700.00000 14.000 700.00000 1
104 2001 REMOVING CONC (PAV) SY     409.000 28.95000 1
104 2009 REMOVING CONC (RIPRAP) SY 1,235.000 8.00000 16,957.000 10.66316 14
104 2011 REMOVING CONC (MEDIANS) SY 29.000 10.00000 2,956.200 15.78648 3
104 2014 REMOVING CONC (FOUNDATIONS) CY 5.900 40.00000 5.900 40.00000 1
104 2015 REMOVING CONC (SIDEWALKS) SY     2,274.000 11.35039 6
104 2017 REMOVING CONC (DRIVEWAYS) SY 1,920.000 9.00000 5,866.400 14.43729 8
104 2021 REMOVING CONC (CURB) LF     24,857.000 3.74691 11
104 2022 REMOVING CONC (CURB AND GUTTER) LF     934.000 8.00000 1
104 2023 REMOVING CONC (CTB) LF     695.000 31.00000 1
104 2024 REMOVING CONC (RETAINING WALLS) SY 45.000 9.00000 45.000 9.00000 1
104 2027 REMOVING CONC (APPR SLAB) SY     28.000 94.00000 1
104 2028 REMOVING CONC (MISC) SY     561.000 8.00000 1
104 2029 REMOVING CONC (CURB OR CURB & GUTTER) LF 7,237.000 10.00000 7,237.000 10.00000 1
104 2031 REMOVING CONC (HEADWALL) CY     44.000 100.00000 1
104 2032 REMOVING CONC (WHEELCHAIR RAMP) SY     47.000 30.20766 2
104 2036 REMOVING CONC (SIDEWALK OR RAMP) SY 339.000 10.00000 1,009.000 11.96135 3
104 2037 REMOVE CONC (RAIL) LF     1,227.635 55.00000 1
104 2040 REMOVING CONC (PAVERS) SY 4.000 7.00000 399.000 6.01003 2
104 2044 REMOVING CONC (FLUME) SY     435.000 5.55000 1
104 2054 REMOVING CONCRETE (MOW STRIP) LF     4,480.000 8.49665 3
105 2011 REMOVING STAB BASE AND ASPH PAV (2" - 6" SY     2,087.000 3.42000 1
105 2014 REMOVING STAB BASE & ASPH PAV (7" - 12") SY     978.000 20.00000 1
105 2016 REMOVING STAB BASE & ASPH PAV (16") SY     24,888.000 6.25000 1
105 2018 REMOVING STAB BASE AND ASPH PAV (7") SY     9,060.700 6.50000 1
105 2030 REMOVING STAB BASE & ASPH PAV (8" - 14") SY     4,803.000 2.44000 1
105 2037 REMOVING STAB BASE AND ASPH PAV (0" - 16" SY 426.000 12.00000 426.000 12.00000 1
105 2039 REMOVE STAB BASE AND ASPH PAV (6" - 20") SY     15,781.000 6.59616 2
105 2049 REMOVING STAB BASE & ASPH PAV (4" - 22") SY     845.000 10.47000 1
110 2001 EXCAVATION (ROADWAY) CY     504,320.550 10.76033 25
110 2002 EXCAVATION (CHANNEL) CY     11,438.400 21.13312 4
110 2003 EXCAVATION (SPECIAL) CY 2,426.000 30.00000 4,396.000 19.07448 2
132 2001 EMBANKMENT (FINAL) (ORD COMP) (TY A) CY     3,455.000 4.34000 1
132 2003 EMBANKMENT (FINAL) (ORD COMP) (TY B) CY     134,889.300 6.10406 20
132 2004 EMBANKMENT (FINAL) (DENS CONT) (TY B) CY     5,580.000 18.36989 2
132 2005 EMBANKMENT (FINAL) (ORD COMP) (TY C) CY     49,668.000 16.00000 1
132 2007 EMBANKMENT (FINAL) (ORD COMP) (TY D) CY     1,832.000 45.67396 2
132 2008 EMBANKMENT (FINAL) (DENS CONT) (TY D) CY     15.000 16.00000 1
150 2002 BLADING HR 12.000 200.00000 128.000 103.62688 6
158 2003 SPEC EXCAV WORK (HYD EXCAVATOR) HR     40.000 125.00000 1
160 2003 FURNISHING AND PLACING TOPSOIL (4") SY     27,374.000 .72281 2
161 2002 COMPOST MANUF TOPSOIL (BOS) (4") SY     599,683.000 1.45338 9
161 2005 COMPOST MANUF TOPSOIL (PB) (4") SY 11,355.000 3.00000 51,666.000 3.78022 2
161 2017 COMPOST MANUF TOPSOIL (BIP) (4") SY     34,832.000 .96000 1
161 2022 GENERAL USE COMPOST (4") SY     17,744.000 3.00000 1
162 2002 BLOCK SODDING SY 11,355.000 4.00000 62,579.000 3.48584 8
164 2003 BROADCAST SEED (PERM) (RURAL) (CLAY) SY 405.000 1.25000 95,645.000 .13206 3
164 2007 BROADCAST SEED (PERM) (URBAN) (CLAY) SY     22,277.000 .12532 3
164 2009 BROADCAST SEED (TEMP) (WARM) SY     11,530.000 .28505 2
164 2011 BROADCAST SEED (TEMP) (COOL) SY     36,776.000 .15802 3
164 2023 CELL FBR MLCH SEED (PERM) (RURAL) (CLAY) SY     48,549.000 .34384 4
164 2027 CELL FBR MLCH SEED (PERM) (URBAN) (CLAY) SY     25,862.000 .26000 1
164 2029 CELL FBR MLCH SEED (TEMP) (WARM) SY     20,550.000 .33335 4
164 2031 CELL FBR MLCH SEED (TEMP) (COOL) SY     20,550.000 .33335 4
164 2033 DRILL SEEDING (PERM) (RURAL) (SANDY) SY     638,876.000 .10781 4
164 2035 DRILL SEEDING (PERM) (RURAL) (CLAY) SY     298,350.000 .15975 6
164 2039 DRILL SEEDING (PERM) (URBAN) (CLAY) SY     11,624.000 .19000 1
164 2041 DRILL SEEDING (TEMP) (WARM) SY     335,897.000 .10805 4
164 2043 DRILL SEEDING (TEMP) (COOL) SY     335,897.000 .10805 4
164 2045 STRAW OR HAY MULCHING SY     250,712.000 .35000 1
164 2051 DRILL SEED (TEMP) (WARM OR COOL) SY     391,617.000 .07237 5
168 2001 VEGETATIVE WATERING MG 184.138 26.84269 30,599.602 15.98482 26
169 2001 SOIL RETENTION BLANKETS (CL 1) (TY A) SY     134,335.000 .85952 7
169 2002 SOIL RETENTION BLANKETS (CL 1) (TY B) SY     369,497.000 .98725 4
169 2003 SOIL RETENTION BLANKETS (CL 1) (TY C) SY     61,788.000 1.39778 2
169 2006 SOIL RETENTION BLANKETS (CL 2) (TY F) SY     7,597.000 1.69005 2
169 2007 SOIL RETENTION BLANKETS (CL 2) (TY G) SY 405.000 2.50000 405.000 2.50000 1
170 2001 IRRIGATION SYSTEM LS     1.000 75,000.00000 1
192 2003 PLANT MATERIAL (3 - GAL) EA     89.000 25.00000 1
192 2004 PLANT MATERIAL (5 - GAL) EA     5,378.000 25.00000 1
192 2005 PLANT MATERIAL (15 - GAL) EA     879.000 100.00000 1
192 2013 MULCH SY     20,627.000 3.00000 1
192 2035 PLANT MATERIAL (MIN 4' HT) (B & B) EA     52.000 300.00000 1
192 2049 PLANT MATERIAL (MIN 4' TRNK HT) (PALM) EA     52.000 400.00000 1
192 2063 PLANT BED PREP (TYPE I) SY     17,744.000 1.00000 1
192 2064 PLANT BED PREP (TYPE II) SY     2,883.000 2.00000 1
192 2079 PLANT MATERIAL (MIN 2' TR HT) (PALM) EA     8.000 300.00000 1
193 2001 PLANT MAINTENANCE MO     24.000 1,500.00000 1
193 2004 PLANT REPLACEMENT (3 - GAL) EA     2.000 25.00000 1
193 2005 PLANT REPLACEMENT (5 - GAL) EA     10.000 30.00000 1
193 2007 IRRIGATION SYSTEM OPER AND MAINT MO     24.000 1,000.00000 1
193 2009 PLANT REPLACEMENT (15 GAL) EA     5.000 125.00000 1