Monthly State Let Construction Report For San Antonio District As Of Mar 13, 2024 Page 7 Of 7
Last Update: Wednesday, March 13, 2024
|
|
Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
County | BEXAR |
Highway | SH 151 |
From | LP 1604 |
To | IH 410 |
CSJ | 3508-01-029 |
Proj ID | F 2023(162) |
Work Type | WIDEN FREEWAY |
|
| 5.591 | 94798463.69 | | 32473985.24 | 34.2 |
County | BEXAR |
Highway | SH 151 |
From | LP 1604 |
To | IH 410 |
CSJ | 3508-01-030 |
Proj ID | ROW 3508-1-30 |
Work Type | RIGHT OF WAY |
|
| 5.591 | 3004452.98 | | 4264798.35 | 99.9 |
Work Order | 02-16-23 |
Work Began | 05-01-23 |
Work Completed | |
Time Computed | 05-01-23 |
Contract Working Days | 1,079 |
Addl Days Granted | 36 |
Working Days Charged | 251 |
Percent Time Used | 22 |
Contractor(s) |
AUSTIN BRIDGE & ROAD SERVICES, LP |
SUBCONTRACTOR(S) FOR CCSJ: 3508-01-029 A. H. BECK FOUNDATION CO., INC. (1.59) C-3 LAND CLEARING, LLC (0.03) AARON CONCRETE CONTRACTORS, LLC (1.74) FLASHER EQUIPMENT COMPANY (1.64) FARR FOUNDATION, INC. (0.41) MEX UTILITIES LLC (1.37) S&S BRIDGE PAINTING (0.00) SK CONCRETE SERVICES LLC (0.02) FLORIDA TRAFFIC CONTROL DEVICES, INC. (13.65) LONE STAR EROSION CONTROL (2.00) Z & L CONCRETE CONTRACTORS, INC. (3.40) WAMPOLE MILLER, INC. (0.19) SERNA"S TRUCKING (0.82) ROYAL REBAR (1.87) PIPE WHOLESALERS OF TEXAS, INC. (1.20) MOBILE ENTERPRISES, INC. (0.04) BOEN LANDSCAPING & IRRIGATION, LLC (0.00) HH&W TRANSPORT INC (0.00) BUYERS BARRICADES, INC. (0.00) RICHEY TRANSPORT LLC (0.00) JC DIRECTIONAL DRILLING (0.31)
|
Contract # | 01233237 |
| Totals | 97802916.67 | 1861769.54 | 36738783.59 | 37.5 |
|
County | BEXAR |
Highway | PA 1502 |
From | FM 1535 |
To | O'CONNOR/CROSSWINDS WAY |
CSJ | 7774-01-004 |
Proj ID | F 2021(678) |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 10.712 | 19520129.83 | | 15727431.84 | 80.5 |
Work Order | 08-18-21 |
Work Began | 02-01-22 |
Work Completed | |
Time Computed | 11-16-21 |
Contract Working Days | 424 |
Addl Days Granted | 109 |
Working Days Charged | 453 |
Percent Time Used | 84 |
Contractor(s) |
JORDAN FOSTER CONSTRUCTION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 7774-01-004 THE LEVY COMPANY, INC. (12.86) JB PINNACLE GROUP, LLC (7.97) RUCOBA & MAYA CONSTRUCTION, LLC (1.36) LONE STAR EROSION CONTROL (4.21) SCOTT DERR PAINTING CO, LLC (0.35) TEXAS CUTTING & CORING GP, INC. (0.03) TEXAS MATERIALS GROUP, INC. (27.98) TRP CONSTRUCTION GROUP, LLC (3.75) STRUCTURAL INTEGRITY GROUP LLC (0.41) ROADWAY SPECIALTIES, INC. (1.08) JT UNDERGROUND AND UTILITY CONSTRUCTION INC (0.00) ENVIRONMENTAL SAFETY SERVICES, INC. (0.17)
|
Contract # | 07213203 |
| Totals | 19520129.83 | 1030186.27 | 15727431.84 | 80.5 |
|