Monthly Local Let Maintenance Report For San Antonio District As Of Aug 12, 2014 Page 2 Of 2

Last Update: Tuesday, August 12, 2014
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyGUADALUPE
Highway FM1979
From BS 123 AT WALNUT BRANCH AND
To FM 1979 AT LONG CREEK
CSJ 6262-81-001
Proj ID BPM - 626281001
Work Type SCOUR REPAIR
 
0.001 104145.00 79336.00 79336.00 76.1
Work Order 07-15-14
Work Began 07-18-14
Work Completed  
Time Computed 07-23-14
Contract Working Days 36
Addl Days Granted 0
Working Days Charged 8
Percent Time Used 22
Contractor(s)
SJ&J CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6262-81-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06141504
Totals 104145.00 79336.00 79336.00 76.1

CountyATASCOSA
Highway SH0173
From AT MILE AND A HALF CREEK
To IN ATASCOSA COUNTY
CSJ 6264-94-001
Proj ID BPM - 626494001
Work Type SCOUR REPAIR__BRIDGE #150070042104008
 
0.001 38710.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6264-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06141501
Totals 38710.00 0.00 0.00 0.0

CountyWILSON
Highway US0181
From VARIOUS LOCATIONS IN
To WILSON COUNTY
CSJ 6265-78-001
Proj ID RMC - 626578001
Work Type PICNIC AREA MAINTENANCE
 
0.001 24600.00 760.00 4142.50 16.8
Work Order 01-30-14
Work Began 02-03-14
Work Completed  
Time Computed 02-03-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 176
Percent Time Used 24
Contractor(s)
MALDONADO NURSERY & LANDSCAPING INC.
SUBCONTRACTOR(S) FOR CCSJ: 6265-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11131501
Totals 24600.00 760.00 4142.50 16.8

CountyMEDINA
Highway SH0173
From SH 173
To SH 173
CSJ 6266-55-001
Proj ID SUP - 626655001
Work Type JANITORIAL SERVICES
 
0.001 5726.74 107.50 3289.50 57.4
Work Order 11-14-13
Work Began 11-23-13
Work Completed  
Time Computed 11-23-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 250
Percent Time Used 68
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6266-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10131530
Totals 5726.74 107.50 3289.50 57.4

CountyUVALDE
Highway US0090
From US 90
To US 90
CSJ 6266-60-001
Proj ID SUP - 626660001
Work Type JANITORIAL SERVICES
 
0.001 5055.36 358.78 3422.93 67.7
Work Order 11-19-13
Work Began 11-23-13
Work Completed  
Time Computed 11-23-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 251
Percent Time Used 68
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6266-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10131531
Totals 5055.36 358.78 3422.93 67.7

CountyFRIO
Highway FM0140
From FM 140
To FM 140
CSJ 6267-50-001
Proj ID SUP - 626750001
Work Type JANITORIAL SERVICES
 
0.001 5156.64 0.00 3115.47 60.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 11-27-13
Work Completed  
Time Computed 11-23-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 220
Percent Time Used 60
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6267-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11131530
Totals 5156.64 0.00 3115.47 60.4

CountyMCMULLEN
Highway SH0016
From VARIOUS LOCATIONS IN
To MCMULLEN COUNTY
CSJ 6267-90-001
Proj ID RMC - 626790001
Work Type MOWING
 
0.001 0.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-07-14
Work Began 07-08-14
Work Completed  
Time Computed 07-14-14
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
WALLA BROTHERS
SUBCONTRACTOR(S) FOR CCSJ: 6267-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01141501
Totals 0.00 0.00 0.00 0.0

CountyBEXAR
Highway US0281
From US 281 AT
To JONES MALTSBERGER
CSJ 6271-82-001
Proj ID RMC - 627182001
Work Type DRAINAGE IMPROVEMENTS
 
0.001 75919.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-07-14
Work Began 07-15-14
Work Completed  
Time Computed 07-14-14
Contract Working Days 26
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BECK-REIT & SONS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6271-82-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06141503
Totals 75919.00 0.00 0.00 0.0

CountyWILSON
Highway SH0097
From FLORESVILLE MAINTENANCE
To OFFICE
CSJ 6274-05-001
Proj ID SUP - 627405001
Work Type JANITORIAL SERVICES
 
0.001 11823.45 1685.17 2136.97 18.0
Work Order 06-10-14
Work Began 06-17-14
Work Completed  
Time Computed 06-13-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 49
Percent Time Used 13
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6274-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141530
Totals 11823.45 1685.17 2136.97 18.0

CountyATASCOSA
Highway US0281
From 2154 2ND STREET
To 2154 2ND STREET
CSJ 6274-12-001
Proj ID SUP - 627412001
Work Type JANITORIAL SERVICES
 
0.001 12207.23 914.04 1828.08 14.9
Work Order 05-30-14
Work Began 06-07-14
Work Completed  
Time Computed 06-06-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 56
Percent Time Used 15
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6274-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141531
Totals 12207.23 914.04 1828.08 14.9

CountyCOMAL
Highway IH0035
From NEW BRAUNFELS
To MAINTENANCE OFFICE
CSJ 6274-14-001
Proj ID SUP - 627414001
Work Type JANITORIAL SERVICES
 
0.001 16579.47 1160.92 1650.07 9.9
Work Order 06-17-14
Work Began 06-22-14
Work Completed  
Time Computed 06-19-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 43
Percent Time Used 11
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6274-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141532
Totals 16579.47 1160.92 1650.07 9.9

CountyGUADALUPE
Highway SH0046
From 2028 HWY 46 N
To 2028 HWY 46 N
CSJ 6274-16-001
Proj ID SUP - 627416001
Work Type JANITORIAL SERVICE
 
0.001 11377.39 839.81 1679.62 14.7
Work Order 06-04-14
Work Began 06-06-14
Work Completed  
Time Computed 06-06-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 56
Percent Time Used 15
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6274-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141533
Totals 11377.39 839.81 1679.62 14.7

CountyGUADALUPE
Highway SH0046
From 2024 HWY 46 N
To 2024 HWY 46 N
CSJ 6275-04-001
Proj ID SUP - 627504001
Work Type JANITORIAL SERVICES
 
0.001 9759.84 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6275-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06141530
Totals 9759.84 0.00 0.00 0.0

CountyGUADALUPE
Highway SH0046
From 2024 HWY 46N
To SEGUIN
CSJ 6275-59-001
Proj ID SUP - 627559001
Work Type GROUNDS MAINTENANCE
 
0.001 4200.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6275-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06141531
Totals 4200.00 0.00 0.00 0.0

CountyGUADALUPE
Highway SH0046
From 2024 N HWY 46
To 2024 N HWY 46
CSJ 6275-60-001
Proj ID SUP - 627560001
Work Type FLOOR MAINTENANCE
 
0.001 14504.40 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6275-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06141532
Totals 14504.40 0.00 0.00 0.0

CountyMCMULLEN
Highway SH0016
From SH 16
To AT NUECES RIVER BRIDGE
CSJ 6276-27-001
Proj ID EMC - 627627001
Work Type BRIDGE REPAIR
 
0.001 348981.31 119879.00 119879.00 34.3
Work Order 07-15-14
Work Began 07-16-14
Work Completed  
Time Computed 07-16-14
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 16
Percent Time Used 53
Contractor(s)
AUSTIN BRIDGE & ROAD, LP
SUBCONTRACTOR(S) FOR CCSJ: 6276-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07141541
Totals 348981.31 119879.00 119879.00 34.3

CountyBEXAR
Highway IH0035
From IH 35 AT
To NEW BRAUNFELS
CSJ 6277-09-001
Proj ID EMC - 627709001
Work Type EMERGENCY BEAM REMOVAL
 
0.001 514065.00 514065.00 514065.00 99.9
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 07-25-14
Contract Working Days 3
Addl Days Granted 0
Working Days Charged 3
Percent Time Used 100
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6277-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07141542
Totals 514065.00 514065.00 514065.00 99.9

CountyBEXAR
Highway FM1976
From FM 1976
To FM 1976
CSJ 6277-60-001
Proj ID SUP - 627760001
Work Type JANITORIAL SERVICES
 
0.001 6716.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TIBH INDUSTRIES, INC.
ENDEAVORS UNLIMITED, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6277-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07141530
Totals 6716.50 0.00 0.00 0.0

CountyBEXAR
Highway IH0410
From 9320 SE LOOP 410
To 9320 SE LOOP 410
CSJ 6277-61-001
Proj ID SUP - 627761001
Work Type JANITORIAL WORK
 
0.001 23270.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TIBH INDUSTRIES, INC.
ENDEAVORS UNLIMITED, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6277-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07141531
Totals 23270.00 0.00 0.00 0.0

page 1 | page 2