Monthly Local Let Maintenance Report For San Antonio District As Of Feb 11, 2015 Page 2 Of 3

Last Update: Wednesday, February 11, 2015
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyUVALDE
Highway US0090
From US 90
To US 90
CSJ 6266-60-001
Proj ID SUP - 626660001
Work Type JANITORIAL SERVICES
 
0.001 5055.36 0.00 4499.28 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-19-13
Work Began 11-23-13
Work Completed 11-22-14
Time Computed 11-23-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 365
Percent Time Used 100
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6266-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10131531
Totals 5055.36 0.00 4499.28 100.0

CountyFRIO
Highway FM0140
From FM 140
To FM 140
CSJ 6267-50-001
Proj ID SUP - 626750001
Work Type JANITORIAL SERVICES
 
0.001 5156.64 0.00 5264.07 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 11-27-13
Work Completed 11-22-14
Time Computed 11-23-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 372
Percent Time Used 101
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6267-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11131530
Totals 5156.64 0.00 5264.07 100.0

CountyMCMULLEN
Highway SH0016
From VARIOUS LOCATIONS IN
To MCMULLEN COUNTY
CSJ 6267-90-001
Proj ID RMC - 626790001
Work Type MOWING
 
0.001 262549.64 0.00 56822.56 21.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 07-08-14
Work Completed  
Time Computed 07-14-14
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 17
Percent Time Used 17
Contractor(s)
WALLA BROTHERS
SUBCONTRACTOR(S) FOR CCSJ: 6267-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01141501
Totals 262549.64 0.00 56822.56 21.6

CountyBEXAR
Highway IH0010
From PROJECT NO. : RMC 6271-80-001
To DISTRICT WIDE VARIOUS ROADWAYS
CSJ 6271-80-001
Proj ID RMC - 627180001
Work Type PREVENTIVE MAINTENANCE, TRAFFIC SIGNALS
 
0.001 250000.00 13700.00 44675.00 17.8
Work Order 10-15-14
Work Began 10-23-14
Work Completed  
Time Computed 10-23-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 101
Percent Time Used 27
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6271-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08141502
Totals 250000.00 13700.00 44675.00 17.8

CountyBEXAR
Highway US0281
From US 281 AT
To JONES MALTSBERGER
CSJ 6271-82-001
Proj ID RMC - 627182001
Work Type DRAINAGE IMPROVEMENTS
 
0.001 75919.00 7015.00 85406.42 99.9
Work Order 07-07-14
Work Began 07-15-14
Work Completed  
Time Computed 07-14-14
Contract Working Days 26
Addl Days Granted 33
Working Days Charged 44
Percent Time Used 74
Contractor(s)
BECK-REIT & SONS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6271-82-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06141503
Totals 75919.00 7015.00 85406.42 99.9

CountyWILSON
Highway SH0097
From FLORESVILLE MAINTENANCE
To OFFICE
CSJ 6274-05-001
Proj ID SUP - 627405001
Work Type JANITORIAL SERVICES
 
0.001 11823.45 903.59 7260.33 61.4
Work Order 06-10-14
Work Began 06-17-14
Work Completed  
Time Computed 06-13-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 233
Percent Time Used 63
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6274-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141530
Totals 11823.45 903.59 7260.33 61.4

CountyBEXAR
Highway IH0010
From VARIOUS LOCATIONS IN THE SAN
To ANTONIO DISTRICT
CSJ 6274-06-001
Proj ID RMC - 627406001
Work Type TRAFFIC SIGNAL MAINTENANCE AND REPAIR
 
0.001 357615.00 1800.00 59418.07 16.6
Work Order 10-15-14
Work Began 10-21-14
Work Completed  
Time Computed 10-23-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 101
Percent Time Used 27
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6274-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09141503
Totals 357615.00 1800.00 59418.07 16.6

CountyATASCOSA
Highway US0281
From 2154 2ND STREET
To 2154 2ND STREET
CSJ 6274-12-001
Proj ID SUP - 627412001
Work Type JANITORIAL SERVICES
 
0.001 12207.23 914.04 7312.32 59.9
Work Order 05-30-14
Work Began 06-07-14
Work Completed  
Time Computed 06-06-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 240
Percent Time Used 65
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6274-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141531
Totals 12207.23 914.04 7312.32 59.9

CountyCOMAL
Highway IH0035
From NEW BRAUNFELS
To MAINTENANCE OFFICE
CSJ 6274-14-001
Proj ID SUP - 627414001
Work Type JANITORIAL SERVICES
 
0.001 16579.47 1304.40 9964.87 60.1
Work Order 06-17-14
Work Began 06-22-14
Work Completed  
Time Computed 06-19-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 227
Percent Time Used 62
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6274-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141532
Totals 16579.47 1304.40 9964.87 60.1

CountyGUADALUPE
Highway SH0046
From 2028 HWY 46 N
To 2028 HWY 46 N
CSJ 6274-16-001
Proj ID SUP - 627416001
Work Type JANITORIAL SERVICE
 
0.001 11377.39 2139.48 8018.15 70.4
Work Order 06-04-14
Work Began 06-06-14
Work Completed  
Time Computed 06-06-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 240
Percent Time Used 65
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6274-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141533
Totals 11377.39 2139.48 8018.15 70.4

CountyCOMAL
Highway IH0035
From VARIOUS_LOCATIONS IN COMAL, WILSON
To AND GUADALUPE COUNTIES
CSJ 6274-38-001
Proj ID RMC - 627438001
Work Type CRACK SEAL
 
0.001 220725.00 0.00 0.00 0.0
Work Order 12-17-14
Work Began 00-00-00
Work Completed  
Time Computed 12-10-14
Contract Working Days 33
Addl Days Granted 0
Working Days Charged 11
Percent Time Used 33
Contractor(s)
TRIPLE R CONTRACTING, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6274-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09141502
Totals 220725.00 0.00 0.00 0.0

CountyMEDINA
Highway FM0471
From VARIOUS HIGHWAYS
To VAR CNTYS ATASCOSA,FRIO,MCMULLEN,MEDINA
CSJ 6274-39-001
Proj ID RMC - 627439001
Work Type CRACK SEAL
 
0.001 316400.00 110040.00 128100.00 40.4
Work Order 12-03-14
Work Began 12-15-14
Work Completed  
Time Computed 12-15-14
Contract Working Days 46
Addl Days Granted 0
Working Days Charged 15
Percent Time Used 32
Contractor(s)
M & M STRIPING & POWER WASHING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6274-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09141504
Totals 316400.00 110040.00 128100.00 40.4

CountyKERR
Highway SH0039
From VARIOUS LOCATIONS IN KERR
To AND BANDERA COUNTIES
CSJ 6274-62-001
Proj ID RMC - 627462001
Work Type PICNIC_AREA MAINTENANCE
 
0.001 195200.00 8100.00 33700.00 17.2
Work Order 09-29-14
Work Began 09-25-14
Work Completed  
Time Computed 09-25-14
Contract Working Days 760
Addl Days Granted 0
Working Days Charged 129
Percent Time Used 16
Contractor(s)
SHORT-LINE CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6274-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08141503
Totals 195200.00 8100.00 33700.00 17.2

CountyKERR
Highway IH0010
From VARIOUS IN KENDALL, KERR, BANDERA
To AND UVALDE COUNTIES
CSJ 6274-63-001
Proj ID RMC - 627463001
Work Type CRACK SEAL
 
0.001 159394.53 24097.44 59038.73 37.0
Work Order 11-17-14
Work Began 11-24-14
Work Completed  
Time Computed 11-24-14
Contract Working Days 32
Addl Days Granted 0
Working Days Charged 19
Percent Time Used 59
Contractor(s)
TRIPLE R CONTRACTING, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6274-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09141501
Totals 159394.53 24097.44 59038.73 37.0

CountyGUADALUPE
Highway SH0046
From 2024 HWY 46 N
To 2024 HWY 46 N
CSJ 6275-04-001
Proj ID SUP - 627504001
Work Type JANITORIAL SERVICES
 
0.001 9759.84 725.77 2115.51 21.6
Work Order 07-07-14
Work Began 07-01-14
Work Completed  
Time Computed 07-07-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 86
Percent Time Used 23
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6275-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06141530
Totals 9759.84 725.77 2115.51 21.6

CountyMCMULLEN
Highway SH0016
From VARIOUS
To VARIOUS
CSJ 6275-14-001
Proj ID RMC - 627514001
Work Type LITTER PICKUP
 
0.001 0.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CTX SPECIAL SERVIES CO LLC
SUBCONTRACTOR(S) FOR CCSJ: 6275-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01151503
Totals 0.00 0.00 0.00 0.0

CountyGUADALUPE
Highway SH0046
From 2024 HWY 46N
To SEGUIN
CSJ 6275-59-001
Proj ID SUP - 627559001
Work Type GROUNDS MAINTENANCE
 
0.001 4200.00 420.00 840.00 20.0
Work Order 08-01-14
Work Began 08-01-14
Work Completed  
Time Computed 08-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 92
Percent Time Used 25
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6275-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06141531
Totals 4200.00 420.00 840.00 20.0

CountyGUADALUPE
Highway SH0046
From 2024 N HWY 46
To 2024 N HWY 46
CSJ 6275-60-001
Proj ID SUP - 627560001
Work Type FLOOR MAINTENANCE
 
0.001 14504.40 1208.70 3626.10 25.0
Work Order 08-01-14
Work Began 08-01-14
Work Completed  
Time Computed 08-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 92
Percent Time Used 25
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6275-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06141532
Totals 14504.40 1208.70 3626.10 25.0

CountyMCMULLEN
Highway SH0016
From SH 16
To AT NUECES RIVER BRIDGE
CSJ 6276-27-001
Proj ID EMC - 627627001
Work Type BRIDGE REPAIR
 
0.001 348981.31 0.00 350338.27 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-15-14
Work Began 07-16-14
Work Completed 11-30-14
Time Computed 07-16-14
Contract Working Days 30
Addl Days Granted 8
Working Days Charged 38
Percent Time Used 100
Contractor(s)
AUSTIN BRIDGE & ROAD, LP
SUBCONTRACTOR(S) FOR CCSJ: 6276-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07141541
Totals 348981.31 0.00 350338.27 100.0

CountyBEXAR
Highway FM1976
From FM 1976
To FM 1976
CSJ 6277-60-001
Proj ID SUP - 627760001
Work Type JANITORIAL SERVICES
 
0.001 6716.50 515.00 3090.00 46.0
Work Order 07-25-14
Work Began 08-07-14
Work Completed  
Time Computed 08-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 184
Percent Time Used 50
Contractor(s)
TIBH INDUSTRIES, INC.
ENDEAVORS UNLIMITED, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6277-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07141530
Totals 6716.50 515.00 3090.00 46.0