Monthly State Let Construction Report For San Angelo District As Of Jul 14, 2017 Page 1 Of 1

Last Update: Monday, July 17, 2017
FTP Icon
page 1

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyRUNNELS
HighwayUS 83
FromAT ELM CREEK AND AT RAILROAD/FM 382
To.
CSJ0034-05-039
Proj IDBR 2015(182)
Work TypeREHABILITATE BRIDGES
 
0.20014622336.5714194710.7297.5
Work Order01-02-15
Work Began01-26-15
Work Completed
Time Computed01-26-15
Contract Working Days304
Addl Days Granted133
Working Days Charged490
Percent Time Used112
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0034-05-039
S & S BRIDGE PAINTING, INC. (13.95)
CONTRACTORS SERVICE COMPANY (0.42)
WILLIS ELECTRIC CO., LP (1.99)
CHOCTAW ERECTORS, INC. (2.70)
RICE ENVIRONMENTAL SERVICES (0.46)
AARON CONCRETE CONTRACTORS, L.P. (3.60)
W. W. FOUNDATION DRILLING, LTD. (2.38)
DOUBLE A CONTRACTING, L.P. (0.55)
RUNNING HORSE CONSTRUCTION, INC. (1.23)
MCL CONTRACTING, LLC (1.52)
KLP COMMERCIAL, LLC (5.37)
STRAIGHT LINE SAWING & SEALING (0.20)
MCL CONTRACTING, LLC (0.11)
HJC FARMS, INC. (0.15)
MICA CORPORATION (0.87)
Contract #10143203
Totals14622336.57461686.3814194710.7297.5

CountyRUNNELS ETC
HighwayUS 83 ETC
From1.7 MI S OF US 67
ToCONCHO COUNTY LINE
CSJ0035-01-033
Proj IDSTP 1702(545)HESG
Work TypeCENTERLINE AND SHOULDER TEXTURING
 
321.4362069426.770.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days164
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0035-01-033
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07173036
Totals2069426.770.000.000.0

CountyMENARD
HighwayUS 83
FromRM 2291
To0.5 MILES SOUTH OF RM 2291
CSJ0035-05-057
Proj IDSTP 2017(955)
Work TypeACP OVERLAY
 
2.1921881273.200.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-22-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days80
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0035-05-057
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04173216
Totals1881273.200.000.000.0

CountyREAL
HighwayUS 83
FromRM 336
ToRM 337 IN LEAKEY
CSJ0036-05-033
Proj IDSTP 2015(350)
Work TypeREHABILITATE EXISTING ROAD
 
2.0556989144.865933289.4084.8
Work Order01-28-15
Work Began06-08-15
Work Completed
Time Computed05-29-15
Contract Working Days225
Addl Days Granted63
Working Days Charged286
Percent Time Used99
Contractor(s)
ALLEN KELLER COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0036-05-033
RELMCO, INC. (14.97)
FUQUAY, INC. (0.36)
PELTZ COMPANIES, INC. (26.55)
THE LEVY COMPANY, L.P. (0.36)
TEXAS CUTTING & CORING, INC. (1.33)
DELGADO"S CONSTRUCTION (1.01)
FLASHER EQUIPMENT COMPANY (1.16)
INCE ENTERPRISES, INC. (0.59)
Contract #12143021
Totals6989144.8659441.135933289.4084.8

CountySTERLING
HighwayUS 87
FromSH 158 IN STERLING CITY
ToCOKE COUNTY LINE
CSJ0069-04-042
Proj IDNH 2016(403)
Work TypeACP OVERLAY
 
15.7517904447.768327099.3199.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-01-16
Work Began06-01-16
Work Completed
Time Computed06-01-16
Contract Working Days102
Addl Days Granted7
Working Days Charged181
Percent Time Used166
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0069-04-042
BARRICADES UNLIMITED (1.60)
CONTRACTORS SERVICE COMPANY (0.26)
DOUBLE A CONTRACTING, L.P. (0.48)
HJC FARMS, INC. (7.08)
PERFORMANCE EQUIPMENT SERVICE (0.12)
PRIMATE CONSTRUCTION, INC. (1.21)
Contract #12153227
Totals7904447.760.008327099.3199.9

CountyTOM GREEN
HighwayUS 87
From9.8 MILES SOUTH OF COKE COUNTY LINE
To33RD STREET IN SAN ANGELO
CSJ0069-07-105
Proj IDNH 1702(026)
Work TypeACP OVERLAY
 
28.7655416629.760.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-07-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days126
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0069-07-105
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05173212
Totals5416629.760.000.000.0

CountyCONCHO
HighwayUS 87
FromTOM GREEN CO LINE
To16.724 MI S OF TOM GREEN CO LINE
CSJ0070-03-057
Proj IDSTP 1702(029)HES
Work TypeSAFETY TREATED FIXED OBJECTS
 
38.0041474796.260.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-14-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days163
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0070-03-057
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05173013
Totals1474796.260.000.000.0

CountyCONCHO ETC
HighwayUS 87 ETC
FromSANTA FE STREET IN EDEN
To1.1 MILES EAST OF US 83
CSJ0070-04-035
Proj IDNH 2017(328)
Work TypeSEAL COAT
 
219.6657317864.520.000.0
Work Order02-22-17
Work Began00-00-00
Work Completed
Time Computed06-01-17
Contract Working Days87
Addl Days Granted0
Working Days Charged26
Percent Time Used29
Contractor(s)
NORTHEASTERN PAVERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0070-04-035
FLAT LINE, INC. (5.11)
BARRICADES PLUS, LLC (0.98)
Contract #01173006
Totals7317864.520.000.000.0

CountyIRION
HighwayUS 67
From30.8 MI SOUTH OF TOM GREEN CO LINE
ToREAGAN COUNTY LINE
CSJ0077-02-031
Proj IDSTP 1502(413)
Work TypeADD PASSING LANES
 
41.24730896539.8031845255.3599.9
Work Order10-20-15
Work Began11-16-15
Work Completed
Time Computed11-16-15
Contract Working Days375
Addl Days Granted5
Working Days Charged337
Percent Time Used88
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0077-02-031
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.14)
COX PAVING COMPANY, L.P. (6.73)
PRIMATE CONSTRUCTION, INC. (0.45)
CONTRACTORS SERVICE COMPANY (0.38)
DOUBLE A CONTRACTING, L.P. (1.52)
HJC FARMS, INC. (1.26)
TEXOP CONSTRUCTION (1.23)
DELGADO"S CONSTRUCTION (0.97)
TITAN MILLING INC. (0.11)
Contract #07153003
Totals30896539.80494750.9431845255.3599.9

CountyTOM GREEN
HighwayUS 67
FromUS 87
ToSHERWOOD WAY
CSJ0077-06-095
Proj IDNH 1602(524)
Work TypeACP OVERLAY
 
5.4356339169.423430398.5954.1
Work Order12-12-16
Work Began03-20-17
Work Completed
Time Computed01-11-17
Contract Working Days175
Addl Days Granted14
Working Days Charged88
Percent Time Used46
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0077-06-095
CONTRACTORS SERVICE COMPANY (0.56)
KL DURHAM CONSTRUCTION, LLC (3.32)
PRIMATE CONSTRUCTION, INC. (1.54)
RPV CONSTRUCTION (3.66)
FLASHER EQUIPMENT COMPANY (1.84)
DOUBLE A CONTRACTING, L.P. (0.18)
T.C. TRUCKING & CONSTRUCTION, LLC (0.00)
Contract #11163207
Totals6339169.421562316.123430398.5954.1

CountyTOM GREEN
HighwayUS 67
FromSL 306
ToFM 2288
CSJ0077-06-098
Proj IDNH 1602(297)
Work TypeUPGRADE NON-FREEWAY
 
0.4003805303.542389663.5862.7
Work Order09-14-16
Work Began09-28-16
Work Completed
Time Computed12-13-16
Contract Working Days174
Addl Days Granted36
Working Days Charged141
Percent Time Used67
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0077-06-098
T.C. TRUCKING & CONSTRUCTION, LLC (1.58)
A BROTHERS MILLING, LLC (0.38)
DYNAMIC VISION CO., INC. (3.24)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.32)
CONTRACTORS SERVICE COMPANY (1.02)
FLASHER EQUIPMENT COMPANY (1.01)
WILLIS ELECTRIC CO., LP (21.83)
QUALITY STRIPING (0.07)
Contract #07163015
Totals3805303.54131555.542389663.5862.7

CountyCROCKETT
HighwayIH 10
From33.1 MI E OF PECOS COUNTY LINE
To38.0 MI E OF PECOS COUNTY LINE
CSJ0140-11-043
Proj IDNH 1602(298)
Work TypeUPGRADE FREEWAY
 
9.92314033551.4415157190.4099.9
Work Order09-06-16
Work Began10-24-16
Work Completed
Time Computed11-05-16
Contract Working Days220
Addl Days Granted20
Working Days Charged169
Percent Time Used70
Contractor(s)
KIEWIT INFRASTRUCTURE SOUTH CO.
SUBCONTRACTOR(S) FOR CCSJ: 0140-11-043
AARON CONCRETE CONTRACTORS, L.P. (6.86)
BRANNAN PAVING CO., LTD. (7.08)
CHEROKEE SERVICES (1.05)
DIAMOND SURFACE, INC. (0.09)
KIOWA PEAK INDUSTRIES INC (0.95)
SAENZ TRANSPORT, LLC (10.16)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.69)
DOUBLE A CONTRACTING, L.P. (1.52)
TEXOP CONSTRUCTION (1.71)
HJC FARMS, INC. (3.48)
RIVER CITY ENVIRONMENTAL, LLC (0.04)
Contract #07163215
Totals14033551.445873782.6515157190.4099.9

CountyCROCKETT
HighwayIH 10
From29.0 MI E OF PECOS COUNTY LINE
To33.1 MI E OF PECOS COUNTY LINE
CSJ0140-11-044
Proj IDNH 1702(546)
Work TypeUPGRADE FREEWAY
 
4.1434567928.750.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days75
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0140-11-044
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07173217
Totals4567928.750.000.000.0

CountyGLASSCOCK
HighwaySH 158
FromMIDLAND COUNTY LINE
To0.3 MILES WEST OF RM 33
CSJ0463-04-025
Proj IDNH 2016(901)
Work TypeACP OVERLAY
 
17.5878716678.759493474.4299.9
Work Order07-15-16
Work Began11-01-16
Work Completed
Time Computed09-14-16
Contract Working Days71
Addl Days Granted0
Working Days Charged128
Percent Time Used180
Contractor(s)
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0463-04-025
A BROTHERS MILLING, LLC (0.15)
BARRICADES UNLIMITED (1.66)
CONTRACTORS SERVICE COMPANY (0.14)
DOUBLE A CONTRACTING, L.P. (0.50)
HJC FARMS, INC. (0.58)
HUDSON, INC. (0.15)
LITTLE MANUFACTURING (0.09)
Contract #04163002
Totals8716678.75153493.109493474.4299.9

CountyCONCHO
HighwayFM 380
FromAT KICKAPOO CREEK
To.
CSJ0555-02-020
Proj IDBR 1602(525)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.1052162110.60577130.8326.6
Work Order09-26-16
Work Began02-13-17
Work Completed
Time Computed12-26-16
Contract Working Days135
Addl Days Granted0
Working Days Charged78
Percent Time Used57
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0555-02-020
BARRICADES UNLIMITED (0.64)
VOGES DRILLING CO. (3.41)
DOUBLE A CONTRACTING, L.P. (0.74)
Contract #08163218
Totals2162110.6062555.04577130.8326.6

CountyCONCHO
HighwayFM 765
FromUS 83
ToFM 2134
CSJ0870-04-039
Proj IDSTP 2017(033)
Work TypeRESTORATION OF EXISTING ROAD
 
7.9122858761.682333526.7081.6
Work Order10-27-16
Work Began01-03-17
Work Completed
Time Computed12-26-16
Contract Working Days174
Addl Days Granted5
Working Days Charged123
Percent Time Used68
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0870-04-039
CONTRACTORS SERVICE COMPANY (1.13)
HJC FARMS, INC. (1.25)
D.I.J. CONSTRUCTION, INC (2.49)
Contract #09163208
Totals2858761.68413117.762333526.7081.6

CountyCONCHO
HighwayFM 765
From0.2 MI EAST OF FM 2402
ToUS 83
CSJ0870-04-040
Proj IDSTP 1702(552)
Work TypeRESTORATION OF EXISTING ROAD
 
6.8592792437.520.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days165
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0870-04-040
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07173019
Totals2792437.520.000.000.0

CountyKIMBLE
HighwayVA
FromVARIOUS LOCATIONS IN KIMBLE CO.
To.
CSJ0907-20-006
Proj IDNH 2017(956)
Work TypeREPLACE AND REFURBISH LARGE SIGNS
 
0.0043089229.590.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-22-17
Work Began07-10-17
Work Completed
Time Computed07-10-17
Contract Working Days410
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
COLLINS & HERMANN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0907-20-006
SOUTHWEST DIGGER & ANCHOR SERVICES (5.91)
Contract #04173018
Totals3089229.590.000.000.0

CountyIRION
HighwayRL SO
FromRR MP 757
ToRR MP 776.9
CSJ7107-08-004
Proj IDNH 1702(336)
Work TypeINFRASTRUCTURE REHAB
 
53.4005357270.960.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days199
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BALFOUR BEATTY INFRASTRUCTURE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 7107-08-004
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06173235
Totals5357270.960.000.000.0