Monthly Local Let Maintenance Report For San Angelo District As Of Jul 14, 2017 Page 3 Of 4

Last Update: Monday, July 17, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyTOM GREEN
HighwayUS0067
FromPICNIC AREA MAINTENANCE AND SPECIAL LAND
ToPICNIC AREA MAINTENANCE AND SPECIAL LAND
CSJ6291-66-001
Proj IDSUP - 629166001
Work TypePICNIC AREA MAINTENANCE & LANDSC MOW
 
0.001255246.36203866.1479.8
Work Order09-01-15
Work Began00-00-00
Work Completed
Time Computed09-01-15
Contract Working Days730
Addl Days Granted0
Working Days Charged669
Percent Time Used91
Contractor(s)
TIBH INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6291-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08150704
Totals255246.368511.32203866.1479.8

CountyREAGAN
HighwayUS0067
FromSTATE USE JANITORIAL
ToBIG LAKE MAINTENANCE
CSJ6292-02-001
Proj IDSUP - 629202001
Work TypeSTATE USE JANITORIAL
 
0.00137306.8019245.6051.5
Work Order09-01-15
Work Began00-00-00
Work Completed
Time Computed09-01-15
Contract Working Days1,095
Addl Days Granted0
Working Days Charged22
Percent Time Used2
Contractor(s)
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6292-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08150706
Totals37306.80874.8019245.6051.5

CountyCONCHO
HighwayUS0087
FromEDEN MAINTENANCE
ToEDEN MAINTENANCE
CSJ6292-03-001
Proj IDSUP - 629203001
Work TypeSTATE USE JANITORIAL
 
0.00135776.8017496.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-01-15
Work Began00-00-00
Work Completed05-19-17
Time Computed09-01-15
Contract Working Days1,095
Addl Days Granted0
Working Days Charged20
Percent Time Used1
Contractor(s)
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6292-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08150707
Totals35776.800.0017496.00100.0

CountyKIMBLE
HighwayUS0083
FromJUNCTION MNT OFFICE
ToJUNCTION AREA OFFICE
CSJ6292-04-001
Proj IDSUP - 629204001
Work TypeJANITORIAL STATE USE SERVICES
 
0.00137907.1620266.8253.4
Work Order09-01-15
Work Began00-00-00
Work Completed
Time Computed09-01-15
Contract Working Days1,095
Addl Days Granted0
Working Days Charged22
Percent Time Used2
Contractor(s)
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6292-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08150708
Totals37907.16874.8020266.8253.4

CountyCROCKETT
HighwaySH0163
FromOZONA MAINTENANCE
ToOZONA MAINTENANCE
CSJ6292-05-001
Proj IDSUP - 629205001
Work TypeSTATE USE JANITORIAL SERVICES
 
0.00137117.6819245.6051.8
Work Order09-01-15
Work Began00-00-00
Work Completed
Time Computed09-01-15
Contract Working Days1,095
Addl Days Granted0
Working Days Charged21
Percent Time Used1
Contractor(s)
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6292-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08150709
Totals37117.68874.8019245.6051.8

CountyTOM GREEN
HighwaySH0208
FromSAN ANGELO AREA OFFICE
ToSAN ANGELO MAINTENANCE OFFICE
CSJ6292-06-001
Proj IDSUP - 629206001
Work TypeSTATE USE JANITIORAL SERVICIES
 
0.00188678.8049816.8056.1
Work Order09-01-15
Work Began00-00-00
Work Completed
Time Computed09-01-15
Contract Working Days1,095
Addl Days Granted0
Working Days Charged669
Percent Time Used61
Contractor(s)
MHMR SERVICES FOR THE CONCHO VALLEY
SUBCONTRACTOR(S) FOR CCSJ: 6292-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08150710
Totals88678.802264.4049816.8056.1

CountySUTTON
HighwayUS0277
FromSONORA MAINT OFFICE
ToSONORA MAINT OFFICE
CSJ6292-07-001
Proj IDSUP - 629207001
Work TypeSTATE USE JANITORIAL
 
0.00141300.5219188.4046.4
Work Order09-01-15
Work Began00-00-00
Work Completed
Time Computed09-01-15
Contract Working Days1,095
Addl Days Granted0
Working Days Charged20
Percent Time Used1
Contractor(s)
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6292-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08150711
Totals41300.52826.2019188.4046.4

CountySTERLING
HighwayUS0087
FromSTERLING CITY MAINT OFFICE
ToSTERLING CITY MAINT OFFICE
CSJ6292-08-001
Proj IDSUP - 629208001
Work TypeJANITORIAL SERVICES STATE USE
 
0.00134647.3019615.3556.6
Work Order09-01-15
Work Began00-00-00
Work Completed
Time Computed09-01-15
Contract Working Days1,095
Addl Days Granted0
Working Days Charged19
Percent Time Used1
Contractor(s)
TIBH INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6292-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08150712
Totals34647.30874.8019615.3556.6

CountyCOKE
HighwaySH0158
FromROBERT LEE
ToROBERT LEE
CSJ6292-09-001
Proj IDSUP - 629209001
Work TypeSTATE USE JANITORIAL SERVICES
 
0.00135082.1819665.3356.0
Work Order09-01-15
Work Began00-00-00
Work Completed
Time Computed09-01-15
Contract Working Days1,095
Addl Days Granted0
Working Days Charged20
Percent Time Used1
Contractor(s)
TIBH INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6292-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08150713
Totals35082.18874.8019665.3356.0

CountyEDWARDS
HighwayUS0377
FromROCKSPRINGS MAINT
ToROCKSPRINGS MAINT
CSJ6292-10-001
Proj IDSUP - 629210001
Work TypeJANITORIAL STATE USE
 
0.00125226.0414169.1156.1
Work Order09-01-15
Work Began00-00-00
Work Completed
Time Computed09-01-15
Contract Working Days1,095
Addl Days Granted0
Working Days Charged19
Percent Time Used1
Contractor(s)
TIBH INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6292-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08150714
Totals25226.04630.4114169.1156.1

CountyRUNNELS
HighwayUS0067
FromBALLINGER MAINT OFF
ToBALLINGER MAINT OFF
CSJ6292-11-001
Proj IDSUP - 629211001
Work TypeJANITORIAL SERVICES - STATE USE
 
0.00135146.4419640.8555.8
Work Order09-01-15
Work Began00-00-00
Work Completed
Time Computed09-01-15
Contract Working Days1,095
Addl Days Granted0
Working Days Charged49
Percent Time Used4
Contractor(s)
TIBH INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6292-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08150715
Totals35146.44874.8019640.8555.8

CountyMENARD
HighwayUS0083
FromMENARD MAINT
ToMENARD MAINT
CSJ6292-13-001
Proj IDSUP - 629213001
Work TypeJANTIORIAL STATE USE - MENARD
 
0.00134552.8019551.6056.5
Work Order09-01-15
Work Began00-00-00
Work Completed
Time Computed09-01-15
Contract Working Days1,095
Addl Days Granted0
Working Days Charged21
Percent Time Used1
Contractor(s)
TIBH INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6292-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08150717
Totals34552.80874.8019551.6056.5

CountyTOM GREEN
HighwayUS0067
FromTOM GREEN URBAN
ToTOM GREEN RURAL
CSJ6293-18-001
Proj IDSUP - 629318001
Work TypeLITTER PICKUP TOM GREEN URBAN-RURAL
 
0.001184632.50276709.5599.9
Work Order09-01-15
Work Began00-00-00
Work Completed
Time Computed09-01-15
Contract Working Days365
Addl Days Granted365
Working Days Charged669
Percent Time Used91
Contractor(s)
TIBH INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6293-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08150718
Totals184632.5010614.50276709.5599.9

CountyTOM GREEN
HighwayRM0584
FromSAN ANGELO DISTRICT SHOP
ToSAN ANGELO DISTRICT SHOP
CSJ6294-04-001
Proj IDSUP - 629404001
Work TypeDAY LABOR - OIL CHANGE AND CAR WASH
 
0.00141871.8472403.4099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days250
Addl Days Granted251
Working Days Charged21
Percent Time Used4
Contractor(s)
TIBH INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6294-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08150719
Totals41871.842916.5372403.4099.9

CountyKIMBLE
HighwayIH0010
FromVARIOUS LOCATIONS IN SAN ANGELO DISTRICT
ToVARIOUS LOCATIONS IN SAN ANGELO DISTRICT
CSJ6294-63-001
Proj IDRMC - 629463001
Work TypeMETAL BEAM GUARDFENCE
 
0.001302880.00515172.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted180
Working Days Charged208
Percent Time Used57
Contractor(s)
D & D ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6294-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10150701
Totals302880.000.00515172.0099.9

CountyTOM GREEN
HighwayRM0584
FromSAN ANGELO DISTRICT CAMPUS
ToSAN ANGELO DISTRICT CAMPUS
CSJ6296-97-001
Proj IDSUP - 629697001
Work TypeJANITORIAL STATE USE SAN ANGELO DISTRICT
 
0.001142163.2873146.4851.4
Work Order09-01-15
Work Began00-00-00
Work Completed
Time Computed09-01-15
Contract Working Days1,095
Addl Days Granted0
Working Days Charged19
Percent Time Used1
Contractor(s)
TIBH INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6296-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10150702
Totals142163.283123.3073146.4851.4

CountyTOM GREEN
HighwayUS0087
FromVARIOUS LOCATIONS IN SJT DISTRICT
To.
CSJ6299-57-001
Proj IDRMC - 629957001
Work TypeVERTICAL CLEARANCE SIGNS
 
0.001216450.00182145.0084.1
Work Order04-04-17
Work Began00-00-00
Work Completed
Time Computed04-10-17
Contract Working Days58
Addl Days Granted0
Working Days Charged54
Percent Time Used93
Contractor(s)
ODUM SERVICES, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6299-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02170701
Totals216450.0078600.00182145.0084.1

CountySTERLING
HighwayUS0087
FromVARIOUS ROADS STERLING GLASSCOCK
ToVARIOUS ROADS STERLING CLASSCOCK
CSJ6305-29-001
Proj IDRMC - 630529001
Work TypeRIGHT OF WAY MOWING STERLING GLASSCOCK
 
0.001161436.54161165.2499.8
Work Order11-09-16
Work Began00-00-00
Work Completed
Time Computed11-21-16
Contract Working Days65
Addl Days Granted65
Working Days Charged25
Percent Time Used19
Contractor(s)
SQUARE G, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6305-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07160701
Totals161436.5480718.27161165.2499.8

CountyREAGAN
HighwayUS0067
FromVARIOUS ROADS IN REAGAN IRION COUNTIES
ToVARIOUS ROADS IN REAGAN IRION COUNTIES
CSJ6305-30-001
Proj IDRMC - 630530001
Work TypeRIGHT OF WAY MOWING IN REAGAN IRION
 
0.001125514.48125514.4899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-09-16
Work Began00-00-00
Work Completed
Time Computed11-14-16
Contract Working Days50
Addl Days Granted50
Working Days Charged23
Percent Time Used23
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6305-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07160702
Totals125514.480.00125514.4899.9

CountyIRION
HighwayRM0853
FromSTA 599+11 TRM 364+1.31
ToSTA 600-47 TRM 364+134
CSJ6310-15-001
Proj IDRMC - 631015001
Work TypeREPLACEMENT OF CONCRETE PAVEMENT
 
0.02582820.0073352.0088.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted0
Working Days Charged25
Percent Time Used55
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6310-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10160702
Totals82820.000.0073352.0088.5

page 1 | page 2 | page 3 | page 4