Monthly State Let Maintenance Report For San Angelo District As Of Aug 16, 2016 Page 1 Of 1

Last Update: Tuesday, August 16, 2016
FTP Icon
page 1

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyKIMBLE
Highway 0000000
From 2124 NORTH MAIN (LOOP 481), JUNCTION
To .
CSJ 4704-01-167
Proj ID CBC - 470401167
Work Type JIM TATE PROJECT MANAGER
 
0.001 1209888.00 0.00 1003145.00 82.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 270
Addl Days Granted 53
Working Days Charged 262
Percent Time Used 81
Contractor(s)
KENDNEL KASPER CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-167
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07144217
Totals 1209888.00 0.00 1003145.00 82.9

CountyTOM GREEN
Highway 0000000
From 4502 KNICKERBOCKER RD
To SAN ANGELO TX
CSJ 4704-01-685
Proj ID CBC - 470401685
Work Type RENOVATION AND REPAIR
 
0.001 769600.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CS ADVANTAGE USAA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-685
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08164223
Totals 769600.00 0.00 0.00 0.0

CountySUTTON
Highway RM1312
From IRION COUNTY
To SUTTON COUNTY
CSJ 6205-40-001
Proj ID RMC - 620540001
Work Type INSTALL BRIDGE RAIL & GUARD RAIL END TRE
 
0.001 308769.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 70
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
K-BAR SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6205-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04104022
Totals 308769.00 0.00 0.00 0.0

CountyCROCKETT
Highway SH0163
From VARIOUS LOCATIONS IN CROCKETT COUNTY
To VARIOUS LOCATIONS IN CROCKETT COUNTY
CSJ 6232-09-001
Proj ID RMC - 623209001
Work Type STRIP MOWING OF RIGHT OF WAY CROCKETT CO
 
0.001 103536.00 0.00 51768.00 50.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-07-12
Work Began 06-01-12
Work Completed  
Time Computed 06-01-12
Contract Working Days 44
Addl Days Granted 0
Working Days Charged 9
Percent Time Used 20
Contractor(s)
SPARKLES TRUCKING
SUBCONTRACTOR(S) FOR CCSJ: 6232-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10114005
Totals 103536.00 0.00 51768.00 50.0

CountyTOM GREEN
Highway US0067
From VARIOUS LOCATIONS IN TOM GREEN URBAN
To VARIOUS LOCATIONS IN TOM GREEN URBAN
CSJ 6245-64-001
Proj ID RMC - 624564001
Work Type RIGHT OF WAY MOWING FOR TOM GREEN URBAN
 
0.001 167384.88 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 24
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SQUARE G, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6245-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08124031
Totals 167384.88 0.00 0.00 0.0

CountyIRION
Highway US0067
From .
To .
CSJ 6270-54-001
Proj ID RMC - 627054001
Work Type WIDENING PAVEMENT
 
0.875 458840.69 0.00 456864.32 99.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-20-14
Work Began 06-30-14
Work Completed  
Time Computed 06-30-14
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 41
Percent Time Used 91
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6270-54-001
CONTRACTORS SERVICE COMPANY(1.06%)
BARRICADES UNLIMITED (4.05%)
ALTEX LANDSCAPE CONSTRUCTION, INC. (2.33%)
Contract # 05144033
Totals 458840.69 0.00 456864.32 99.5

CountyTOM GREEN
Highway US0277
From VARIOUS ROADWAYS IN SJT DISTRICT
To VARIOUS ROADWAYS IN SJT DISTRICT
CSJ 6273-17-001
Proj ID RMC - 627317001
Work Type RETRACE PAVEMENT MARKINGS AND MARKERS
 
108.353 351907.60 0.00 351907.60 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 03-02-15
Work Completed 06-08-15
Time Computed 00-00-00
Contract Working Days 49
Addl Days Granted 0
Working Days Charged 36
Percent Time Used 73
Contractor(s)
VIZCAINO, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6273-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10144202
Totals 351907.60 0.00 351907.60 100.0

CountyTOM GREEN
Highway US0087
From VARIOUS LOCATIONS IN SAN ANGELO DISTRICT
To VARIOUS LOCATIONS IN SAN ANGELO DISTRICT
CSJ 6279-27-001
Proj ID RMC - 627927001
Work Type ON - CALL TRAFFIC CONTROL SERVICES
 
0.001 777700.00 0.00 2404031.25 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 02-17-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 365
Working Days Charged 107
Percent Time Used 14
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6279-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11144006
Totals 777700.00 0.00 2404031.25 99.9

CountyCROCKETT
Highway SH0290
From SH 290 CROCKETT COUNTY
To .
CSJ 6280-63-001
Proj ID RMC - 628063001
Work Type REPAIRING RETAINING WALL
 
0.074 1018552.00 0.00 1038179.56 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 03-30-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 85
Addl Days Granted 0
Working Days Charged 68
Percent Time Used 80
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6280-63-001
GEOSTABILIZATION INTERNATIONAL, LLC( 61.56%)
C.E. COOK & SONS, INC. (7.39%)
ARTISTIC CONCRETE & MASONRY(2.43%)
Contract # 01154219
Totals 1018552.00 0.00 1038179.56 99.9

CountyTOM GREEN
Highway US0277
From COKE COUNTY LINE
To 0.03 MILES SOUTH OF OLD BALLINGER HWAY
CSJ 6280-70-001
Proj ID RMC - 628070001
Work Type SEAL COAT
 
64.800 2305233.29 0.00 2594078.85 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 05-26-15
Work Completed 08-01-15
Time Computed 00-00-00
Contract Working Days 103
Addl Days Granted 0
Working Days Charged 77
Percent Time Used 74
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6280-70-001
STRIPE-A-ZONE, INC.(6.53%)
BRYDL CONTRACTING, INC.(0.84%)
Contract # 12144201
Totals 2305233.29 0.00 2594078.85 100.0

CountyKIMBLE
Highway RM1674
From FROM 2.8 MILES NORTH OF IH 10
To 3 MILES NORTH
CSJ 6281-45-001
Proj ID RMC - 628145001
Work Type ROADWAY WIDENING
 
3.000 1003498.95 232414.44 766291.64 76.3
Work Order 04-29-16
Work Began 00-00-00
Work Completed  
Time Computed 05-02-16
Contract Working Days 86
Addl Days Granted 11
Working Days Charged 54
Percent Time Used 55
Contractor(s)
ALLEN KELLER COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6281-45-001
D.I.J. CONSTRUCTION, INC (2.99%)
TEXAS ALTERNATIVE GRASSER, INC. (BOWIE)(0.19%)
Contract # 03164202
Totals 1003498.95 232414.44 766291.64 76.3

CountyKIMBLE
Highway IH0010
From VARIOUS
To VARIOUS
CSJ 6286-51-001
Proj ID RMC - 628651001
Work Type CLEANING AND SEALING JOINTS AND CRACKS
 
595.200 474106.09 0.00 488214.83 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 8
Percent Time Used 17
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6286-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08154208
Totals 474106.09 0.00 488214.83 99.9

CountyKIMBLE
Highway IH0010
From VARIOUS LOCATIONS IN SAN ANGELO DISTRICT
To VARIOUS LOCATIONS IN SAN ANGELO DISTRICT
CSJ 6289-21-001
Proj ID RMC - 628921001
Work Type METAL BEAM GUARDFENCE
 
0.001 319646.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 180
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CKORP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6289-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08154210
Totals 319646.00 0.00 0.00 0.0

CountyIRION
Highway FM0072
From VARIOUS LOCATIONS IN SJT DISTRICT
To .
CSJ 6289-36-001
Proj ID RMC - 628936001
Work Type SEAL COAT
 
39.084 1354977.37 0.00 1483335.84 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 39
Addl Days Granted 3
Working Days Charged 36
Percent Time Used 85
Contractor(s)
RONALD R. WAGNER & CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 6289-36-001
FLASHER EQUIPMENT COMPANY(8.85%)
Contract # 11154203
Totals 1354977.37 0.00 1483335.84 99.9

CountyTOM GREEN
Highway US0067
From VARIOUS ROADWAYS IN SJT DISTRICT
To VARIOUS ROADWAYS IN SJT DISTRICT
CSJ 6298-89-001
Proj ID RMC - 629889001
Work Type RETRACE PAVEMENT MARKINGS AND MARKERS
 
66.800 682612.34 251766.16 382848.82 56.0
Work Order 05-16-16
Work Began 06-11-16
Work Completed  
Time Computed 05-26-16
Contract Working Days 93
Addl Days Granted 0
Working Days Charged 42
Percent Time Used 45
Contractor(s)
FLASHER EQUIPMENT COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6298-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03164201
Totals 682612.34 251766.16 382848.82 56.0

page 1