Monthly State Let Construction Report For Tyler District As Of Jan 13, 2015 Page 1 Of 3

Last Update: Tuesday, January 13, 2015
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyWOOD
Highway SH 11 ETC
From .2 MI N OF FM 852 IN WINNSBORO, E
To 0.6 MI E OF FM 1647 (CAMP C/L)
CSJ 0083-06-038
Proj ID STP 2015(312)
Work Type SEAL COAT & PAVEMENT MARKINGS
 
268.064 8548703.60 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 91
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CDM HOLDINGS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0083-06-038
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11143203
Totals 8548703.60 0.00 0.00 0.0

CountyVAN ZANDT
Highway US 80 ETC
From 3.2 MI W OF FM 2965 (KAUFMAN C/L),E
To 0.7 MI E OF SH 64 IN WILLS POINT
CSJ 0095-06-064
Proj ID STP 2014(205)
Work Type SEAL COAT & PAVEMENT MARKINGS
 
155.152 7401723.84 0.00 7205411.31 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-05-13
Work Began 06-02-14
Work Completed 10-23-14
Time Computed 06-01-14
Contract Working Days 91
Addl Days Granted 0
Working Days Charged 69
Percent Time Used 75
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0095-06-064
FLAT LINE, INC.( 11.94%)
RED SIXTEEN CONSTRUCTION, INC. (0.96%)
Contract # 11133022
Totals 7401723.84 0.00 7205411.31 100.0

CountyGREGG
Highway US 80
From 0.35 MI E OF SH 42 IN WHITE OAK, E
To 1.4 MI W OF SL 281(FISHER RD)IN LVW
CSJ 0096-04-065
Proj ID STP 2013(206)
Work Type GR, BS, HMAC SURF, STRM SWR, C & G, SIGNS
 
1.558 3482669.95 36918.46 3344540.03 100.0
Work Order 01-31-13
Work Began 02-18-13
Work Completed 12-18-14
Time Computed 02-16-13
Contract Working Days 221
Addl Days Granted 13
Working Days Charged 222
Percent Time Used 94
Contractor(s)
REYNOLDS & KAY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0096-04-065
RICE ENVIRONMENTAL SERVICES(0.75%)
COWBELL TRAFFIC SERVICES, INC. (0.38%)
DUSTROL, INC.(1.15%)
G & L FLOWERS TRUCKING (2.00%)
STRIPING TECHNOLOGY, L.P.(1.14%)
ROBINSON CONSTRUCTION(3.63%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.13%)
Contract # 12123218
Totals 3482669.95 36918.46 3344540.03 100.0

CountyHENDERSON
Highway SH 19
From 4.1 MI N OF FM 837 (CR 468N), N
To 3.5 MI S OF FM 1615 (COON CRK BRG)
CSJ 0108-05-014
Proj ID C 108-5-14
Work Type GR, STRS, HMA BS & SURF, OCST, LVL - UP
 
4.636 6385017.81 104109.50 6214113.72 100.0
Work Order 10-18-12
Work Began 11-19-12
Work Completed 12-17-14
Time Computed 11-03-12
Contract Working Days 265
Addl Days Granted 18
Working Days Charged 287
Percent Time Used 101
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0108-05-014
HIGHWAY TECHNOLOGIES, INC. (0.29%)
COX PAVING COMPANY, L.P. (4.37%)
D. I. J. CONSTRUCTION, INC.(1.01%)
FORTSON CONTRACTING, INC.(1.50%)
3LW MANAGEMENT, LLC(9.06%)
CF SOUTHWEST ENVIRONMENT SERVICES LLC(1.51%)
Contract # 08123224
Totals 6385017.81 104109.50 6214113.72 100.0

CountyANDERSON
Highway SH 19
From 3.6 MI N OF FM 837(HENDERSON C/L),S
To 0.4 MI N OF FM 321 AT MONTALBA
CSJ 0108-06-051
Proj ID STP 2013(637)
Work Type GR, STRS, HMA BS & SURF, OCST, LVL - UP
 
11.813 12487715.87 36981.15 1210121.22 9.6
Work Order 07-10-14
Work Began 09-02-14
Work Completed  
Time Computed 07-26-14
Contract Working Days 453
Addl Days Granted 0
Working Days Charged 66
Percent Time Used 14
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0108-06-051
COLD CREEK CONSTRUCTION, LTD (0.82%)
FORTSON CONTRACTING, INC.(0.45%)
HIGHWAY 19 CONSTRUCTION, LLC ( 10.97%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.35%)
SAMMY G. SMALLWOOD (0.46%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.15%)
STRIPING TECHNOLOGY, L.P.(1.23%)
Contract # 05143205
Totals 12487715.87 36981.15 1210121.22 9.6

CountyRUSK
Highway US 84
From 1.1 MI W OF FM 3055, E
To 0.2 MI W OF US 259 IN MT ENTERPRISE
CSJ 0123-05-014
Proj ID STP 2015(531)
Work Type ACP BS & SURF, PVT MRKG
 
1.800 1077700.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0123-05-014
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01153021
Totals 1077700.00 0.00 0.00 0.0

CountyGREGG
Highway SH 31
From 0.5 MI S OF FM 2205 IN LONGVIEW, N
To 0.45 MI S OF US 80 (SOUTH ST)
CSJ 0138-01-095
Proj ID NH 2013(911)
Work Type IRRIGATION, PLANTING BED PREP, PLANTS
 
2.025 189035.00 0.00 200498.50 99.9
Work Order 09-16-13
Work Began 10-21-13
Work Completed  
Time Computed 10-02-13
Contract Working Days 28
Addl Days Granted 0
Working Days Charged 22
Percent Time Used 78
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0138-01-095
ALTUS TRAFFIC MANAGEMENT LLC (1.56%)
TX DOWN UNDER CONSTRUCTION LLC (6.10%)
Contract # 08133225
Totals 189035.00 0.00 200498.50 99.9

CountyRUSK
Highway US 259
From AT FM 1798, NEAR MINDEN
To .
CSJ 0138-05-052
Proj ID STP 1102(218)SB
Work Type GR, STRS, FLX & ACP BS, SURF, SIGN, ILUMTN
 
0.766 5497236.41 44055.02 5625151.05 99.9
Work Order 08-11-11
Work Began 06-04-12
Work Completed  
Time Computed 01-02-12
Contract Working Days 263
Addl Days Granted 60
Working Days Charged 291
Percent Time Used 90
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0138-05-052
AMERICAN REMEDIATION OPTIONS, INC. (2.09%)
STRIPING TECHNOLOGY, L.P.(2.83%)
COWBELL TRAFFIC SERVICES, INC. (0.09%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.05%)
SCOTT DERR PAINTING CO, LLC(0.10%)
PANOLA SIGN & BARRICADE, INC.(0.23%)
MAC TRANSPORTATION, LTD, L.L.P.(3.32%)
MESA ROD BUSTERS, INC. (0.07%)
R & R TELCO ENTERPRISES, INC.(0.12%)
DUSTROL, INC.(0.00%)
Contract # 06113241
Totals 5497236.41 44055.02 5625151.05 99.9

CountyGREGG
Highway SH 31
From 0.3 MI N OF FM 2205 (GRACE CRK), N
To 0.2 MI S OF US 80(COTTON) IN LONGVW
CSJ 0138-08-026
Proj ID STP 1402(088)
Work Type FENCE, WELCOME SIGN, PLANTINGS
 
0.278 281249.70 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 52
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SOUTH TEXAS ILLUMINATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0138-08-026
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12143232
Totals 281249.70 0.00 0.00 0.0

CountyGREGG
Highway FM 2208
From AT SMELLEY/HOLLYBROOK INTERSECTION
To 0.14 MI N OF SL 281 N RAMP
CSJ 0138-15-010
Proj ID STP 2014(917)
Work Type SIGNAL
 
0.100 144010.50 0.00 140513.65 97.5
CountyGREGG
Highway FM 2208
From 0.4 MI N OF SL 281 (HARRISON C/L),S
To SL 281 N RAMP IN LONGVIEW
CSJ 0138-15-011
Proj ID CC 138-15-11
Work Type GR, ACP, OCST, C & G
 
0.371 397810.77 4955.13 368328.28 92.5
Work Order 08-13-14
Work Began 09-15-14
Work Completed  
Time Computed 08-29-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 59
Percent Time Used 98
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0138-15-010
SOUTHWEST ENVIRONMENT SERVICES LLC (1.00%)
PANOLA SIGN & BARRICADE, INC.(0.74%)
MAC TRANSPORTATION, LTD, L.L.P.(3.85%)
STRIPING TECHNOLOGY, L.P.( 24.55%)
TEX OP CONSTRUCTION, LP(0.97%)
Contract # 07143022
Totals 541821.27 4955.13 508841.93 93.9

CountyGREGG
Highway US 259
From AT SYNERGY DR IN KILGORE
To 0.3 MI N OF FM 349
CSJ 0138-16-003
Proj ID NH 2013(912)
Work Type SBG WDN, HMAC BS & SURF, OCST, MBGF, SIGN
 
0.317 489748.16 0.00 445950.17 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-09-13
Work Began 03-19-14
Work Completed 10-24-14
Time Computed 03-17-14
Contract Working Days 29
Addl Days Granted 0
Working Days Charged 28
Percent Time Used 96
Contractor(s)
REYNOLDS & KAY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0138-16-003
ALTUS TRAFFIC MANAGEMENT LLC (0.69%)
STRIPING TECHNOLOGY, L.P.(3.69%)
DUSTIN ALLEN, INC. (2.12%)
TEX OP CONSTRUCTION, LP(1.19%)
SOUTHWEST ENVIRONMENT SERVICES LLC (2.71%)
GREGG WILLIAMS CONSTRUCTION(0.09%)
Contract # 08133040
Totals 489748.16 0.00 445950.17 100.0

CountyHENDERSON
Highway SH 31
From 0.34 MI W OF FM 773 (BEG C&G), E
To 1.1 MI W OF FM 1803(W) IN MURCHISON
CSJ 0164-01-068
Proj ID STP 2013(549)
Work Type PVMT RPR, PLNG, CAM, OCST, HARST, HMAC
 
7.862 4945961.90 0.00 4665412.52 95.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-26-13
Work Began 08-12-13
Work Completed  
Time Computed 07-12-13
Contract Working Days 52
Addl Days Granted 0
Working Days Charged 92
Percent Time Used 176
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0164-01-068
DUSTROL, INC.(4.44%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.13%)
PENHALL COMPANY(0.14%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.21%)
STRIPING TECHNOLOGY, L.P.(2.94%)
VIKING CONSTRUCTION, INC.( 12.69%)
COX PAVING COMPANY, L.P. (4.71%)
Contract # 04133218
Totals 4945961.90 0.00 4665412.52 95.1

CountyWOOD
Highway SH 37
From 0.4 MI S OF FM 515 IN WINNSBORO, S
To FM 2088 IN QUITMAN
CSJ 0190-02-038
Proj ID STP 2015(534)
Work Type PVT RPR, PLNG, OCST, HMAC SURF, PVT MRK
 
13.893 7688421.61 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0190-02-038
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01153202
Totals 7688421.61 0.00 0.00 0.0

CountySMITH
Highway US 69
From 0.2 MI S OF CUMBERLAND RD,S 0.57 MI
To 0.66 MI N OF TOLL 49
CSJ 0191-01-082
Proj ID CC 191-1-82
Work Type GR, STR, FLX BS, PVMT, SIGNS, SIGS, STRPG
 
0.567 2021972.96 13026.55 1973368.95 97.7
Work Order 03-13-14
Work Began 05-05-14
Work Completed  
Time Computed 03-29-14
Contract Working Days 107
Addl Days Granted 0
Working Days Charged 112
Percent Time Used 104
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0191-01-082
TOTAL HIGHWAY MAINTENANCE, LLC (0.22%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.04%)
STRIPING TECHNOLOGY, L.P.(1.30%)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.( 17.94%)
J & M CONTRACTING, COMPANY (2.02%)
TEX OP CONSTRUCTION, LP(4.56%)
Contract # 01143020
Totals 2021972.96 13026.55 1973368.95 97.7

CountyHENDERSON
Highway US 175
From 0.1 MI SE OF FM 804, SE
To CR 4712 (END OF C-S)
CSJ 0198-01-023
Proj ID NH 1402(195)
Work Type RECONSTR GR, STRS, BS, SURF & PAV M
 
6.695 39261003.89 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-21-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 605
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
A. L. HELMCAMP, INC.
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0198-01-023
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143055
Totals 39261003.89 0.00 0.00 0.0

CountyWOOD
Highway US 69
From 0.6 MI NW OF FM 779 IN GOLDEN, SE
To SL 564 IN MINEOLA
CSJ 0203-05-037
Proj ID C 203-5-37
Work Type GR, STRS, ACP BS & SURF, PVT MRK
 
4.207 2817127.02 27198.14 2665028.74 95.0
Work Order 08-09-13
Work Began 09-10-13
Work Completed  
Time Computed 08-25-13
Contract Working Days 84
Addl Days Granted 0
Working Days Charged 101
Percent Time Used 120
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0203-05-037
BUYERS BARRICADES, INC.(0.66%)
AMERICAN REMEDIATION OPTIONS, INC. (2.07%)
WEST TEXAS RUMBLE STRIP(0.13%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.46%)
STRIPING TECHNOLOGY, L.P.(1.80%)
MAC TRANSPORTATION, LTD, L.L.P.(7.48%)
P.R. PARKER COMPANY, INC.(0.42%)
TEX OP CONSTRUCTION, LP(0.38%)
Contract # 06133223
Totals 2817127.02 27198.14 2665028.74 95.0

CountyANDERSON
Highway US 79
From 1.6 MI SW OF LP 256 IN PALESTINE, S
To 0.4 MI SW OF FM 645
CSJ 0205-07-043
Proj ID NH 2008(510)
Work Type GR, BS, ASPH PVT, SIGS, ILLUM, SIGNS
 
8.601 41986850.19 474983.87 19747842.26 47.0
Work Order 10-24-12
Work Began 11-12-12
Work Completed  
Time Computed 11-09-12
Contract Working Days 880
Addl Days Granted 0
Working Days Charged 523
Percent Time Used 59
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0205-07-043
HIGHWAY TECHNOLOGIES, INC. (0.10%)
STRIPING TECHNOLOGY, L.P.(1.65%)
MAC TRANSPORTATION, LTD, L.L.P.(3.12%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.39%)
AMERICAN REMEDIATION OPTIONS, INC. (0.53%)
DANRIDGE CONSTRUCTION, LLC.(0.30%)
DUSTROL, INC.(0.20%)
WEST TEXAS RUMBLE STRIP(0.05%)
CF SOUTHWEST ENVIRONMENT SERVICES LLC(1.30%)
NORTH TEXAS REBAR, LLC (0.02%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.23%)
P.R. PARKER COMPANY, INC.(0.02%)
Contract # 09123003
Totals 41986850.19 474983.87 19747842.26 47.0

CountySMITH
Highway SH 64
From 0.1 MI W OF FM 2661, E
To 0.6 MI W OF FM 724 (NEAR CR 1184)
CSJ 0245-05-046
Proj ID STP 2013(225)
Work Type GR, SURF, BASE, ACP, PVT MRKG
 
1.191 2387571.56 0.00 2304122.37 96.5
Work Order 07-08-13
Work Began 08-05-13
Work Completed  
Time Computed 07-24-13
Contract Working Days 106
Addl Days Granted 0
Working Days Charged 106
Percent Time Used 100
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0245-05-046
HIGHWAY 19 CONSTRUCTION, LLC ( 25.78%)
STRIPING TECHNOLOGY, L.P.(1.24%)
MARCOM"S MOWING SERVICE, LLC (0.81%)
SOUTHWEST ENVIRONMENT SERVICES LLC (2.36%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.32%)
Contract # 05133033
Totals 2387571.56 0.00 2304122.37 96.5

CountySMITH
Highway SH 64
From FM 3226 SE OF CHAPEL HILL, SE
To SH 135 NEAR ARP
CSJ 0245-06-076
Proj ID STP 2014(590)
Work Type GR, STRS, FLX BS, LVL - UP, OCST, HMAC SRF
 
8.294 3872443.98 145287.12 781748.63 20.1
Work Order 06-30-14
Work Began 08-21-14
Work Completed  
Time Computed 07-16-14
Contract Working Days 125
Addl Days Granted 0
Working Days Charged 53
Percent Time Used 42
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0245-06-076
PANOLA SIGN & BARRICADE, INC.(0.60%)
DREWERY & WHEATON, LLC (2.51%)
J & M CONTRACTING, COMPANY ( 10.08%)
COWBELL TRAFFIC SERVICES, INC. (0.35%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.90%)
STRIPING TECHNOLOGY, L.P.(1.96%)
TEX OP CONSTRUCTION, LP(0.52%)
DREWERY BROS TREE SERVICE, INC.(1.72%)
Contract # 04143017
Totals 3872443.98 145287.12 781748.63 20.1

CountyRUSK
Highway SH 64
From 0.17 MI W OF BS 64E IN HENDERSON,E
To 0.2 MI W OF US79/US259 (N MARSHALL)
CSJ 0245-08-040
Proj ID STP 2013(913)
Work Type GR, STRS, PLNG, HMA BS, C & G, SURF, PV MKG
 
0.338 2102152.24 0.00 766416.41 36.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-08-13
Work Began 10-11-13
Work Completed  
Time Computed 08-24-13
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 107
Percent Time Used 107
Contractor(s)
L. S. EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0245-08-040
STRIPING TECHNOLOGY, L.P.(6.47%)
ROBINSON CONSTRUCTION( 11.78%)
REYNOLDS & KAY, LTD. (8.20%)
TEX OP CONSTRUCTION, LP(0.66%)
Contract # 07133246
Totals 2102152.24 0.00 766416.41 36.7