Monthly State Let Construction Report For Tyler District As Of Jul 11, 2014 Page 3 Of 3

Last Update: Friday, July 11, 2014
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyGREGG
Highway LP 281
From 101 FT E OF FM 2206, E 562 FT
To 663 FT E OF FM 2206 IN LONGVIEW
CSJ 1763-02-029
Proj ID CC 1763-2-29
Work Type SBGRD WDN, ACP BS & SURF, OCST, C & G, PVMK
 
0.106 135005.11 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-15-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1763-02-029
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03143013
Totals 135005.11 0.00 0.00 0.0

CountyGREGG
Highway LP 281
From SH 31 IN LONGVIEW, S
To 0.42 MI S OF FM 2087
CSJ 1763-03-029
Proj ID STP 1102(227)RGS
Work Type GR, STRS, HMAC BS, CONC PVT, C & G, SIGNLS
 
1.680 13235356.95 466991.58 4666762.93 35.2
Work Order 09-27-11
Work Began 03-18-13
Work Completed  
Time Computed 03-01-12
Contract Working Days 575
Addl Days Granted 0
Working Days Charged 176
Percent Time Used 30
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1763-03-029
PANOLA SIGN & BARRICADE, INC.(0.27%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.97%)
MAC TRANSPORTATION, LTD, L.L.P.(3.61%)
SCOTT DERR PAINTING CO, LLC(0.04%)
STRIPING TECHNOLOGY, L.P.(5.45%)
DUSTIN ALLEN, INC. (0.16%)
TEX OP CONSTRUCTION, LP(0.53%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.76%)
DIAMOND H SERVICES, INC. (0.03%)
DUKE IRRIGATION(0.00%)
Contract # 08113205
Totals 13235356.95 466991.58 4666762.93 35.2

CountySMITH
Highway LP 323
From US 69 (N) IN TYLER, E
To LP323,.5 MI E OF US271(AMER LEG RD)
CSJ 2075-01-053
Proj ID NH 2013(466)
Work Type OCST, 2" OVERLAY
 
3.985 1965643.25 -970.00 2005837.18 99.9
CountySMITH
Highway LP 323
From US 69 (N) IN TYLER, E
To LP323,.5 MI E OF US271(AMER LEG RD)
CSJ 2075-01-056
Proj ID NH 2013(466)
Work Type OCST, 2" OVERLAY
 
3.985 1828463.02 48036.35 1854335.41 99.9
Work Order 06-12-13
Work Began 07-16-13
Work Completed  
Time Computed 06-28-13
Contract Working Days 50
Addl Days Granted 0
Working Days Charged 82
Percent Time Used 164
Contractor(s)
REYNOLDS & KAY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2075-01-053
TOTAL HIGHWAY MAINTENANCE, LLC (0.32%)
ODUM SERVICES, L.P.(1.44%)
DUSTROL, INC.(1.30%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.12%)
STRIPING TECHNOLOGY, L.P.(2.01%)
J & I TRUCKING CO(0.65%)
Contract # 03133207
Totals 3794106.27 47066.35 3860172.59 99.9

CountySMITH
Highway LP 323
From SH 31 (W) IN TYLER, N 0.295 MI
To ELM ST
CSJ 2075-01-055
Proj ID C 2075-1-55
Work Type GR, ACP BS & SURF, PVT MRKG
 
0.295 1520796.14 0.00 143910.25 9.4
CountySMITH
Highway LP 323
From 0.6 MI S OF SH 31 (SHAW ST), N
To SH 31 (W) IN TYLER
CSJ 2075-02-045
Proj ID C 2075-2-45
Work Type REPLACE EXISTING RAILROAD UNDERPASS
 
0.637 10467992.74 319183.36 858136.99 8.1
Work Order 05-09-14
Work Began 05-19-14
Work Completed  
Time Computed 02-03-14
Contract Working Days 459
Addl Days Granted 0
Working Days Charged 31
Percent Time Used 6
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2075-02-045
STRIPING TECHNOLOGY, L.P.(3.86%)
PANOLA SIGN & BARRICADE, INC.(0.42%)
FORTSON CONTRACTING, INC.(0.46%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.01%)
TEX OP CONSTRUCTION, LP(0.27%)
ATS DRILLING, INC. (4.48%)
MAC TRANSPORTATION, LTD, L.L.P.(2.87%)
MCL CONTRACTING, LLC (0.30%)
Contract # 11133219
Totals 11988788.88 319183.36 1002047.24 8.3

CountyGREGG
Highway FM 2275
From MCCANN RD, 0.1 MI N OF GRAYSTONE, E
To SS 502,0.6 MI S OF FM 1844 IN LNGVW
CSJ 2158-01-013
Proj ID C 2158-1-13
Work Type GR, STRS, ACP BS & SURF, CONC PVT, OCST
 
2.400 12884788.32 0.00 1785755.69 13.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-18-14
Work Began 04-01-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 360
Addl Days Granted 0
Working Days Charged 37
Percent Time Used 10
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2158-01-013
SOUTHWEST ENVIRONMENT SERVICES LLC (1.25%)
REYNOLDS & KAY, LTD. (1.99%)
LONE STAR BARRIER SERVICES, LLC(0.19%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.72%)
STRIPING TECHNOLOGY, L.P.(4.06%)
SOTO"S STEEL (0.04%)
STRINGFELLOW LOGGING (0.00%)
Contract # 01143203
Totals 12884788.32 0.00 1785755.69 13.8

CountySMITH
Highway SP 364
From SH 31, SE
To SL 323 IN TYLER
CSJ 2833-01-011
Proj ID STP 2013(683)
Work Type 2" MILL, OCST, 2' INLAY
 
6.922 2870170.33 5682.24 2842007.68 99.1
Work Order 07-08-13
Work Began 08-12-13
Work Completed  
Time Computed 07-24-13
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 105
Percent Time Used 105
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2833-01-011
FORTSON CONTRACTING, INC.(2.50%)
HIGHWAY 19 CONSTRUCTION, LLC (6.21%)
MARCOM"S MOWING SERVICE, LLC (0.28%)
STRIPING TECHNOLOGY, L.P.(2.24%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.98%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.78%)
Contract # 05133236
Totals 2870170.33 5682.24 2842007.68 99.1

page 1 | page 2 | page 3