Monthly State Let Construction Report For Tyler District As Of Jan 11, 2016 Page 3 Of 4

Last Update: Tuesday, January 12, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyCHEROKEE
Highway FM 22
From US 69 S OF JACKSONVILLE, SW
To 1.5 MI W OF FM 768(N)(GAL'N CTY LM)
CSJ 0634-01-011
Proj ID SSW 634-01-011
Work Type SBGR WDN, ACP BS & SURF, OCST, STRS, SIGN
 
14.256 7730087.27 0.00 292080.00 3.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-13-15
Work Began 12-15-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 138
Addl Days Granted 0
Working Days Charged 10
Percent Time Used 7
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0634-01-011
DUSTIN ALLEN, INC. (1.90%)
HEMPHILL PILE DRIVING CO., A CORP. (0.42%)
STRIPE-A-ZONE, INC.(2.41%)
SOUTHWEST ENVIRONMENT SERVICES LLC (7.81%)
PANOLA SIGN & BARRICADE, INC.(0.47%)
BAHENA CONSTRUCTION CO.,INC. ( 10.90%)
UNIVERSAL LAND CLEARING(1.42%)
Contract # 06153215
Totals 7730087.27 0.00 292080.00 3.7

CountyGREGG
Highway FM 449
From US 259 N OF LONGVIEW, E
To FM 2751
CSJ 0640-07-005
Proj ID STP 1502(284)HES
Work Type SUBGR WDN, ACP LVL - UP, STRS, OCST, PVMK
 
8.012 4436875.01 0.00 1281403.46 28.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-13-15
Work Began 10-12-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 284
Addl Days Granted 0
Working Days Charged 50
Percent Time Used 17
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0640-07-005
BAHENA CONSTRUCTION CO.,INC. (2.85%)
COWBELL TRAFFIC SERVICES, INC. (0.26%)
PANOLA SIGN & BARRICADE, INC.(0.60%)
SOUTHWEST ENVIRONMENT SERVICES LLC (6.94%)
STRIPE-A-ZONE, INC.(2.47%)
Contract # 06153032
Totals 4436875.01 0.00 1281403.46 28.8

CountyVAN ZANDT
Highway FM 314
From 2.3 MI N OF SH 64(CR 4907),S
To FM 279 (E) IN EDOM
CSJ 0745-01-015
Proj ID STP 2014(634)
Work Type SCAR, RESHAPE, FLX BS, SURF TRT, STRS
 
11.712 11961746.06 0.00 3183139.94 26.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-08-14
Work Began 11-07-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 486
Addl Days Granted 0
Working Days Charged 165
Percent Time Used 33
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0745-01-015
STRIPING TECHNOLOGY, L.P.(1.39%)
DUSTIN ALLEN, INC. (0.74%)
KENSAR LLC DBA S & S TRUCKING(4.64%)
Contract # 05143203
Totals 11961746.06 0.00 3183139.94 26.6

CountyANDERSON
Highway FM 323 ETC
From US 84 IN PALESTINE, SE
To N OF SH 294
CSJ 0891-02-019
Proj ID STP 2015(091)HESG
Work Type PROFILE TEXTURE CENTERLINE
 
389.544 1884151.05 61921.50 1517852.12 81.6
Work Order 10-02-14
Work Began 03-23-15
Work Completed  
Time Computed 10-18-14
Contract Working Days 100
Addl Days Granted 20
Working Days Charged 146
Percent Time Used 121
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0891-02-019
PANOLA SIGN & BARRICADE, INC.(6.75%)
COWBELL TRAFFIC SERVICES, INC. (7.95%)
NE-TEX CONSTRUCTION, LTD.(0.00%)
BRYDL CONTRACTING, INC.(5.47%)
L. S. EQUIPMENT CO., INC.(5.76%)
Contract # 09143014
Totals 1884151.05 61921.50 1517852.12 81.6

CountySMITH
Highway VA
From VARIOUS LOCATIONS IN
To THE TYLER DISTRICT
CSJ 0910-00-094
Proj ID STP 2015(160)
Work Type THERMOPLASTIC MARKINGS
 
1.000 296128.85 0.00 289054.48 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-02-14
Work Began 12-02-14
Work Completed 02-13-15
Time Computed 10-18-14
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 18
Percent Time Used 60
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0910-00-094
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143218
Totals 296128.85 0.00 289054.48 100.0

CountySMITH
Highway VA
From VARIOUS LOCATIONS IN HENDERSON
To WOOD, VAN ZANDT & ANDERSON COUNTIES
CSJ 0910-00-095
Proj ID STP 2013(682)
Work Type ADA CURB RAMPS
 
1.000 1347171.00 0.00 1357227.23 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-26-13
Work Began 08-12-13
Work Completed 06-01-15
Time Computed 07-12-13
Contract Working Days 218
Addl Days Granted 0
Working Days Charged 236
Percent Time Used 108
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0910-00-095
PANOLA SIGN & BARRICADE, INC.(1.44%)
PAVEMENT MARKINGS INC. (2.52%)
Contract # 05133034
Totals 1347171.00 0.00 1357227.23 100.0

CountySMITH
Highway VA
From ON US 79 & US 69 IN
To CHEROKEE & RUSK COUNTIES
CSJ 0910-00-096
Proj ID STP 2016(365)
Work Type THERMOPLASTIC PAVEMENT MARKINGS
 
29.300 140236.68 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 21
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0910-00-096
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12153027
Totals 140236.68 0.00 0.00 0.0

CountySMITH
Highway VA
From ON IH20,E OF FM757 WB,W OF FM849 EB
To IN SMITH,E OF FM1255 WB IN VANZANDT
CSJ 0910-00-098
Proj ID ITS 2004(807)
Work Type DMS INSTALLATION (FY04 ITS PGM)
 
41.884 177095.57 0.00 142375.32 92.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-14-13
Work Began 06-26-14
Work Completed  
Time Computed 11-30-13
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 111
Percent Time Used 148
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0910-00-098
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC(1.62%)
ODUM SERVICES, L.P.(6.59%)
CARTHAGE DRILLING, INC.(1.41%)
B & B UNDERGROUND, LLC (2.42%)
TX DOWN UNDER CONSTRUCTION LLC (0.00%)
Contract # 10133219
Totals 177095.57 0.00 142375.32 92.3

CountyGREGG
Highway CR
From SPINKS-CHAPMAN RD AT RABBIT CRK
To STR# AA00-07-002
CSJ 0910-07-059
Proj ID BR 1302(076)
Work Type RPLC BRG & APPRS, GRD, ACP BS & SURF, MBGF
 
0.082 487743.10 0.00 479102.63 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-15-14
Work Began 06-30-14
Work Completed 07-29-15
Time Computed 05-01-14
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 74
Percent Time Used 98
Contractor(s)
MASSANA CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 0910-07-059
LONE STAR BARRIER SERVICES, LLC(2.37%)
ALTUS TRAFFIC MANAGEMENT LLC (0.48%)
EROSION CONTROL MANAGEMENT SERVICES(1.63%)
FRAIRE"S REBAR, INC(1.32%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (8.18%)
EAST TEXAS BRIDGE, INC.(8.31%)
Contract # 03143214
Totals 487743.10 0.00 479102.63 100.0

CountyGREGG
Highway VA
From VARIOUS LOCATIONS IN
To GREGG COUNTY
CSJ 0910-07-066
Proj ID STP 1502(475)
Work Type PLANT TREES OR SHRUBS
 
3.000 389220.39 0.00 290314.44 74.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-06-15
Work Began 09-24-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 72
Addl Days Granted 0
Working Days Charged 55
Percent Time Used 76
Contractor(s)
SOUTH TEXAS ILLUMINATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0910-07-066
GREEN BLADE IRRIGATION & LANDSCAPE ( 33.97%)
FLEX SUPPLY, LLC (4.80%)
Contract # 07153033
Totals 389220.39 0.00 290314.44 74.5

CountyANDERSON
Highway CR
From CR 471 AT BOX CREEK
To STR # AA04-71-101
CSJ 0910-08-040
Proj ID BR 2000(274)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.161 817412.15 39702.54 459817.29 56.2
Work Order 04-27-15
Work Began 06-18-15
Work Completed  
Time Computed 05-13-15
Contract Working Days 177
Addl Days Granted 0
Working Days Charged 57
Percent Time Used 32
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0910-08-040
AMERICAN REMEDIATION OPTIONS, INC. (5.72%)
PANOLA SIGN & BARRICADE, INC.(1.06%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (9.81%)
MESA ROD BUSTERS, INC. (0.37%)
Contract # 03153203
Totals 817412.15 39702.54 459817.29 56.2

CountyANDERSON
Highway CR
From CR 432 AT LAKE CREEK
To STR # AA03-44-001
CSJ 0910-08-055
Proj ID BR 2007(723)
Work Type RPLC BRG & APPRS, GRD, ACP BS & SURF, MBGF
 
0.150 610062.05 0.00 620447.54 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-15-14
Work Began 05-29-14
Work Completed 03-10-15
Time Computed 05-01-14
Contract Working Days 82
Addl Days Granted 0
Working Days Charged 82
Percent Time Used 100
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0910-08-055
AMERICAN REMEDIATION OPTIONS, INC. (4.88%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (7.98%)
PANOLA SIGN & BARRICADE, INC.(1.02%)
MESA ROD BUSTERS, INC. (0.40%)
Contract # 03143203
Totals 610062.05 0.00 620447.54 100.0

CountyANDERSON
Highway CR
From CR 453 AT BEAVER CREEK
To STR# AA0349-001
CSJ 0910-08-062
Proj ID BR 1302(075)
Work Type RPLC BRG & APPR, ACP BS & SURF, GR, MBGF
 
0.080 256312.87 0.00 249902.51 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-11-15
Work Began 03-24-15
Work Completed 12-16-15
Time Computed 02-27-15
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 77
Percent Time Used 102
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0910-08-062
LONE STAR BARRIER SERVICES, LLC(4.08%)
PANOLA SIGN & BARRICADE, INC.(1.16%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. ( 15.15%)
MESA ROD BUSTERS, INC. (0.39%)
Contract # 01153223
Totals 256312.87 0.00 249902.51 100.0

CountyANDERSON
Highway PW
From VARIOUS LOCATIONS
To WITHIN GUS ENGLING WMA
CSJ 0910-08-063
Proj ID C 910-8-63
Work Type BRIDGE & CULVERT REPAIR
 
1.000 483321.04 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 62
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MHB CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0910-08-063
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01163009
Totals 483321.04 0.00 0.00 0.0

CountyVAN ZANDT
Highway CR
From CR 2702 AT LACY FORK TRIBUTARY
To STR# AA02-48-001
CSJ 0910-12-061
Proj ID STP 1302(031)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.271 1021653.72 0.00 958713.52 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-25-14
Work Began 05-20-14
Work Completed 07-30-15
Time Computed 05-11-14
Contract Working Days 216
Addl Days Granted 0
Working Days Charged 190
Percent Time Used 87
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0910-12-061
PANOLA SIGN & BARRICADE, INC.(1.06%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.99%)
MAC TRANSPORTATION, LTD, L.L.P.(3.52%)
SAMMY G. SMALLWOOD (3.87%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.37%)
SOTO"S STEEL (0.19%)
Contract # 03143227
Totals 1021653.72 0.00 958713.52 100.0

CountyVAN ZANDT
Highway PW
From WITHIN PURTIS CREEK STATE PARK
To OFF OF FM 316
CSJ 0910-12-128
Proj ID C 910-12-128
Work Type ADD ROAD BASE & CLEAN DITCHES
 
0.573 90549.00 4180.00 92904.00 100.0
Work Order 07-16-15
Work Began 08-19-15
Work Completed 12-17-15
Time Computed 08-16-15
Contract Working Days 28
Addl Days Granted 0
Working Days Charged 24
Percent Time Used 85
Contractor(s)
CONSTRUCTION COMPANIES GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0910-12-128
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153051
Totals 90549.00 4180.00 92904.00 100.0

CountySMITH
Highway CR
From CR 448 AT VILLAGE CREEK
To STR# AA05-11-002
CSJ 0910-16-115
Proj ID BR 2012(167)
Work Type RPLC BRG & APPRCH, GR, ACP BS & SURF, MBGF
 
0.122 485890.80 15112.02 505938.59 100.0
Work Order 09-11-14
Work Began 11-13-14
Work Completed 08-21-15
Time Computed 09-27-14
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 86
Percent Time Used 95
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-115
FORTSON CONTRACTING, INC.(4.30%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.86%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.88%)
Contract # 07143237
Totals 485890.80 15112.02 505938.59 100.0

CountySMITH
Highway CR
From CR 481 AT DUCK CREEK
To STR# AA06-54-001
CSJ 0910-16-117
Proj ID BR 2012(174)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.127 555839.20 1100.00 538566.56 96.8
Work Order 04-20-15
Work Began 05-18-15
Work Completed  
Time Computed 05-06-15
Contract Working Days 113
Addl Days Granted 0
Working Days Charged 106
Percent Time Used 93
Contractor(s)
PIERCE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-117
TOTAL HIGHWAY MAINTENANCE, LLC (0.71%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.53%)
FORTSON CONTRACTING, INC.(3.97%)
SOUTHWEST ENVIRONMENT SERVICES LLC (2.72%)
DREWERY CONSTRUCTION COMPANY, INCORPORATED ( 16.66%)
Contract # 03153225
Totals 555839.20 1100.00 538566.56 96.8

CountySMITH
Highway VA
From VARIOUS LOCATIONS IN
To THE CITY OF TYLER
CSJ 0910-16-128
Proj ID STP 1402(013)
Work Type TREE PLANTING
 
1.000 130690.00 0.00 131690.00 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-20-14
Work Began 09-15-14
Work Completed 03-13-15
Time Computed 09-05-14
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 14
Percent Time Used 46
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0910-16-128
SOUTH TEXAS ILLUMINATION, LLC(5.78%)
FLEX SUPPLY, LLC (9.64%)
Contract # 07143049
Totals 130690.00 0.00 131690.00 100.0

CountyHENDERSON
Highway CS
From CARDINAL DR AT LITTLE DUNCAN CRK
To STR# S000-20-001, IN MURCHISON
CSJ 0910-34-028
Proj ID BR 2014(042)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.066 341919.44 0.00 321777.35 96.3
Work Order 04-20-15
Work Began 06-25-15
Work Completed  
Time Computed 05-06-15
Contract Working Days 56
Addl Days Granted 0
Working Days Charged 69
Percent Time Used 123
Contractor(s)
HARTBEAT CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 0910-34-028
ALTUS TRAFFIC MANAGEMENT LLC (0.75%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.15%)
REYNOLDS & KAY, LTD. ( 10.78%)
Contract # 03153018
Totals 341919.44 0.00 321777.35 96.3