Monthly Local Let Maintenance Report For Tyler District As Of Apr 11, 2016 Page 3 Of 8

Last Update: Monday, April 11, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHENDERSON
Highway SH0031
From ATHENS MTCE. OFFICE
To HENDERSON CO.
CSJ 6272-96-001
Proj ID SUP - 627296001
Work Type LAWN MTCE.
 
0.010 16782.00 386.50 7802.00 46.4
Work Order 08-14-14
Work Began 09-02-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 578
Percent Time Used 79
Contractor(s)
TIBH INDUSTRIES, INC.
ANDREWS DIVERSIFIED INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6272-96-001
ANDREWS DIVERSIFIED INDUSTRIES (100.00%)
Contract # 07141033
Totals 16782.00 386.50 7802.00 46.4

CountyGREGG
Highway SL0281
From LONGVIEW MTCE. OFFICE
To GREGG CO.
CSJ 6272-97-001
Proj ID SUP - 627297001
Work Type LAWN MTCE.
 
0.010 37260.00 705.00 19770.00 53.0
Work Order 08-14-14
Work Began 09-02-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 578
Percent Time Used 79
Contractor(s)
TIBH INDUSTRIES, INC.
ANDREWS DIVERSIFIED INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6272-97-001
ANDREWS DIVERSIFIED INDUSTRIES (100.00%)
Contract # 07141034
Totals 37260.00 705.00 19770.00 53.0

CountySMITH
Highway IH0020
From IH 20 EAST & WEST DERRICK PARK
To SH 31 @ FM 2661
CSJ 6272-98-001
Proj ID SUP - 627298001
Work Type PICNIC AREA MTCE.
 
0.010 124980.00 4764.00 97991.00 78.4
Work Order 08-14-14
Work Began 09-02-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 577
Percent Time Used 79
Contractor(s)
TIBH INDUSTRIES, INC.
ANDREWS DIVERSIFIED INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6272-98-001
ANDREWS DIVERSIFIED INDUSTRIES (100.00%)
Contract # 07141035
Totals 124980.00 4764.00 97991.00 78.4

CountySMITH
Highway IH0020
From IH 20 @ US 69 &
To IH 20 @ US 271
CSJ 6272-99-001
Proj ID SUP - 627299001
Work Type TRAFFIC ISLAND LANDSCAPE MTCE.
 
0.010 22158.24 461.63 9232.60 41.6
Work Order 08-14-14
Work Began 09-02-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 578
Percent Time Used 79
Contractor(s)
TIBH INDUSTRIES, INC.
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6272-99-001
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT(100.00%)
Contract # 07141036
Totals 22158.24 461.63 9232.60 41.6

CountyWOOD
Highway US0080
From US 80(2), US 69, FM 2088
To SH 37(2)
CSJ 6273-00-001
Proj ID SUP - 627300001
Work Type PICNIC AREA MTCE.
 
0.010 122429.04 4018.34 75332.20 61.5
Work Order 08-14-14
Work Began 09-02-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 578
Percent Time Used 79
Contractor(s)
TIBH INDUSTRIES, INC.
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6273-00-001
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT(100.00%)
Contract # 07141037
Totals 122429.04 4018.34 75332.20 61.5

CountyWOOD
Highway SL0564
From MINEOLA AO & MTCE. OFFICE
To SL 564, WOOD CO.
CSJ 6273-01-001
Proj ID SUP - 627301001
Work Type LAWN MTCE.
 
0.010 31945.70 364.82 16579.26 51.8
Work Order 08-14-14
Work Began 09-02-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 578
Percent Time Used 79
Contractor(s)
TIBH INDUSTRIES, INC.
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT
SUBCONTRACTOR(S) FOR CCSJ: 6273-01-001
WOODCREEK OUTREACH REHABILITATION DEVELOPMENT(100.00%)
Contract # 07141038
Totals 31945.70 364.82 16579.26 51.8

CountySMITH
Highway SH0155
From TYLER AO & MTCE. OFFICE
To SH 155 S IN NOONDAY
CSJ 6273-02-001
Proj ID SUP - 627302001
Work Type JANITORIAL MTCE.
 
0.001 42749.92 1411.27 33473.71 78.3
Work Order 08-15-14
Work Began 09-02-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 578
Percent Time Used 79
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6273-02-001
WORLD TECHNICAL SERVICES, INC. (100.00%)
Contract # 07141039
Totals 42749.92 1411.27 33473.71 78.3

CountyANDERSON
Highway SH0019
From PALESTINE MTCE. OFFICE
To ANDERSON CO.
CSJ 6273-03-001
Proj ID SUP - 627303001
Work Type JANITORIAL MTCE.
 
0.010 24599.52 872.59 18407.89 74.8
Work Order 08-31-14
Work Began 09-02-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 577
Percent Time Used 79
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6273-03-001
WORLD TECHNICAL SERVICES, INC. (100.00%)
Contract # 07141040
Totals 24599.52 872.59 18407.89 74.8

CountyCHEROKEE
Highway LP0456
From JACKSONVILLE MTCE. OFFICE
To LP 456
CSJ 6273-04-001
Proj ID SUP - 627304001
Work Type LAWN MTCE.
 
0.010 18465.00 275.00 5952.50 32.2
Work Order 08-15-14
Work Began 09-02-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 578
Percent Time Used 79
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6273-04-001
GATEWAY COMMUNITY PARTNERS, INC. (100.00%)
Contract # 07141041
Totals 18465.00 275.00 5952.50 32.2

CountyCHEROKEE
Highway US0069
From RUSK MTCE. OFFICE
To US 69
CSJ 6273-05-001
Proj ID SUP - 627305001
Work Type LAWN MTCE.
 
0.010 14740.00 315.00 6450.00 43.7
Work Order 08-15-14
Work Began 09-02-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 578
Percent Time Used 79
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6273-05-001
GATEWAY COMMUNITY PARTNERS, INC. (100.00%)
Contract # 07141042
Totals 14740.00 315.00 6450.00 43.7

CountyCHEROKEE
Highway US0069
From JVILLE/RUSK MTCE SECTIONS
To CHEROKEE CO.
CSJ 6273-06-001
Proj ID SUP - 627306001
Work Type LANDSCAPE ISLAND MTCE.
 
0.010 22803.36 475.07 8551.26 37.5
Work Order 08-15-14
Work Began 09-02-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 578
Percent Time Used 79
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6273-06-001
GATEWAY COMMUNITY PARTNERS, INC. (100.00%)
Contract # 07141043
Totals 22803.36 475.07 8551.26 37.5

CountyRUSK
Highway SH0064
From SH 64 W, US 259 N, US 259 S, SH 43 N
To HENDERSON MTCE. SECTION
CSJ 6273-07-001
Proj ID SUP - 627307001
Work Type PICNIC AREA MTCE.
 
0.010 55264.00 2584.00 39179.00 70.8
Work Order 08-15-14
Work Began 09-02-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 578
Percent Time Used 79
Contractor(s)
TIBH INDUSTRIES, INC.
COMMUNITY HEALTHCORE
SUBCONTRACTOR(S) FOR CCSJ: 6273-07-001
COMMUNITY REHABILITATION CENTER TRANSPORTATION, LLC(100.00%)
Contract # 07141044
Totals 55264.00 2584.00 39179.00 70.8

CountyRUSK
Highway FM0225
From HENDERSON MTCE SECTION OFFICE
To FM 225 RUSK CO.
CSJ 6273-08-001
Proj ID SUP - 627308001
Work Type LAWN MTCE.
 
0.010 12192.36 368.00 5904.12 48.4
Work Order 08-15-14
Work Began 09-02-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 578
Percent Time Used 79
Contractor(s)
TIBH INDUSTRIES, INC.
COMMUNITY HEALTHCORE
SUBCONTRACTOR(S) FOR CCSJ: 6273-08-001
COMMUNITY REHABILITATION CENTER TRANSPORTATION, LLC(100.00%)
Contract # 07141045
Totals 12192.36 368.00 5904.12 48.4

CountyRUSK
Highway SH0064
From HENDERSON MTCE. SECTION
To RUSK CO.
CSJ 6273-09-001
Proj ID SUP - 627309001
Work Type LITTER PICK UP
 
0.010 242191.70 28374.50 189052.99 78.0
Work Order 08-26-14
Work Began 09-02-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 578
Percent Time Used 79
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6273-09-001
RUCON, INC.(0.00%)
Contract # 07141046
Totals 242191.70 28374.50 189052.99 78.0

CountySMITH
Highway SL0323
From SPECIAL JOBS MTCE. OFFICE
To N SL 323
CSJ 6276-06-001
Proj ID SUP - 627606001
Work Type JANITORIAL
 
0.010 17811.00 0.00 9112.50 51.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-31-14
Work Began 08-01-14
Work Completed  
Time Computed 08-01-14
Contract Working Days 761
Addl Days Granted 0
Working Days Charged 451
Percent Time Used 59
Contractor(s)
TIBH INDUSTRIES, INC.
COMMUNITY HEALTHCORE
SUBCONTRACTOR(S) FOR CCSJ: 6276-06-001
COMMUNITY HEALTHCORE (100.00%)
Contract # 07141030
Totals 17811.00 0.00 9112.50 51.1

CountySMITH
Highway SH0031
From TYLER DISTRICT HEADQUARTERS COMPLEX
To FRONT ST
CSJ 6276-07-001
Proj ID SUP - 627607001
Work Type JANITORIAL
 
0.010 265226.60 0.00 123649.50 46.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 08-01-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 761
Addl Days Granted 0
Working Days Charged 440
Percent Time Used 57
Contractor(s)
TIBH INDUSTRIES, INC.
COMMUNITY HEALTHCORE
SUBCONTRACTOR(S) FOR CCSJ: 6276-07-001
COMMUNITY HEALTHCORE (100.00%)
Contract # 07141031
Totals 265226.60 0.00 123649.50 46.6

CountySMITH
Highway SH0031
From VARIOUS ROADWAYS IN THE
To TYLER MAINTENANCE SECTION
CSJ 6278-16-001
Proj ID RMC - 627816001
Work Type ROW MOWING
 
0.001 257840.79 0.00 253884.77 98.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 06-08-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 53
Addl Days Granted 53
Working Days Charged 51
Percent Time Used 48
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6278-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02151001
Totals 257840.79 0.00 253884.77 98.4

CountyWOOD
Highway US0069
From VARIOUS ROADWAY IN THE
To MINEOLA MAINTENANCE
CSJ 6278-17-001
Proj ID RMC - 627817001
Work Type ROW MOWING
 
0.001 236416.70 0.00 235236.70 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 06-15-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 53
Addl Days Granted 53
Working Days Charged 54
Percent Time Used 50
Contractor(s)
HX FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6278-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02151002
Totals 236416.70 0.00 235236.70 99.9

CountyCHEROKEE
Highway US0084
From VARIOUS ROADWAYS IN THE
To JACKSONVILLE MAINTENANCE SECTION
CSJ 6278-18-001
Proj ID RMC - 627818001
Work Type ROW MOWING
 
0.001 215132.80 0.00 214047.40 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 06-08-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 49
Addl Days Granted 0
Working Days Charged 61
Percent Time Used 124
Contractor(s)
SERVIN MOWING
SUBCONTRACTOR(S) FOR CCSJ: 6278-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02151003
Totals 215132.80 0.00 214047.40 99.9

CountyANDERSON
Highway US0287
From VARIOUS ROADWAYS IN THE
To PALESTINE MAINTENANCE SECTION
CSJ 6278-19-001
Proj ID RMC - 627819001
Work Type ROW MOWING
 
0.001 235072.32 0.00 229762.32 97.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 06-26-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 49
Addl Days Granted 49
Working Days Charged 51
Percent Time Used 52
Contractor(s)
LAWRENCE W. SIMS
SUBCONTRACTOR(S) FOR CCSJ: 6278-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02151004
Totals 235072.32 0.00 229762.32 97.7