Monthly Local Let Maintenance Report For Tyler District As Of Mar 10, 2015 Page 4 Of 5

Last Update: Wednesday, March 11, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyCHEROKEE
Highway US0069
From RUSK MTCE. OFFICE
To US 69
CSJ 6273-05-001
Proj ID SUP - 627305001
Work Type LAWN MTCE.
 
0.010 14740.00 0.00 1510.00 10.2
Work Order 08-15-14
Work Began 09-02-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 181
Percent Time Used 24
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6273-05-001
GATEWAY COMMUNITY PARTNERS, INC. (100.00%)
Contract # 07141042
Totals 14740.00 0.00 1510.00 10.2

CountyCHEROKEE
Highway US0069
From JVILLE/RUSK MTCE SECTIONS
To CHEROKEE CO.
CSJ 6273-06-001
Proj ID SUP - 627306001
Work Type LANDSCAPE ISLAND MTCE.
 
0.010 22803.36 0.00 1900.28 8.3
Work Order 08-15-14
Work Began 09-02-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 181
Percent Time Used 24
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6273-06-001
GATEWAY COMMUNITY PARTNERS, INC. (100.00%)
Contract # 07141043
Totals 22803.36 0.00 1900.28 8.3

CountyRUSK
Highway SH0064
From SH 64 W, US 259 N, US 259 S, SH 43 N
To HENDERSON MTCE. SECTION
CSJ 6273-07-001
Proj ID SUP - 627307001
Work Type PICNIC AREA MTCE.
 
0.010 55264.00 1107.00 9807.00 17.7
Work Order 08-15-14
Work Began 09-02-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 181
Percent Time Used 24
Contractor(s)
TIBH INDUSTRIES, INC.
COMMUNITY HEALTHCORE
SUBCONTRACTOR(S) FOR CCSJ: 6273-07-001
COMMUNITY REHABILITATION CENTER TRANSPORTATION, LLC(100.00%)
Contract # 07141044
Totals 55264.00 1107.00 9807.00 17.7

CountyRUSK
Highway FM0225
From HENDERSON MTCE SECTION OFFICE
To FM 225 RUSK CO.
CSJ 6273-08-001
Proj ID SUP - 627308001
Work Type LAWN MTCE.
 
0.010 12192.36 0.00 1104.00 9.0
Work Order 08-15-14
Work Began 09-02-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 181
Percent Time Used 24
Contractor(s)
TIBH INDUSTRIES, INC.
COMMUNITY HEALTHCORE
SUBCONTRACTOR(S) FOR CCSJ: 6273-08-001
COMMUNITY REHABILITATION CENTER TRANSPORTATION, LLC(100.00%)
Contract # 07141045
Totals 12192.36 0.00 1104.00 9.0

CountyRUSK
Highway SH0064
From HENDERSON MTCE. SECTION
To RUSK CO.
CSJ 6273-09-001
Proj ID SUP - 627309001
Work Type LITTER PICK UP
 
0.010 242191.70 26794.75 60862.49 25.1
Work Order 08-26-14
Work Began 09-02-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 181
Percent Time Used 24
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6273-09-001
RUCON, INC.(0.00%)
Contract # 07141046
Totals 242191.70 26794.75 60862.49 25.1

CountySMITH
Highway SL0323
From SPECIAL JOBS MTCE. OFFICE
To N SL 323
CSJ 6276-06-001
Proj ID SUP - 627606001
Work Type JANITORIAL
 
0.010 17811.00 436.00 4229.25 23.7
Work Order 07-31-14
Work Began 08-01-14
Work Completed  
Time Computed 08-01-14
Contract Working Days 761
Addl Days Granted 0
Working Days Charged 212
Percent Time Used 27
Contractor(s)
TIBH INDUSTRIES, INC.
COMMUNITY HEALTHCORE
SUBCONTRACTOR(S) FOR CCSJ: 6276-06-001
COMMUNITY HEALTHCORE (100.00%)
Contract # 07141030
Totals 17811.00 436.00 4229.25 23.7

CountySMITH
Highway SH0031
From TYLER DISTRICT HEADQUARTERS COMPLEX
To FRONT ST
CSJ 6276-07-001
Proj ID SUP - 627607001
Work Type JANITORIAL
 
0.010 265226.60 0.00 58756.40 22.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 08-01-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 761
Addl Days Granted 0
Working Days Charged 212
Percent Time Used 27
Contractor(s)
TIBH INDUSTRIES, INC.
COMMUNITY HEALTHCORE
SUBCONTRACTOR(S) FOR CCSJ: 6276-07-001
COMMUNITY HEALTHCORE (100.00%)
Contract # 07141031
Totals 265226.60 0.00 58756.40 22.1

CountySMITH
Highway SH0031
From VARIOUS ROADWAYS IN THE
To TYLER MAINTENANCE SECTION
CSJ 6278-16-001
Proj ID RMC - 627816001
Work Type ROW MOWING
 
0.001 257840.79 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 53
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6278-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02151001
Totals 257840.79 0.00 0.00 0.0

CountyWOOD
Highway US0069
From VARIOUS ROADWAY IN THE
To MINEOLA MAINTENANCE
CSJ 6278-17-001
Proj ID RMC - 627817001
Work Type ROW MOWING
 
0.001 236416.70 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 53
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HX FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6278-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02151002
Totals 236416.70 0.00 0.00 0.0

CountyCHEROKEE
Highway US0084
From VARIOUS ROADWAYS IN THE
To JACKSONVILLE MAINTENANCE SECTION
CSJ 6278-18-001
Proj ID RMC - 627818001
Work Type ROW MOWING
 
0.001 215132.80 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 49
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SERVIN MOWING
SUBCONTRACTOR(S) FOR CCSJ: 6278-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02151003
Totals 215132.80 0.00 0.00 0.0

CountyANDERSON
Highway US0287
From VARIOUS ROADWAYS IN THE
To PALESTINE MAINTENANCE SECTION
CSJ 6278-19-001
Proj ID RMC - 627819001
Work Type ROW MOWING
 
0.001 235072.32 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 49
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LAWRENCE W. SIMS
SUBCONTRACTOR(S) FOR CCSJ: 6278-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02151004
Totals 235072.32 0.00 0.00 0.0

CountyGREGG
Highway US0080
From VARIOUS LOCATION IN THE
To LONGVIEW MAINTENANCE SECTION
CSJ 6278-20-001
Proj ID RMC - 627820001
Work Type ROW MOWING
 
0.001 86822.68 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 31
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SERVIN MOWING
SUBCONTRACTOR(S) FOR CCSJ: 6278-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02151005
Totals 86822.68 0.00 0.00 0.0

CountyRUSK
Highway US0259
From VARIOUS ROADWAYS IN THE
To HENDERSON MAINTENANCE SECTION
CSJ 6278-21-001
Proj ID RMC - 627821001
Work Type ROW MOWING
 
0.001 254493.30 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 55
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SERVIN MOWING
SUBCONTRACTOR(S) FOR CCSJ: 6278-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02151006
Totals 254493.30 0.00 0.00 0.0

CountyVAN ZANDT
Highway SH0064
From VARIOUS ROADWAYS IN THE
To VAN ZANDT MAINTENANCE SECTION
CSJ 6278-22-001
Proj ID RMC - 627822001
Work Type ROW MOWING
 
0.001 206761.97 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 49
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
C & C MOWING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6278-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02151007
Totals 206761.97 0.00 0.00 0.0

CountyHENDERSON
Highway US0175
From VARIOUS ROADWAYS IN
To THE ATHENS MAINTENANCE SECTION
CSJ 6278-23-001
Proj ID RMC - 627823001
Work Type ROW MOWING
 
0.001 254356.86 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 55
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
C & C MOWING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6278-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02151008
Totals 254356.86 0.00 0.00 0.0

CountySMITH
Highway SH0031
From VARIOUS ROADWAYS IN THE
To TYLER DISTRICT
CSJ 6278-30-001
Proj ID RMC - 627830001
Work Type SIGNAL MAINTENANCE
 
0.001 253570.00 6492.00 10317.00 4.0
Work Order 01-09-15
Work Began 00-00-00
Work Completed  
Time Computed 01-19-15
Contract Working Days 255
Addl Days Granted 0
Working Days Charged 30
Percent Time Used 11
Contractor(s)
TEXAS TRAFFIC CONTROL SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6278-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11141005
Totals 253570.00 6492.00 10317.00 4.0

CountySMITH
Highway SH0031
From VARIOUS ROADWAYS IN
To THE TYLER DISTRICT
CSJ 6278-31-001
Proj ID RMC - 627831001
Work Type ILLUMINATION MAINTENANCE
 
0.001 61860.00 2620.00 2845.00 4.5
Work Order 01-09-15
Work Began 00-00-00
Work Completed  
Time Computed 01-28-15
Contract Working Days 255
Addl Days Granted 0
Working Days Charged 23
Percent Time Used 9
Contractor(s)
TEXAS TRAFFIC CONTROL SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6278-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11141004
Totals 61860.00 2620.00 2845.00 4.5

CountyHENDERSON
Highway SH0274
From VARIOUS LOCATIONS IN ATHENS MTCE.
To IN HENDERSON COUNTY
CSJ 6278-72-001
Proj ID RMC - 627872001
Work Type TREE TRIMMING AND BRUSH REMOVAL
 
75.400 139491.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-02-15
Work Began 00-00-00
Work Completed  
Time Computed 03-23-15
Contract Working Days 76
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
L&S EXCAVATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6278-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11141001
Totals 139491.00 0.00 0.00 0.0

CountyWOOD
Highway FM0778
From VARIOUS ROADWAYS IN MINEOLA MTCE.
To IN WOOD COUNTY
CSJ 6278-73-001
Proj ID RMC - 627873001
Work Type TREE TRIMMING AND BRUSH REMOVAL
 
79.050 106639.45 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-02-15
Work Began 00-00-00
Work Completed  
Time Computed 03-23-15
Contract Working Days 80
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FOWLER CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6278-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11141002
Totals 106639.45 0.00 0.00 0.0

CountyRUSK
Highway US0259
From VARIOUS ROADWAYS
To IN RUSK COUNTY
CSJ 6278-74-001
Proj ID RMC - 627874001
Work Type TREE TRIMMING AND REMOVAL
 
34.410 60750.08 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-27-15
Work Began 00-00-00
Work Completed  
Time Computed 03-09-15
Contract Working Days 35
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MORRIS COUNTY CONTRACTORS, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6278-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12141001
Totals 60750.08 0.00 0.00 0.0

page 1 | page 2 | page 3 | page 4 | page 5