AVERAGE LOW BID UNIT PRICE - CONSTRUCTION - STATEWIDE

Last Update: Friday, June 26, 2015
ITEMS 529 2017 TO 530 6022
Items Items Bid Code Range
0100 - 0193
0204 - 0292
0305 - 0368
0400 - 0499
0500 - 0560
0610 - 0690
0700 - 0788
0800 - 0800
1002 - 1158
2021 - 2336
3000 - 3289
4001 - 4686
5001 - 5991
6000 - 6986
7001 - 7661
8020 - 8999
9012 - 9059
500 2001 - 512 2088
512 2092 - 529 2015
529 2017 - 530 6022
530 6023 - 540 2001
540 2002 - 545 2024
545 2030 - 560 2010
560 2011 - 560 6021
Item No Description Units June 30, 2015 Twelve Month Moving Usage
Quantity Avg Bid Quantity Avg Bid
529 2017 CONC CURB & GUTTER (VALLEY GUTTER) LF     11,235.700 18.24376 3
529 2018 CONC CURB (MONO) (TY II) (SPECIAL) LF     8,098.000 2.00000 1
529 2019 CONC CURB & GUTTER (TY B) (MOUNTABLE) LF     6,415.000 10.17557 2
529 2021 CONC CURB (DOWEL) (REINF) (TY II) LF     3,445.000 14.69254 4
529 2023 CONC CURB (MONO) LF     500.000 32.00000 1
529 2024 CONC CURB (MOUNTABLE) LF     2,771.000 7.00000 1
529 2026 CONC CURB (ARMOR CURB SLOT) LF     168.000 191.66667 2
529 2032 CONC CURB (TY B) MOUNTABLE LF     1,136.000 7.00000 1
529 2034 CONC GUTTER (TY B) VALLEY GUTTER LF     28.000 32.55000 1
529 2037 CONC CURB (TY II) (REINF) LF     14.000 36.00000 1
529 2038 CONC CURB AND GUTTER (TY A) LF     21.000 50.00000 1
529 2059 CONC CURB & GUTTER (TY I) (MOD) LF     1,336.000 18.83084 2
529 2061 CONC CURB (TY C1) LF     309.000 26.42744 2
529 2064 CONC CURB (TY F1) LF     46.500 150.00000 1
529 2065 CONC CURB (TY F2) LF     119.000 130.00000 1
529 2066 CONC CURB (RIBBON) (MOD) LF     3,208.000 14.44536 3
529 2069 CONC CURB AND GUTTER (TY I) (REINF) LF     786.000 27.72000 1
529 2070 CONCRETE CURB (TYPE U - TURN) (SPECIAL) LF     2,282.000 30.15031 2
529 2071 CONC CURB (SLOTTED) LF     150.000 25.20000 1
529 2075 CONC CURB (TY 1) (MOD) LF     557.000 30.42908 3
529 2083 CONC CURB & GUTTER (SPANDREL) LF     785.000 22.80000 1
529 2086 CONC CURB (DOWEL) (SLOTTED) LF     1,258.000 13.24006 2
529 2094 CONC CURB (TY F3) LF     289.000 90.00000 1
529 2107 CONC CURB (TY I) (DOWEL) (REINF) LF     2,425.000 15.00000 1
529 2108 CONC CURB (MONO) (TY I) (REINF) LF     5,077.000 1.00000 1
529 2109 CONC CURB (MONO) (TY II) (REINF) LF     4,601.000 1.34000 1
529 6001 CONC CURB (TY I) LF 31,239.000 5.59402 76,959.000 8.15860 7
529 6002 CONC CURB (TY II) LF 4,704.000 22.33440 15,800.000 17.17106 16
529 6004 CONC CURB (MONO) (TY I) LF     2,450.000 7.22612 2
529 6005 CONC CURB (MONO) (TY II) LF 18,380.000 2.75648 91,129.510 5.08475 22
529 6006 CONC CURB (MONO) (TY II A) LF 8,704.000 3.85000 8,704.000 3.85000 1
529 6007 CONC CURB & GUTTER (TY I) LF     468.000 41.95940 3
529 6008 CONC CURB & GUTTER (TY II) LF 53,810.500 19.30268 245,085.780 16.25374 28
529 6009 CONC CURB (DOWEL) (SLOTTED) LF 352.000 13.00000 3,844.000 19.36948 5
529 6010 CONC CURB (U - TURN) LF     3,129.300 30.32633 4
529 6011 CONC CURB (DOWEL) LF     45,050.000 9.23999 7
529 6012 CONC CURB (SLOTTED) LF 3,225.000 25.03876 7,590.000 18.24602 6
529 6013 CONC CURB (SPECIAL) (TYPE II) LF 158.700 35.46818 6,906.700 9.58559 4
529 6014 CONC CURB (MOD) (TYPE I) LF     420.000 41.90476 2
529 6015 CONC CURB (TY C1) LF 100.000 70.00000 100.000 70.00000 1
529 6016 CONC CURB (TY F1) LF 2,850.000 88.00000 2,934.000 88.03579 2
529 6017 CONC CURB (TY F2) LF     95.000 99.75000 1
529 6018 CONC CURB (TY F3) LF     425.000 115.50000 1
529 6020 CONC CURB & GUTTER (ARMOR CURB) LF 308.000 125.00000 336.000 128.33333 2
529 6021 CONC CURB & GUTTER (SLOTTED) LF     630.000 42.68571 3
530 2002 INTERSECTIONS (ACP) EA     66.000 4,602.27273 6
530 2003 INTERSECTIONS (SURF TREAT) EA     28.000 3,468.04786 3
530 2004 INTERSECTIONS (CONC) SY     9,144.000 69.89534 3
530 2005 INTERSECTIONS (ACP) SY     57,625.200 23.36740 25
530 2006 INTERSECTIONS (SURF TREAT) SY     27,667.400 24.43042 16
530 2007 DRIVEWAYS (CONC) EA     35.000 5,005.71429 5
530 2008 DRIVEWAYS (ACP) EA     716.000 1,132.70251 15
530 2009 DRIVEWAYS (SURF TREAT) EA     416.000 1,675.60349 7
530 2010 DRIVEWAYS (CONC) SY 1,361.000 52.00000 158,255.800 60.48717 126
530 2011 DRIVEWAYS (ACP) SY     241,346.850 32.54766 103
530 2012 DRIVEWAYS (SURF TREAT) SY     93,775.000 22.52340 32
530 2014 TURNOUTS (ACP) EA     267.000 2,159.08240 8
530 2015 TURNOUTS (SURF TREAT) EA     45.000 947.05333 2
530 2017 TURNOUTS (ACP) SY     8,492.700 46.72352 19
530 2018 TURNOUTS (SURF TREAT) SY     14,558.710 22.11152 20
530 2020 INTRSCT, DRVWAYS, & TURNOUT (ACP) SY     542.000 25.74170 2
530 2023 DRIVEWAYS AND TURNOUTS (ACP) SY     84.000 45.92190 1
530 2024 DRIVEWAYS AND TURNOUTS (SURF TREAT) SY     3,050.000 40.00000 1
530 2029 DRIVEWAYS (OTHER) SY     3,869.000 12.52158 4
530 2030 DRIVEWAYS (ACP) (TYPE 1) SY     10,596.000 21.06614 3
530 2031 DRIVEWAYS (ACP) (TYPE 2) SY     460.000 33.09326 3
530 2036 DRIVEWAYS (CONC) (TYPE 2) SY     241.100 68.42804 2
530 2037 DRIVEWAYS (CONC) (TYPE 1) SY     67.000 70.00000 1
530 2038 DRIVEWAYS (CONC) (HES) SY     18,539.000 82.58715 7
530 2050 DRIVEWAYS (SURF TREAT) (TYPE 1) SY     13,752.200 19.32545 2
530 2051 DRIVEWAYS (SURF TREAT) (TYPE 2) SY     781.100 47.94636 2
530 2056 INTERSECTIONS (CONC) (HES) SY     1,124.000 76.00000 1
530 2057 TURNOUTS (RAP) SY     1,453.000 31.00000 1
530 2058 DRIVEWAYS (OTHER) EA     44.000 700.00000 1
530 2071 INTERSECTIONS (ACP) (TYPE 1) SY     10,401.000 21.00000 1
530 2072 INTERSECTIONS (ACP) (TYPE 2) SY     812.000 26.00000 1
530 2073 INTERSECTIONS (ACP) (TYPE 3) SY     2,123.000 63.00000 1
530 2075 DRIVEWAYS (GRAVEL) SY     3,932.000 19.16813 5
530 2090 DRIVEWAYS (FL BS) SY     5,004.000 22.11364 8
530 2096 DRIVEWAY (FLEX BASE) EA     22.000 1,800.00000 1
530 6001 INTERSECTIONS (CONC) SY 1,078.000 83.00000 2,792.000 115.51519 3
530 6002 INTERSECTIONS (ACP) SY 14,976.240 41.45848 39,464.740 33.23705 22
530 6003 INTERSECTIONS (SURF TREAT) SY 4,613.000 31.94390 30,689.000 32.37760 16
530 6004 DRIVEWAYS (CONC) SY 12,203.400 85.45990 59,223.000 68.77403 63
530 6005 DRIVEWAYS (ACP) SY 42,848.790 33.97663 90,428.118 34.26327 64
530 6006 DRIVEWAYS (SURF TREAT) SY 35,575.000 23.56930 81,770.418 25.94340 33
530 6008 TURNOUTS (ACP) SY 1,001.600 54.93895 3,725.600 57.57823 16
530 6009 TURNOUTS (SURF TREAT) SY 3,451.110 24.37407 18,909.110 29.42403 23
530 6010 INTRSCT, DRVWAYS, & TURNOUT (CONC) SY     760.000 83.72000 1
530 6011 INTRSCT, DRVWAYS, & TURNOUT (ACP) SY 677.000 10.20000 8,109.000 30.77474 4
530 6012 INTRSCT, DRVWAYS, & TURNOUT (SURF TREAT SY     16,947.000 35.64068 3
530 6014 DRIVEWAYS AND TURNOUTS (ACP) SY     568.000 42.11268 2
530 6015 DRIVEWAYS AND TURNOUTS (SURF TREAT) SY 9,137.000 35.96202 16,870.000 35.97943 3
530 6016 DRIVEWAYS (BASE) SY 1,142.200 30.79233 7,544.200 21.43339 12
530 6017 DRIVEWAYS (CONC) (HES) SY 3,389.600 106.24286 4,484.600 99.26544 7
530 6018 DRIVEWAYS (ACP AND CONCRETE) SY 5,677.000 60.00000 13,564.000 56.51121 2
530 6019 DRIVEWAYS (ACP) (TYPE 1) SY     980.000 14.30000 1
530 6020 DRIVEWAYS (CONC) (TYPE 1) SY     441.000 70.00000 1
530 6021 DRIVEWAYS (ACP) (TYPE 2) SY     3,266.000 32.25000 1
530 6022 INTERSECTIONS (ACP) (TYPE 1) SY     4,479.000 11.40000 1