Tabulation of Bids for Project BPM - 636564001
Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months.
The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.
Text version of this page | |||
County: | CHAMBERS | Let Date: | 01/06/21 |
Type: | CLEAN & SEAL JOINTS/EROSION CNTRL/CONC REPAIR | Seq No: | 2001 |
Time: | 45 WORKING DAYS | Project ID: | BPM - 636564001 |
Highway: | IH0010 | Contract #: | 01212001 |
Length: | 0.000 | CCSJ: | 6365-64-001 |
Limits: | |||
From: | VARIOUS | Check: | $2,000 |
To: | VARIOUS | Misc Cost: |
Estimate | $84,878.70 | % Over/Under | Company |
Bidder 1 | $72,198.00 | -14.94% | TALBRAN ENTERPRISES LLC |
Bidder 2 | $72,293.17 | -14.83% | JAMES CONSTRUCTION GROUP, L.L.C. |
Bidder 3 | $75,045.00 | -11.59% | SJ&J CONSTRUCTION, LLC |
Bidder 4 | $77,500.00 | -8.69% | BLACKSMITH VENTURES LLC |
Bidder 5 | $83,153.00 | -2.03% | TREVWAY, INC. |
Bidder 6 | $96,905.80 | +14.17% | SCR CIVIL CONSTRUCTION, LLC |
Bidder 7 | $98,735.00 | +16.32% | FORDE CONSTRUCTION COMPANY, INC. |
Bidder 8 | $132,149.00 | +55.69% | ISI CONTRACTING, INC. |
Bidder 9 | $135,450.00 | +59.58% | MAIN LANE INDUSTRIES LTD. |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
4016001 | FLOWABLE BACKFILL | CY | 25.000 | 170.96 | 1 2 3 4 5 6 7 8 9 | 440.000 550.250 180.000 400.000 200.000 475.000 350.000 1,200.000 900.000 |
4296002 | CONC STR REPAIR (EPOXY MORTAR) | SF | 10.000 | 153.00 | 1 2 3 4 5 6 7 8 9 | 550.000 220.000 150.000 420.000 600.000 500.000 345.000 550.000 900.000 |
4296007 | CONC STR REPAIR (VERTICAL & OVERHEAD) | SF | 33.000 | 211.00 | 1 2 3 4 5 6 7 8 9 | 330.000 312.000 150.000 260.000 261.000 500.000 245.000 650.000 750.000 |
4386001 | CLEANING AND SEALING EXISTING JOINTS | LF | 718.000 | 48.65 | 1 2 3 4 5 6 7 8 9 | 55.000 42.410 40.000 40.000 30.000 50.600 25.000 68.000 50.000 |
5006001 | MOBILIZATION | LS | 1.000 | 9,000.00 | 1 2 3 4 5 6 7 8 9 | 3,095.000 7,000.540 15,000.000 10,000.000 8,500.000 9,600.000 36,000.000 12,000.000 13,500.000 |
5026001008 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 3.000 | 8,602.00 | 1 2 3 4 5 6 7 8 9 | 1.000 500.000 6,000.000 2,500.000 6,500.000 3,200.000 5,000.000 2,000.000 5,600.000 |
7206003 | SPALLING REPAIR (POLYMERIC) (SEMIRIGID) | GAL | 5.000 | 75.00 | 1 2 3 4 5 6 7 8 9 | 440.000 500.000 75.000 500.000 800.000 800.000 500.000 475.000 600.000 |
61856002002 | TMA (STATIONARY) | DAY | 20.000 | 100.00 | 1 2 3 4 5 6 7 8 9 | 1.000 229.500 100.000 300.000 500.000 200.000 350.000 300.000 500.000 |