The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.
Text version of this page | |||
County: | NACOGDOCHES | Let Date: | 01/08/20 |
Type: | TREE REMOVAL | Seq No: | 1110 |
Time: | 175 W | Project ID: | RMC - 635456001 |
Highway: | US0059 | Contract #: | 01201110 |
Length: | 0.000 | CCSJ: | 6354-56-001 |
Limits: | |||
From: | NACOGDOCHES COUNTY | Check: | $3,000 |
To: | VARIOUS ROADWAY | Misc Cost: | $1,500.00 |
Estimate | $137,700.00 | % Over/Under | Company |
Bidder 1 | $109,500.00 | -20.48% | ACE CONTRACTORS, INC. |
Bidder 2 | $124,125.00 | -9.86% | K & R CONTRACTORS |
Bidder 3 | $133,425.00 | -3.10% | DREWERY CONSTRUCTION COMPANY, INCORPORATED |
Bidder 4 | $149,975.00 | +8.91% | AZA CONSTRUCTION INC |
Bidder 5 | $157,990.00 | +14.73% | JC ROAD MAINTENANCE, LLC |
Bidder 6 | $264,250.00 | +91.90% | PROENVIROTECH, INC. |
Bidder 7 | $33,095,381.00 | +23934.41% | NELMS SERVICES, INC. |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
5006033 | MOBILIZATION (CALLOUT) | EA | 6.000 | 2,000.00 | 1 2 3 4 5 6 7 | 600.000 500.000 500.000 1,600.000 5,000.000 2,000.000 1.000 |
7526005 | TREE REMOVAL (4" - 12" DIA) | EA | 400.000 | 75.00 | 1 2 3 4 5 6 7 | 75.000 80.000 52.000 80.000 40.000 150.000 150.000 |
7526006 | TREE REMOVAL (12" - 18" DIA) | EA | 300.000 | 100.00 | 1 2 3 4 5 6 7 | 75.000 100.000 68.000 110.000 54.000 175.000 110,000.000 |
7526007 | TREE REMOVAL (18" - 24" DIA) | EA | 130.000 | 125.00 | 1 2 3 4 5 6 7 | 80.000 125.000 95.000 150.000 118.000 200.000 100.000 |
7526008 | TREE REMOVAL (24" - 30" DIA) | EA | 75.000 | 171.00 | 1 2 3 4 5 6 7 | 200.000 200.000 275.000 225.000 219.000 250.000 75.000 |
7526009 | TREE REMOVAL (30" - 36" DIA) | EA | 30.000 | 325.00 | 1 2 3 4 5 6 7 | 300.000 300.000 325.000 300.000 535.000 500.000 100.000 |
7526010 | TREE REMOVAL (36" - 42" DIA) | EA | 25.000 | 443.00 | 1 2 3 4 5 6 7 | 300.000 325.000 600.000 400.000 639.000 750.000 75.000 |
7526011 | TREE REMOVAL (42" - 48" DIA) | EA | 25.000 | 472.00 | 1 2 3 4 5 6 7 | 300.000 350.000 700.000 600.000 640.000 850.000 75.000 |
61856002002 | TMA (STATIONARY) | DAY | 20.000 | 200.00 | 1 2 3 4 5 6 7 | 200.000 100.000 700.000 250.000 800.000 2,000.000 500.000 |