Tabulation of Bids for Project BR 1702(011)
Text version of this page | |||
County: | MEDINA | Let Date: | 01/08/19 |
Type: | REPLACE BRIDGE & APPROACHES | Seq No: | 3034 |
Time: | 78 WORKING DAYS | Project ID: | BR 1702(011) |
Highway: | CR | Contract #: | 01193034 |
Length: | 0.072 | CCSJ: | 0915-45-053 |
Limits: | |||
From: | 1.0 MI E OF FM 1343 | Check: | $9,000 |
To: | AT FRANCISCO PEREZ CRK | Misc Cost: | $3,000.00 |
Estimate | $452,744.15 | % Over/Under | Company |
Bidder 1 | $487,790.56 | +7.74% | RELMCO, INC. |
Bidder 2 | $511,815.91 | +13.05% | ACME BRIDGE COMPANY, INC. |
Bidder 3 | $526,753.65 | +16.35% | TMES LLC |
Bidder 4 | $543,130.40 | +19.96% | HILL COUNTRY BRIDGE, INC. |
Bidder 5 | $566,217.65 | +25.06% | SB CONTRACTORS LLC |
Bidder 6 | $625,906.55 | +38.25% | DALRYMPLE GRAVEL AND CONTRACTING COMPANY, INC. |
Bidder 7 | $698,130.28 | +54.20% | DEAN WORD COMPANY, LTD. |
Bidder 8 | $728,884.24 | +60.99% | SALINAS CONSTRUCTION TECHNOLOGIES, LTD. |
Bidder 9 | $885,963.00 | +95.69% | FNH CONSTRUCTION, LLC |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
1006002 | PREPARING ROW | STA | 3.800 | 3,000.00 | 1 2 3 4 5 6 7 8 9 | 1,250.000 3,000.000 3,500.000 1,970.000 3,000.000 2,000.000 104.000 1,473.290 20,000.000 |
1006006 | PREP ROW (TREE)(LESS THAN 24" DIA) | EA | 4.000 | 1,000.00 | 1 2 3 4 5 6 7 8 9 | 1,100.000 1,100.000 1,250.000 1,055.000 1,000.000 1,000.000 3,540.000 2,190.370 2,000.000 |
1006007 | PREP ROW (TREE)(GREATER THAN 24" DIA) | EA | 1.000 | 2,500.00 | 1 2 3 4 5 6 7 8 9 | 2,200.000 2,100.000 2,200.000 2,105.000 1,500.000 2,000.000 4,080.000 4,057.710 5,000.000 |
1056037 | REMOVING STAB BASE AND ASPH PAV(0"-16") | SY | 488.000 | 6.00 | 1 2 3 4 5 6 7 8 9 | 7.000 5.000 6.000 8.950 6.500 7.000 11.980 12.060 20.000 |
1106001 | EXCAVATION (ROADWAY) | CY | 144.000 | 10.00 | 1 2 3 4 5 6 7 8 9 | 13.000 25.000 11.000 27.350 12.000 25.000 84.604 35.260 20.000 |
1106002 | EXCAVATION (CHANNEL) | CY | 173.000 | 15.00 | 1 2 3 4 5 6 7 8 9 | 13.000 25.000 25.000 29.450 12.000 25.000 75.023 47.750 30.000 |
1326003002 | EMBANKMENT (FINAL)(ORD COMP)(TY B) | CY | 28.000 | 15.00 | 1 2 3 4 5 6 7 8 9 | 34.000 25.000 50.000 31.550 10.000 15.000 23.840 42.050 35.000 |
1616017 | COMPOST MANUF TOPSOIL (4") | SY | 566.000 | 2.00 | 1 2 3 4 5 6 7 8 9 | 2.780 4.000 6.450 6.750 6.000 2.650 3.037 6.620 10.000 |
1646023 | CELL FBR MLCH SEED(PERM)(RURAL)(CLAY) | SY | 566.000 | 1.00 | 1 2 3 4 5 6 7 8 9 | 2.220 2.250 1.700 2.250 1.550 2.150 1.560 1.890 2.000 |
1646029 | CELL FBR MLCH SEED(TEMP)(WARM) | SY | 283.000 | 0.50 | 1 2 3 4 5 6 7 8 9 | 4.450 4.500 3.400 4.250 3.100 4.250 3.120 3.780 2.000 |
1646031 | CELL FBR MLCH SEED(TEMP)(COOL) | SY | 283.000 | 0.50 | 1 2 3 4 5 6 7 8 9 | 4.450 4.500 0.500 4.250 3.100 4.250 3.120 3.780 2.000 |
1686001 | VEGETATIVE WATERING | MG | 13.300 | 18.50 | 1 2 3 4 5 6 7 8 9 | 89.920 62.200 88.000 140.000 45.000 100.000 75.500 173.920 100.000 |
1696003 | SOIL RETENTION BLANKETS (CL 1) (TY C) | SY | 87.000 | 1.50 | 1 2 3 4 5 6 7 8 9 | 1.050 1.050 3.300 1.050 3.000 1.000 2.600 4.490 10.000 |
2166001 | PROOF ROLLING | HR | 2.000 | 120.00 | 1 2 3 4 5 6 7 8 9 | 19.500 100.000 100.000 420.000 75.000 135.000 58.962 66.730 150.000 |
2476475003 | FL BS (CIP)(TY D GR 1-2, OR 5)FINAL POS | CY | 138.000 | 60.00 | 1 2 3 4 5 6 7 8 9 | 60.000 90.000 82.500 83.100 70.000 100.000 89.358 121.960 85.000 |
3106027 | PRIME COAT(MC-30 OR AE-P) | GAL | 155.000 | 4.00 | 1 2 3 4 5 6 7 8 9 | 12.000 10.700 11.000 10.500 11.000 10.000 11.016 10.420 10.000 |
3166224 | AGGR(TY-PB GR-4 SAC-B) | CY | 12.000 | 90.00 | 1 2 3 4 5 6 7 8 9 | 225.000 267.000 275.000 263.000 255.000 250.000 406.840 538.960 300.000 |
3166413 | ASPH(AC-15P, HFRS-2P OR CRS-2P) | GAL | 416.000 | 3.50 | 1 2 3 4 5 6 7 8 9 | 6.000 12.800 13.200 12.600 13.000 12.000 9.272 6.280 10.000 |
4006005 | CEM STABIL BKFL | CY | 19.000 | 110.00 | 1 2 3 4 5 6 7 8 9 | 135.000 200.000 175.000 200.000 155.000 190.000 138.250 229.960 250.000 |
4166002 | DRILL SHAFT (24 IN) | LF | 651.000 | 185.00 | 1 2 3 4 5 6 7 8 9 | 158.000 150.000 159.550 176.750 175.000 300.000 171.307 163.410 330.000 |
4206013 | CL C CONC (ABUT) | CY | 14.000 | 850.00 | 1 2 3 4 5 6 7 8 9 | 1,250.000 1,100.000 750.000 790.000 1,400.000 1,600.000 2,490.400 1,469.030 850.000 |
4206025 | CL C CONC (BENT) | CY | 19.600 | 875.00 | 1 2 3 4 5 6 7 8 9 | 1,200.000 1,100.000 1,000.000 1,080.000 1,400.000 2,500.000 1,754.595 1,447.970 1,200.000 |
4226015 | APPROACH SLAB | CY | 44.700 | 475.00 | 1 2 3 4 5 6 7 8 9 | 950.000 600.000 450.000 455.000 700.000 700.000 717.448 680.580 1,000.000 |
4226019 | SLAB SPAN | CY | 103.000 | 850.00 | 1 2 3 4 5 6 7 8 9 | 890.000 1,000.000 1,028.000 955.000 1,300.000 1,100.000 1,292.754 1,549.160 1,500.000 |
4326045 | RIPRAP (MOW STRIP)(4 IN) | CY | 10.000 | 450.00 | 1 2 3 4 5 6 7 8 9 | 515.000 950.000 450.000 615.000 525.000 525.000 636.000 919.960 550.000 |
4506006 | RAIL (TY T223) | LF | 184.000 | 110.00 | 1 2 3 4 5 6 7 8 9 | 93.000 100.000 110.000 95.000 110.000 155.000 222.600 180.340 185.000 |
4596001 | GABIONS (GALV) | CY | 18.000 | 300.00 | 1 2 3 4 5 6 7 8 9 | 253.000 250.000 253.000 320.000 235.000 230.000 243.298 566.110 300.000 |
4596007 | GABION MATTRESSES (GALV)(12 IN) | SY | 491.000 | 65.00 | 1 2 3 4 5 6 7 8 9 | 85.800 75.900 85.000 108.100 80.000 78.000 63.773 105.110 125.000 |
4646003 | RC PIPE (CL III)(18 IN) | LF | 20.000 | 55.00 | 1 2 3 4 5 6 7 8 9 | 80.000 113.000 75.000 65.000 80.000 50.000 64.240 122.110 85.000 |
4676363 | SET (TY II) (18 IN) (RCP) (6: 1) (P) | EA | 2.000 | 1,250.00 | 1 2 3 4 5 6 7 8 9 | 885.000 1,000.000 1,500.000 1,155.000 1,300.000 1,250.000 1,227.200 640.440 2,000.000 |
4966007 | REMOV STR (PIPE) | LF | 21.000 | 16.00 | 1 2 3 4 5 6 7 8 9 | 59.280 22.500 20.000 25.000 12.000 12.000 23.960 17.880 40.000 |
4966009 | REMOV STR (BRIDGE 0 - 99 FT LENGTH) | EA | 1.000 | 14,500.00 | 1 2 3 4 5 6 7 8 9 | 14,000.000 12,500.000 24,000.000 21,400.000 10,000.000 9,000.000 54,330.000 30,033.000 50,000.000 |
4966043 | REMOV STR (SMALL FENCE) | LF | 92.000 | 3.50 | 1 2 3 4 5 6 7 8 9 | 9.680 3.550 3.000 17.500 5.000 4.000 9.780 6.550 20.000 |
5006001 | MOBILIZATION | LS | 1.000 | 40,000.00 | 1 2 3 4 5 6 7 8 9 | 40,000.000 53,000.000 62,500.000 54,300.000 58,000.000 30,000.000 69,514.597 120,960.730 70,000.000 |
5026001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 5.000 | 1,500.00 | 1 2 3 4 5 6 7 8 9 | 1,500.000 3,000.000 2,381.000 2,500.000 2,500.000 1,500.000 1,481.265 743.730 4,000.000 |
5066002002 | ROCK FILTER DAMS (INSTALL) (TY 2) | LF | 77.000 | 30.00 | 1 2 3 4 5 6 7 8 9 | 26.250 29.800 27.500 26.300 35.000 25.000 29.068 34.900 30.000 |
5066011002 | ROCK FILTER DAMS (REMOVE) | LF | 77.000 | 8.50 | 1 2 3 4 5 6 7 8 9 | 17.060 10.700 16.500 25.350 16.250 16.250 10.400 11.800 15.000 |
5066038002 | TEMP SEDMT CONT FENCE (INSTALL) | LF | 656.000 | 2.50 | 1 2 3 4 5 6 7 8 9 | 2.620 2.600 2.750 2.650 4.000 2.500 2.517 2.910 4.000 |
5066039002 | TEMP SEDMT CONT FENCE (REMOVE) | LF | 656.000 | 0.60 | 1 2 3 4 5 6 7 8 9 | 0.780 1.050 0.750 1.150 0.750 0.750 1.040 0.710 2.000 |
5066043002 | BIODEG EROSN CONT LOGS (REMOVE) | LF | 146.000 | 1.25 | 1 2 3 4 5 6 7 8 9 | 1.570 2.150 1.650 2.500 2.000 1.500 2.080 1.810 12.000 |
5066045002 | BIODEG EROSN CONT LOGS (INSTL) (6") | LF | 146.000 | 1.50 | 1 2 3 4 5 6 7 8 9 | 4.200 4.250 4.400 6.700 5.000 4.000 4.160 8.080 16.000 |
5306005 | DRIVEWAYS (ACP) | SY | 26.000 | 35.00 | 1 2 3 4 5 6 7 8 9 | 148.200 64.200 56.000 85.000 65.000 75.000 41.435 148.690 45.000 |
5406001 | MTL W-BEAM GD FEN (TIM POST) | LF | 75.000 | 25.00 | 1 2 3 4 5 6 7 8 9 | 28.770 29.200 30.800 28.800 27.400 27.400 26.291 30.100 25.000 |
5406007 | MTL BEAM GD FEN TRANS (TL2) | EA | 2.000 | 1,000.00 | 1 2 3 4 5 6 7 8 9 | 1,029.000 1,050.000 1,078.000 1,031.000 980.000 980.000 1,279.200 1,421.470 1,850.000 |
5406016 | DOWNSTREAM ANCHOR TERMINAL SECTION | EA | 2.000 | 1,200.00 | 1 2 3 4 5 6 7 8 9 | 1,008.000 1,020.000 1,056.000 1,010.000 960.000 960.000 1,302.080 1,455.570 1,850.000 |
5406018 | MTL BM GD FEN TRANS (NON - SYM) | EA | 2.000 | 900.00 | 1 2 3 4 5 6 7 8 9 | 766.500 779.000 803.000 768.000 730.000 730.000 462.800 596.470 1,850.000 |
5426002 | REMOVE TERMINAL ANCHOR SECTION | EA | 4.000 | 200.00 | 1 2 3 4 5 6 7 8 9 | 157.500 160.000 100.000 210.000 150.000 150.000 636.000 300.990 500.000 |
5446001 | GUARDRAIL END TREATMENT (INSTALL) | EA | 2.000 | 2,500.00 | 1 2 3 4 5 6 7 8 9 | 2,903.250 2,950.000 3,041.500 2,909.000 2,765.000 2,765.000 3,057.600 3,362.970 2,850.000 |
5526003001 | WIRE FENCE (TY C) | LF | 365.000 | 6.50 | 1 2 3 4 5 6 7 8 9 | 2.880 16.000 10.000 20.500 12.000 12.000 20.644 24.430 4.000 |
60016001 | PORTABLE CHANGEABLE MESSAGE SIGN | DAY | 20.000 | 110.00 | 1 2 3 4 5 6 7 8 9 | 195.000 60.000 125.000 255.000 200.000 135.000 984.000 106.950 150.000 |