Tabulation of Bids for Project STP 2019(439)
Text version of this page | |||
County: | YOUNG | Let Date: | 01/09/19 |
Type: | LEVEL UP AND OVERLAY | Seq No: | 3241 |
Time: | 54 WORKING DAYS | Project ID: | STP 2019(439) |
Highway: | US 380 | Contract #: | 01193241 |
Length: | 8.674 | CCSJ: | 0134-03-032 |
Limits: | |||
From: | FM 2179 | Check: | $54,000 |
To: | JACK COUNTY LINE | Misc Cost: | $4,000.00 |
Estimate | $2,714,623.03 | % Over/Under | Company |
Bidder 1 | $2,678,507.13 | -1.33% | JAGOE-PUBLIC COMPANY |
Bidder 2 | $2,824,886.69 | +4.06% | DUININCK, INC. |
Bidder 3 | $2,863,494.83 | +5.48% | BLYTHE CONSTRUCTION, INC. |
Bidder 4 | $2,942,874.21 | +8.41% | A. L. HELMCAMP, INC. |
Bidder 5 | $2,993,451.44 | +10.27% | ZACK BURKETT CO. |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
1346001 | BACKFILL (TY A) | STA | 458.000 | 150.00 | 1 2 3 4 5 | 141.000 270.000 205.000 352.000 350.000 |
1646036 | DRILL SEEDING (PERM) (RURAL) (CLAY) | AC | 10.500 | 525.00 | 1 2 3 4 5 | 550.540 550.000 523.000 540.000 617.000 |
1646042 | DRILL SEEDING (TEMP) (WARM) | AC | 5.300 | 525.00 | 1 2 3 4 5 | 314.740 315.000 299.000 310.000 353.000 |
1646044 | DRILL SEEDING (TEMP) (COOL) | AC | 5.300 | 450.00 | 1 2 3 4 5 | 357.900 360.000 340.000 340.000 400.000 |
1686001 | VEGETATIVE WATERING | MG | 424.800 | 15.00 | 1 2 3 4 5 | 28.000 22.000 20.000 20.000 35.000 |
3416046001 | D-GR HMA TY-D PG70-28 | TON | 25,247.000 | 77.00 | 1 2 3 4 5 | 79.000 79.000 80.000 79.000 80.000 |
3416256001 | D-GR HMA TY-D PG70-28 (LEVEL-UP) | TON | 3,232.000 | 82.00 | 1 2 3 4 5 | 82.000 95.500 92.000 90.000 105.000 |
5006001 | MOBILIZATION | LS | 1.000 | 245,420.28 | 1 2 3 4 5 | 145,000.000 130,000.000 180,000.000 280,000.000 203,500.000 |
5026001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 3.000 | 5,000.00 | 1 2 3 4 5 | 3,500.000 20,500.000 14,000.000 9,000.000 5,000.000 |
5336001 | RUMBLE STRIPS (SHOULDER) | LF | 81,400.000 | 0.25 | 1 2 3 4 5 | 0.090 0.190 0.130 0.150 0.300 |
5336002 | RUMBLE STRIPS (CENTERLINE) | LF | 43,000.000 | 0.30 | 1 2 3 4 5 | 0.110 0.260 0.150 0.190 0.300 |
6626109 | WK ZN PAV MRK SHT TERM (TAB)TY W | EA | 210.000 | 1.00 | 1 2 3 4 5 | 0.700 1.050 1.900 0.600 1.000 |
6626111 | WK ZN PAV MRK SHT TERM (TAB)TY Y-2 | EA | 3,268.000 | 1.00 | 1 2 3 4 5 | 0.700 1.050 1.500 0.600 1.000 |
6666036007 | REFL PAV MRK TY I (W)8"(SLD)(100MIL) | LF | 300.000 | 1.00 | 1 2 3 4 5 | 1.320 1.300 1.250 1.300 1.260 |
6666300007 | RE PM W/RET REQ TY I (W)4"(BRK)(100MIL) | LF | 600.000 | 0.29 | 1 2 3 4 5 | 0.430 0.430 0.410 0.420 1.180 |
6666303007 | RE PM W/RET REQ TY I (W)4"(SLD)(100MIL) | LF | 89,856.000 | 0.25 | 1 2 3 4 5 | 0.380 0.380 0.360 0.370 0.570 |
6666312007 | RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL) | LF | 6,950.000 | 0.29 | 1 2 3 4 5 | 0.430 0.430 0.410 0.420 0.590 |
6666315007 | RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL) | LF | 53,237.000 | 0.25 | 1 2 3 4 5 | 0.380 0.380 0.360 0.370 0.580 |
6686077 | PREFAB PAV MRK TY C (W) (ARROW) | EA | 6.000 | 200.00 | 1 2 3 4 5 | 289.480 290.000 275.000 290.000 338.000 |
6686085 | PREFAB PAV MRK TY C (W) (WORD) | EA | 6.000 | 250.00 | 1 2 3 4 5 | 405.270 405.000 385.000 400.000 430.000 |
6726007 | REFL PAV MRKR TY I-C | EA | 30.000 | 3.00 | 1 2 3 4 5 | 3.950 3.950 3.750 4.000 29.500 |
6726009 | REFL PAV MRKR TY II-A-A | EA | 1,157.000 | 3.00 | 1 2 3 4 5 | 3.950 3.950 3.750 4.000 7.080 |
30666001 | BONDING COURSE | GAL | 22,952.000 | 3.00 | 1 2 3 4 5 | 2.990 3.100 4.200 3.250 3.550 |
61856002 | TMA (STATIONARY) | DAY | 36.000 | 175.00 | 1 2 3 4 5 | 360.000 265.000 625.000 200.000 175.000 |
61856005 | TMA (MOBILE OPERATION) | DAY | 10.000 | 300.00 | 1 2 3 4 5 | 1,470.000 1,000.000 850.000 200.000 65.000 |