Tabulation of Bids for Project STP 2017(760)HES
Text version of this page | |||
County: | BRAZOS | Let Date: | 02/02/17 |
Type: | HIGH FRICTION SURFACE TREATMENT | Seq No: | 3013 |
Time: | 12 WORKING DAYS | Project ID: | STP 2017(760)HES |
Highway: | SH 47 | Contract #: | 02173013 |
Length: | 0.230 | CCSJ: | 3138-02-011 |
Limits: | |||
From: | ON SH 47 | Check: | $2,000 |
To: | CURVE WEST(NORTH) OF FM 60 | Misc Cost: | $2,000.00 |
Estimate | $104,022.16 | % Over/Under | Company |
Bidder 1 | $65,138.90 | -37.38% | TOTAL HIGHWAY MAINTENANCE, LLC |
Bidder 2 | $102,084.00 | -1.86% | GIBSON & ASSOCIATES, INC. |
Bidder 3 | $105,362.65 | +1.29% | STRIPE-A-ZONE, INC. |
Bidder 4 | $129,250.50 | +24.25% | AMERICAN CIVIL CONSTRUCTORS WEST COAST LLC |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
5006001 | MOBILIZATION | LS | 1.000 | 6,750.00 | 1 2 3 4 | 4,000.000 11,000.000 9,000.000 12,500.000 |
5026001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 1.000 | 4,000.00 | 1 2 3 4 | 2,500.000 10,000.000 4,500.000 7,500.000 |
6666303 | RE PM W/RET REQ TY I (W)4"(SLD)(100MIL) | LF | 1,728.000 | 0.32 | 1 2 3 4 | 0.300 1.500 2.000 1.500 |
6666315 | RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL) | LF | 1,710.000 | 0.32 | 1 2 3 4 | 0.300 1.500 2.000 1.500 |
30376001 | HIGH FRICTION SURFACE COURSE | SY | 3,249.000 | 28.00 | 1 2 3 4 | 17.500 23.000 25.850 31.500 |
60016002 | PORTABLE CHANGEABLE MESSAGE SIGN | EA | 1.000 | 1,200.00 | 1 2 3 4 | 750.000 1,200.000 1,000.000 1,750.000 |