Tabulation of Bids for Project STP 2017(766)HES
Text version of this page | |||
County: | BAILEY | Let Date: | 02/02/17 |
Type: | INSTALL LED ADVANCE WARNING SIGNS | Seq No: | 3042 |
Time: | 7 WORKING DAYS | Project ID: | STP 2017(766)HES |
Highway: | FM 54 | Contract #: | 02173042 |
Length: | 0.758 | CCSJ: | 0563-02-011 |
Limits: | |||
From: | 3.973 MILES EAST OF SH 214 | Check: | $0.000 |
To: | 4.731 MILES EAST OF SH 214 | Misc Cost: | $500.000 |
Estimate | $11,000.00 | % Over/Under | Company |
Bidder 1 | $5,673.00 | -48.43% | L. UNITED BUILDING COMPANY |
Bidder 2 | $10,700.00 | -2.73% | M & S CONCRETE CO. |
Bidder 3 | $11,000.00 | +0.00% | SIGNAL SERVICES GROUP INC. |
Bidder 4 | $13,300.00 | +20.91% | VACA UNDERGROUND UTILITIES INC |
Bidder 5 | $13,743.00 | +24.94% | BXB GROUP INCORPORATION |
Bidder 6 | $14,600.00 | +32.73% | LIPHAM ASPHALT AND PAVING COMPANY, LLC |
Bidder 7 | $18,897.96 | +71.80% | AMERICAN LIGHTING AND SIGNALIZATION, INC. |
Bidder 8 | $27,200.00 | +147.27% | CHAMPION INFRASTRUCTURE, LLC |
Bidder 9 | $55,200.00 | +401.82% | NNA CONSTRUCTION & CONTRACTING |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
5006001 | MOBILIZATION | LS | 1.000 | 1,000.000 | 1 2 3 4 5 6 7 8 9 | 100.000 2,000.000 500.000 1,000.000 1,000.000 1,500.000 8,446.560 5,000.000 14,000.000 |
5026001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 1.000 | 2,000.000 | 1 2 3 4 5 6 7 8 9 | 500.000 1,000.000 500.000 100.000 519.000 500.000 1,492.800 3,000.000 16,000.000 |
6446004 | IN SM RD SN SUP&AM TY10BWG(1)SA(T) | EA | 2.000 | 1,000.000 | 1 2 3 4 5 6 7 8 9 | 300.000 650.000 1,200.000 1,200.000 2,826.000 1,600.000 538.560 1,100.000 2,000.000 |
6446076 | REMOVE SM RD SN SUP&AM | EA | 2.000 | 500.000 | 1 2 3 4 5 6 7 8 9 | 50.000 200.000 600.000 200.000 954.000 500.000 157.740 500.000 600.000 |
62276001 | SOLAR POWERED LED WARNING SIGN | EA | 2.000 | 2,500.000 | 1 2 3 4 5 6 7 8 9 | 2,186.500 3,000.000 3,200.000 4,700.000 2,332.000 4,200.000 3,783.000 8,000.000 10,000.000 |