Tabulation of Bids for Project BPM - 639323001
Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months.
The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.
Text version of this page | |||
County: | DALLAS | Let Date: | 03/03/22 |
Type: | BRIDGE REPAIR | Seq No: | 4008 |
Time: | 79 W | Project ID: | BPM - 639323001 |
Highway: | SH0352 | Contract #: | 03224008 |
Length: | 0.010 | CCSJ: | 6393-23-001 |
Limits: | |||
From: | VARIOUS LOCATIONS ALONG SH 352 IN | Check: | $8,000 |
To: | SOUTHEAST DALLAS COUNTY MAINTENANCE | Misc Cost: |
Estimate | $377,370.00 | % Over/Under | Company |
Bidder 1 | $389,185.00 | +3.13% | PATHFIELD INVESTMENTS LLC |
Bidder 2 | $511,710.00 | +35.60% | IBCTX, LLC |
Bidder 3 | $569,580.00 | +50.93% | HIGHWAY 19 CONSTRUCTION LLC |
Bidder 4 | $591,530.00 | +56.75% | RAGLE CONSTRUCTION, INC. |
Bidder 5 | $676,223.46 | +79.19% | SCOTT TUCKER CONSTRUCTION COMPANY, LLC |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
1006002 | PREPARING ROW | STA | 2.000 | 2,000.00 | 1 2 3 4 5 | 5,000.000 12,500.000 10,000.000 29,000.000 6,440.290 |
4206158 | CL C CONC(PILE ENCASEMENT) | LF | 899.000 | 350.00 | 1 2 3 4 5 | 375.000 450.000 500.000 420.000 616.460 |
5006001 | MOBILIZATION | LS | 1.000 | 35,000.00 | 1 2 3 4 5 | 10,000.000 51,100.000 50,000.000 59,000.000 67,580.000 |
5026001008 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 6.000 | 2,500.00 | 1 2 3 4 5 | 2,500.000 2,500.000 5,000.000 14,000.000 2,534.330 |
5066020002 | CONSTRUCTION EXITS (INSTALL) (TY 1) | SY | 224.000 | 20.00 | 1 2 3 4 5 | 50.000 50.000 35.000 35.000 65.170 |
5066024002 | CONSTRUCTION EXITS (REMOVE) | SY | 224.000 | 10.00 | 1 2 3 4 5 | 15.000 15.000 10.000 15.000 41.170 |
61856002002 | TMA (STATIONARY) | DAY | 10.000 | 200.00 | 1 2 3 4 5 | 250.000 150.000 1,000.000 175.000 253.920 |