Tabulation of Bids for Project RMC - 636959001
Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months.
The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.
Text version of this page | |||
County: | VICTORIA | Let Date: | 03/04/21 |
Type: | ON CALL CONCRETE PUNCHOUTS | Seq No: | 4021 |
Time: | 365 CALENDAR DAYS | Project ID: | RMC - 636959001 |
Highway: | US0059 | Contract #: | 03214021 |
Length: | 0.000 | CCSJ: | 6369-59-001 |
Limits: | |||
From: | . | Check: | $20,000 |
To: | . | Misc Cost: |
Estimate | $1,018,250.00 | % Over/Under | Company |
Bidder 1 | $979,700.00 | -3.79% | MAIN LANE INDUSTRIES LTD. |
Bidder 2 | $1,424,350.00 | +39.88% | O. TREVINO CONSTRUCTION, LLC |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
3406136003 | D-GR HMA(SQ) TY-D SAC-B PG76-22 | TON | 250.000 | 125.00 | 1 2 | 150.000 310.000 |
3616002 | FULL - DEPTH REPAIR CRCP (8") | SY | 450.000 | 460.00 | 1 2 | 420.000 335.000 |
3616004 | FULL - DEPTH REPAIR CRCP (10") | SY | 1,100.000 | 400.00 | 1 2 | 390.000 401.000 |
3616057 | FULL - DEPTH REPAIR CRCP (12")(SPL) | SY | 140.000 | 350.00 | 1 2 | 430.000 625.000 |
3616058 | FULL - DEPTH REPAIR CRCP (16")(SPL) | SY | 150.000 | 500.00 | 1 2 | 460.000 650.000 |
5006033 | MOBILIZATION (CALLOUT) | EA | 2.000 | 25,000.00 | 1 2 | 5,000.000 70,000.000 |
5026001008 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 6.000 | 4,000.00 | 1 2 | 9,000.000 20,000.000 |
7216002001 | FIBER REINFORCED POLYMER PATCHING MATLS | LB | 40,000.000 | 3.25 | 1 2 | 2.750 7.000 |
61856002002 | TMA (STATIONARY) | DAY | 60.000 | 200.00 | 1 2 | 350.000 500.000 |