The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.
Text version of this page | |||
County: | WALLER | Let Date: | 03/05/19 |
Type: | INSTALL MEDIAN BARRIER | Seq No: | 3028 |
Time: | 28 WORKING DAYS | Project ID: | STP 2019(486)HES |
Highway: | US 290 | Contract #: | 03193028 |
Length: | 1.401 | CCSJ: | 0114-11-080 |
Limits: | |||
From: | 4.098 MILES WEST OF SH 6 | Check: | $6,000 |
To: | 2.698 MILES WEST OF SH6 | Misc Cost: | $3,764.00 |
Estimate | $276,236.00 | % Over/Under | Company |
Bidder 1 | $349,012.00 | +26.35% | SCR CIVIL CONSTRUCTION, LLC |
Bidder 2 | $394,534.00 | +42.82% | CHAMPION INFRASTRUCTURE, LLC |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
1106001 | EXCAVATION (ROADWAY) | CY | 258.000 | 8.00 | 1 2 | 60.000 85.000 |
4326045 | RIPRAP (MOW STRIP)(4 IN) | CY | 258.000 | 450.00 | 1 2 | 620.000 740.000 |
5006001 | MOBILIZATION | LS | 1.000 | 35,000.00 | 1 2 | 35,500.000 32,000.000 |
5026001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 2.000 | 3,000.00 | 1 2 | 14,000.000 6,500.000 |
5436002 | CABLE BARRIER SYSTEM (TL-4) | LF | 6,706.000 | 12.00 | 1 2 | 12.000 14.000 |
5436020 | CABLE BARRIER TERMINAL SECTION (TL-4) | EA | 8.000 | 3,000.00 | 1 2 | 3,000.000 4,300.000 |
61856002 | TMA (STATIONARY) | DAY | 28.000 | 450.00 | 1 2 | 200.000 300.000 |