The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.
Text version of this page | |||
County: | UPSHUR | Let Date: | 03/06/24 |
Type: | REPLACE BRIDGE AND APPROACHES | Seq No: | 3222 |
Time: | 0 X | Project ID: | BR 2024(791) |
Highway: | FM 993 | Contract #: | 03243222 |
Length: | 0.066 | CCSJ: | 1511-01-013 |
Limits: | |||
From: | AT WEST GREASY CREEK | Check: | $38,000 |
To: | . | Misc Cost: |
Estimate | $2,229,422.25 | % Over/Under | Company |
Bidder 1 | $1,790,148.09 | -19.70% | THK CONSTRUCTION LLC |
Bidder 2 | $1,939,811.60 | -12.99% | TRUE ROADS CONSTRUCTION, LLC |
Bidder 3 | $1,994,460.00 | -10.54% | HODGES AND SON CONSTRUCTION COMPANY, INC. |
Bidder 4 | $2,039,492.20 | -8.52% | EAST TEXAS BRIDGE, INC. |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
1046009 | REMOVING CONC (RIPRAP) | SY | 122.000 | 45.00 | 1 2 3 4 | 7.000 10.000 18.000 30.000 |
1046054 | REMOVING CONCRETE(MOW STRIP) | LF | 650.000 | 15.00 | 1 2 3 4 | 5.000 4.000 6.000 15.000 |
1056076 | REMOV STAB BASE AND ASPH PAV (2"-15") | SY | 2,184.000 | 15.00 | 1 2 3 4 | 12.000 7.000 15.000 13.500 |
1106001 | EXCAVATION (ROADWAY) | CY | 508.000 | 30.00 | 1 2 3 4 | 20.000 24.000 15.000 25.000 |
1326006 | EMBANKMENT (FINAL)(DENS CONT)(TY C) | CY | 1,953.000 | 50.00 | 1 2 3 4 | 20.000 24.000 30.000 30.000 |
1606003 | FURNISHING AND PLACING TOPSOIL (4") | SY | 2,832.000 | 5.50 | 1 2 3 4 | 4.500 4.500 3.000 4.000 |
1646054 | BOND FBR MTRX SEED (PERM)(RURAL)(SAND) | SY | 2,832.000 | 1.50 | 1 2 3 4 | 2.680 0.700 2.000 1.100 |
1646055 | BONDED FBR MTRX SEED (TEMP)(WARM) | SY | 1,416.000 | 1.25 | 1 2 3 4 | 0.010 0.700 1.000 0.900 |
1646056 | BONDED FBR MTRX SEED (TEMP)(COOL) | SY | 1,416.000 | 1.25 | 1 2 3 4 | 0.010 0.700 1.000 0.900 |
1686001 | VEGETATIVE WATERING | MG | 91.000 | 160.00 | 1 2 3 4 | 10.000 30.000 1.000 10.000 |
1696002 | SOIL RETENTION BLANKETS (CL 1) (TY B) | SY | 160.000 | 4.50 | 1 2 3 4 | 2.000 2.400 4.000 2.000 |
2476236005 | FL BS (RDWY DEL)(TY A GR 1-2)(FNAL POS) | CY | 727.000 | 110.00 | 1 2 3 4 | 175.000 140.000 100.000 85.000 |
2756001 | CEMENT | TON | 95.000 | 325.00 | 1 2 3 4 | 250.000 350.000 300.000 375.000 |
2756010 | CEMENT TREAT (SUBGRADE) (8") | SY | 3,319.000 | 6.75 | 1 2 3 4 | 5.750 6.000 7.000 5.000 |
2756078 | CEMENT TREAT (NEW BASE)(DC)(8") | SY | 3,267.000 | 5.25 | 1 2 3 4 | 5.750 6.000 7.000 5.000 |
3106009 | PRIME COAT (MC-30) | GAL | 818.000 | 12.00 | 1 2 3 4 | 8.360 10.000 15.000 10.000 |
4006005 | CEM STABIL BKFL | CY | 137.000 | 300.00 | 1 2 3 4 | 300.000 310.000 300.000 300.000 |
4166002 | DRILL SHAFT (24 IN) | LF | 275.000 | 275.00 | 1 2 3 4 | 206.220 275.000 195.000 230.000 |
4166004 | DRILL SHAFT (36 IN) | LF | 240.000 | 375.00 | 1 2 3 4 | 272.070 425.000 275.000 315.000 |
4206014001 | CL C CONC (ABUT)(HPC) | CY | 27.800 | 1,700.00 | 1 2 3 4 | 1,100.000 1,385.000 1,600.000 1,400.000 |
4206030001 | CL C CONC (CAP)(HPC) | CY | 22.800 | 1,700.00 | 1 2 3 4 | 1,100.000 1,320.000 1,600.000 1,500.000 |
4206038001 | CL C CONC (COLUMN)(HPC) | CY | 8.500 | 2,000.00 | 1 2 3 4 | 1,500.000 1,575.000 1,800.000 1,500.000 |
4226008 | REINF CONC SLAB (SLAB BEAM)(HPC) | SF | 4,848.000 | 25.00 | 1 2 3 4 | 19.500 31.000 22.000 25.000 |
4226016 | APPROACH SLAB (HPC) | CY | 84.400 | 895.00 | 1 2 3 4 | 630.000 700.000 1,000.000 1,000.000 |
4256009001 | PRESTR CONC SLAB BEAM (4SB12) | LF | 414.000 | 250.00 | 1 2 3 4 | 235.000 280.000 250.000 230.000 |
4256010001 | PRESTR CONC SLAB BEAM (5SB12) | LF | 621.000 | 260.00 | 1 2 3 4 | 235.000 280.000 250.000 230.000 |
4326006 | RIPRAP (CONC)(CL B) | CY | 2.400 | 875.00 | 1 2 3 4 | 950.000 1,000.000 950.000 2,000.000 |
4326031 | RIPRAP (STONE PROTECTION)(12 IN) | CY | 566.000 | 225.00 | 1 2 3 4 | 160.000 175.000 200.000 200.000 |
4326039 | BEDDING MATERIAL (6 IN) | CY | 108.000 | 215.00 | 1 2 3 4 | 140.000 180.000 180.000 200.000 |
4326045 | RIPRAP (MOW STRIP)(4 IN) | CY | 30.000 | 740.00 | 1 2 3 4 | 750.000 600.000 600.000 800.000 |
4506111001 | RAIL (TY SSTR) (W/DRAIN SLOT) (HPC) | LF | 234.000 | 165.00 | 1 2 3 4 | 160.000 135.000 150.000 150.000 |
4546003 | ARMOR JOINT | LF | 88.000 | 195.00 | 1 2 3 4 | 150.000 90.000 200.000 100.000 |
4546004 | ARMOR JOINT (SEALED) | LF | 85.000 | 200.00 | 1 2 3 4 | 150.000 110.000 220.000 150.000 |
4646003001 | RC PIPE (CL III)(18 IN) | LF | 28.000 | 105.00 | 1 2 3 4 | 100.000 90.000 120.000 80.000 |
4676363 | SET (TY II) (18 IN) (RCP) (6: 1) (P) | EA | 2.000 | 1,700.00 | 1 2 3 4 | 1,000.000 1,500.000 2,500.000 1,200.000 |
4966009 | REMOV STR (BRIDGE 0 - 99 FT LENGTH) | EA | 1.000 | 40,000.00 | 1 2 3 4 | 25,000.000 31,000.000 50,000.000 25,000.000 |
4966016 | REMOV STR (PIPE) | EA | 1.000 | 2,000.00 | 1 2 3 4 | 500.000 525.000 1,000.000 500.000 |
4966043 | REMOV STR (SMALL FENCE) | LF | 858.000 | 15.00 | 1 2 3 4 | 5.000 4.500 5.000 8.000 |
5006001 | MOBILIZATION | LS | 1.000 | 175,000.00 | 1 2 3 4 | 175,000.000 60,000.000 150,000.000 200,000.000 |
5026001008 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 6.000 | 10,000.00 | 1 2 3 4 | 1,500.000 1,600.000 4,500.000 6,500.000 |
5066002005 | ROCK FILTER DAMS (INSTALL) (TY 2) | LF | 100.000 | 50.00 | 1 2 3 4 | 47.700 54.000 1.000 42.000 |
5066003005 | ROCK FILTER DAMS (INSTALL) (TY 3) | LF | 15.000 | 75.00 | 1 2 3 4 | 53.000 96.000 1.000 55.000 |
5066011005 | ROCK FILTER DAMS (REMOVE) | LF | 115.000 | 18.00 | 1 2 3 4 | 10.600 18.000 1.000 16.000 |
5066020005 | CONSTRUCTION EXITS (INSTALL) (TY 1) | SY | 160.000 | 37.50 | 1 2 3 4 | 37.100 42.000 1.000 40.000 |
5066024005 | CONSTRUCTION EXITS (REMOVE) | SY | 160.000 | 13.00 | 1 2 3 4 | 7.420 12.000 1.000 16.000 |
5066038005 | TEMP SEDMT CONT FENCE (INSTALL) | LF | 1,608.000 | 5.00 | 1 2 3 4 | 4.770 4.500 1.000 4.500 |
5066039005 | TEMP SEDMT CONT FENCE (REMOVE) | LF | 1,608.000 | 1.75 | 1 2 3 4 | 1.060 0.300 1.000 1.500 |
5066042005 | BIODEG EROSN CONT LOGS (INSTL) (18") | LF | 355.000 | 12.00 | 1 2 3 4 | 12.460 6.000 5.000 11.000 |
5066043005 | BIODEG EROSN CONT LOGS (REMOVE) | LF | 355.000 | 2.75 | 1 2 3 4 | 1.590 1.200 1.000 5.500 |
5306005 | DRIVEWAYS (ACP) | SY | 119.000 | 115.00 | 1 2 3 4 | 25.160 100.000 120.000 75.000 |
5406001001 | MTL W-BEAM GD FEN (TIM POST) | LF | 287.500 | 30.00 | 1 2 3 4 | 25.000 27.000 24.000 25.000 |
5406006001 | MTL BEAM GD FEN TRANS (THRIE-BEAM) | EA | 4.000 | 2,500.00 | 1 2 3 4 | 1,749.000 2,000.000 1,700.000 1,850.000 |
5426001 | REMOVE METAL BEAM GUARD FENCE | LF | 400.000 | 6.75 | 1 2 3 4 | 2.120 2.400 2.000 2.500 |
5426005 | RM MTL BM GD FEN TRANS (T101) | EA | 4.000 | 300.00 | 1 2 3 4 | 159.000 180.000 150.000 200.000 |
5446001 | GUARDRAIL END TREATMENT (INSTALL) | EA | 4.000 | 3,450.00 | 1 2 3 4 | 3,047.500 3,450.000 2,900.000 3,200.000 |
5446003 | GUARDRAIL END TREATMENT (REMOVE) | EA | 4.000 | 410.00 | 1 2 3 4 | 212.000 240.000 500.000 250.000 |
5526003 | WIRE FENCE (TY C) | LF | 760.000 | 35.00 | 1 2 3 4 | 20.000 21.000 20.000 32.000 |
5526005 | GATE (TY 1) | EA | 1.000 | 3,450.00 | 1 2 3 4 | 500.000 900.000 2,000.000 1,200.000 |
6446001 | IN SM RD SN SUP&AM TY10BWG(1)SA(P) | EA | 1.000 | 950.00 | 1 2 3 4 | 1,500.000 1,200.000 1,500.000 1,700.000 |
6446060 | IN SM RD SN SUP&AM TYTWT(1)WS(P) | EA | 2.000 | 900.00 | 1 2 3 4 | 1,500.000 1,200.000 1,500.000 1,400.000 |
6446076 | REMOVE SM RD SN SUP&AM | EA | 1.000 | 155.00 | 1 2 3 4 | 500.000 180.000 500.000 100.000 |
6586014 | INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI) | EA | 4.000 | 45.00 | 1 2 3 4 | 21.200 24.000 20.000 30.000 |
6586016 | INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BI) | EA | 7.000 | 35.00 | 1 2 3 4 | 21.200 24.000 20.000 30.000 |
6626109 | WK ZN PAV MRK SHT TERM (TAB)TY W | EA | 100.000 | 2.50 | 1 2 3 4 | 0.100 2.400 5.000 3.000 |
6626111 | WK ZN PAV MRK SHT TERM (TAB)TY Y-2 | EA | 100.000 | 3.00 | 1 2 3 4 | 0.100 2.400 5.000 3.000 |
6666225007 | PAVEMENT SEALER 6" | LF | 608.000 | 1.00 | 1 2 3 4 | 2.120 2.400 2.000 2.200 |
6726009 | REFL PAV MRKR TY II-A-A | EA | 22.000 | 8.00 | 1 2 3 4 | 10.600 12.000 10.000 11.000 |
6786002 | PAV SURF PREP FOR MRK (6") | LF | 608.000 | 0.75 | 1 2 3 4 | 2.120 2.400 2.000 2.200 |
6786033 | PAV SURF PREP FOR MRK (RPM) | EA | 4.000 | 1.50 | 1 2 3 4 | 26.500 30.000 25.000 27.500 |
30776032 | SP MIXES SP-C PG76-22 | TON | 352.000 | 180.00 | 1 2 3 4 | 207.790 234.000 300.000 245.000 |
60016002 | PORTABLE CHANGEABLE MESSAGE SIGN | EA | 2.000 | 15,950.00 | 1 2 3 4 | 10,000.000 18,000.000 10,000.000 15,000.000 |
61496004 | REFL PAV MRK AWT (W) 6" (SLD) (100MIL) | LF | 1,720.000 | 1.40 | 1 2 3 4 | 3.180 3.600 3.000 3.300 |
61496010 | REFL PAV MRK AWT (Y) 6" (SLD) (100MIL) | LF | 1,720.000 | 1.50 | 1 2 3 4 | 3.180 3.600 3.000 3.300 |
61856002002 | TMA (STATIONARY) | DAY | 5.000 | 400.00 | 1 2 3 4 | 400.000 240.000 150.000 300.000 |
61856003002 | TMA (MOBILE OPERATION) | HR | 60.000 | 92.00 | 1 2 3 4 | 35.000 60.000 20.000 30.000 |