Tabulation of Bids for Project NH 2018(065)
Text version of this page | |||
County: | BEXAR | Let Date: | 04/03/18 |
Type: | STRUCTURE REPAIR/REPLACE BRG EXPANSION JOINTS | Seq No: | 3003 |
Time: | 178 WORKING DAYS | Project ID: | NH 2018(065) |
Highway: | IH 35 | Contract #: | 04183003 |
Length: | 4.372 | CCSJ: | 0017-10-267 |
Limits: | |||
From: | VARIOUS LOCATIONS ON IH 35 | Check: | $100,000 |
To: | LAREDO ST TO 0.2 MI W OF IH 37 | Misc Cost: | $85,000.00 |
Estimate | $5,557,970.00 | % Over/Under | Company |
Bidder 1 | $4,831,650.00 | -13.07% | CHAMPION INFRASTRUCTURE, LLC |
Bidder 2 | $5,062,088.00 | -8.92% | DBI SERVICES, LLC |
Bidder 3 | $5,376,186.00 | -3.27% | CEKRA INC. |
Bidder 4 | $5,804,113.00 | +4.43% | GIBSON & ASSOCIATES, INC. |
Bidder 5 | $6,494,545.00 | +16.85% | RESTEK, INC. |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
5006001 | MOBILIZATION | LS | 1.000 | 424,170.00 | 1 2 3 4 5 | 650,000.000 500,000.000 500,000.000 452,000.000 500,000.000 |
5026001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 15.000 | 20,000.00 | 1 2 3 4 5 | 16,000.000 2,500.000 15,000.000 42,750.000 50,000.000 |
7856012 | BRIDGE JOINT REPLACEMENT (FINGER) | LF | 9,336.000 | 500.00 | 1 2 3 4 5 | 400.000 458.000 476.000 485.500 540.000 |
61856002 | TMA (STATIONARY) | DAY | 829.000 | 200.00 | 1 2 3 4 5 | 250.000 300.000 250.000 215.000 245.000 |