Tabulation of Bids for Project HP 2012(770)
| Text version of this page | |||
| County: | RED RIVER | Let Date: | 04/03/13 |
| Type: | PAVING, BASE WORK, OVERLAY, ETC. | Seq No: | 3006 |
| Time: | 58 WORKING DAYS | Project ID: | HP 2012(770) |
| Highway: | CR | Contract #: | 04133006 |
| Length: | 7.247 | CCSJ: | 0901-27-044 |
| Limits: | |||
| From: | ON CR 3230 & CR 3240 FROM FM 1158 | Check: | $9,000.00 |
| To: | FM 1159 | Misc Cost: | $16,200.00 |
| Estimate | $799,791.44 | % Over/Under | Company |
| Bidder 1 | $488,684.78 | -38.90% | SAMMY GIST ENTERPRISES, INC. |
| Bidder 2 | $746,569.27 | -6.65% | D. L. LENNON INCORPORATED - CONTRACTOR |
| Bidder 3 | $825,077.40 | +3.16% | EAST TEXAS BRIDGE, INC. |
| Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
| 1342002 | BACKFILL (TY B) | STA | 224.300 | 115.00 | 1 2 3 |
10.000 250.000 250.000 |
| 1642023 | CELL FBR MLCH SEED (PERM) (RURAL) (CLAY) | SY | 18108.000 | 0.18 | 1 2 3 |
0.180 0.490 0.300 |
| 1682001 | VEGETATIVE WATERING | MG | 76.000 | 10.00 | 1 2 3 |
0.010 0.010 15.000 |
| 2472209 | FL BS (CMP IN PLC) (TY D GR 4) (4") | SY | 28555.000 | 8.00 | 1 2 3 |
4.400 9.990 8.500 |
| 3102001 | PRIME COAT (MC - 30) | GAL | 4283.000 | 6.00 | 1 2 3 |
4.250 6.000 5.000 |
| 3162006 | ASPH (AC - 20 - 5TR) | GAL | 10280.000 | 5.50 | 1 2 3 |
3.210 5.000 4.500 |
| 3162221 | AGGR (TY - PB GR - 3 SAC - B) | CY | 272.000 | 80.00 | 1 2 3 |
77.000 85.000 91.000 |
| 5002001 | MOBILIZATION | LS | 1.000 | 59250.00 | 1 2 3 |
1.000 69000.000 80000.000 |
| 5022001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 3.000 | 2400.00 | 1 2 3 |
1083.000 2150.000 13000.000 |
| 11222037 | TEMPORARY SEDIMENT CONTROL FENCE INSTL | LF | 350.000 | 2.50 | 1 2 3 |
3.000 3.000 5.000 |
| 11222057 | TEMPORARY SEDIMENT CONTROL FENCE REMOV | LF | 350.000 | 0.70 | 1 2 3 |
0.500 0.500 2.000 |
| 1642023 | CELL FBR MLCH SEED (PERM) (RURAL) (CLAY) | SY | 15250.000 | 0.18 | 1 2 3 |
0.180 0.490 0.400 |
| 1682001 | VEGETATIVE WATERING | MG | 64.000 | 10.00 | 1 2 3 |
0.010 0.010 15.000 |
| 3512006 | FLEXIBLE PAVEMENT STRUCTURE REPAIR (10" | SY | 3660.000 | 55.00 | 1 2 3 |
45.000 15.000 26.000 |
| 5022001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 1.000 | 2400.00 | 1 2 3 |
1083.000 2150.000 50000.000 |
| 11222037 | TEMPORARY SEDIMENT CONTROL FENCE INSTL | LF | 250.000 | 2.50 | 1 2 3 |
3.000 3.000 5.000 |
| 11222057 | TEMPORARY SEDIMENT CONTROL FENCE REMOV | LF | 250.000 | 0.70 | 1 2 3 |
0.500 0.500 2.000 |
| 3162006 | ASPH (AC - 20 - 5TR) | GAL | 5490.000 | 5.50 | 1 2 3 |
3.210 5.000 4.500 |
| 3162221 | AGGR (TY - PB GR - 3 SAC - B) | CY | 145.000 | 80.00 | 1 2 3 |
77.000 85.000 100.000 |
| 3162006 | ASPH (AC - 20 - 5TR) | GAL | 5490.000 | 5.50 | 1 2 3 |
3.210 5.000 4.500 |
| 3162221 | AGGR (TY - PB GR - 3 SAC - B) | CY | 145.000 | 80.00 | 1 2 3 |
77.000 85.000 100.000 |
| 3162006 | ASPH (AC - 20 - 5TR) | GAL | 6214.000 | 5.50 | 1 2 3 |
3.210 5.000 4.500 |
| 3162221 | AGGR (TY - PB GR - 3 SAC - B) | CY | 164.000 | 80.00 | 1 2 3 |
77.000 85.000 100.000 |
| 3162006 | ASPH (AC - 20 - 5TR) | GAL | 4065.000 | 5.50 | 1 2 3 |
3.210 5.000 4.500 |
| 3162221 | AGGR (TY - PB GR - 3 SAC - B) | CY | 108.000 | 80.00 | 1 2 3 |
77.000 85.000 100.000 |