Tabulation of Bids for Project BPM - 631862001
Text version of this page | |||
County: | GRAYSON | Let Date: | 04/03/18 |
Type: | EROSION REPAIR-INSTALL SOIL NAIL RETAINING WALL | Seq No: | 4001 |
Time: | 75 W | Project ID: | BPM - 631862001 |
Highway: | FM0084 | Contract #: | 04184001 |
Length: | 0.001 | CCSJ: | 6318-62-001 |
Limits: | |||
From: | FM 84 AT THE | Check: | $10,000 |
To: | UNION PACIFIC RAILROAD | Misc Cost: | $3,000.00 |
Estimate | $520,487.50 | % Over/Under | Company |
Bidder 1 | $629,000.00 | +20.85% | ED BELL CONSTRUCTION COMPANY |
Bidder 2 | $688,502.00 | +32.28% | GHB EQUIPMENT COMPANY, L.L.C. |
Bidder 3 | $692,993.50 | +33.14% | WEST TEXAS REBAR PLACERS INC. |
Bidder 4 | $737,375.00 | +41.67% | FNH CONSTRUCTION, LLC |
Bidder 5 | $907,953.00 | +74.44% | IOWA BRIDGE & CULVERT, LC |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
1046009 | REMOVING CONC (RIPRAP) | SY | 1,027.000 | 25.00 | 1 2 3 4 5 | 11.550 30.000 20.000 20.000 100.000 |
1106001 | EXCAVATION (ROADWAY) | CY | 1,900.000 | 20.00 | 1 2 3 4 5 | 21.000 20.000 20.000 20.000 50.000 |
1626002 | BLOCK SODDING | SY | 1,350.000 | 5.00 | 1 2 3 4 5 | 6.300 4.000 5.000 5.500 6.000 |
4016001 | FLOWABLE BACKFILL | CY | 60.000 | 200.00 | 1 2 3 4 5 | 420.000 350.000 200.000 350.000 280.000 |
4106001 | SOIL NAIL ANCHORS | LF | 7,936.000 | 20.00 | 1 2 3 4 5 | 21.000 37.000 41.000 30.000 18.000 |
4236022 | RETAINING WALL (SOIL NAIL)(FACIA) | SF | 2,965.000 | 45.00 | 1 2 3 4 5 | 63.000 50.000 52.500 70.000 85.000 |
4326001 | RIPRAP (CONC)(4 IN) | CY | 43.000 | 550.00 | 1 2 3 4 5 | 525.000 350.000 500.000 550.000 1,200.000 |
4326031 | RIPRAP (STONE PROTECTION)(12 IN) | CY | 50.000 | 100.00 | 1 2 3 4 5 | 157.500 160.000 150.000 185.000 300.000 |
4326045 | RIPRAP (MOW STRIP)(4 IN) | CY | 38.200 | 650.00 | 1 2 3 4 5 | 525.000 350.000 500.000 550.000 500.000 |
5006001 | MOBILIZATION | LS | 1.000 | 45,000.00 | 1 2 3 4 5 | 51,522.220 68,000.000 40,000.000 70,000.000 90,000.000 |
5026001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 5.000 | 3,000.00 | 1 2 3 4 5 | 11,550.000 2,000.000 2,500.000 8,500.000 5,000.000 |
5066038002 | TEMP SEDMT CONT FENCE (INSTALL) | LF | 345.000 | 5.00 | 1 2 3 4 5 | 1.860 7.000 4.000 4.000 10.000 |
5066039002 | TEMP SEDMT CONT FENCE (REMOVE) | LF | 345.000 | 2.50 | 1 2 3 4 5 | 0.270 1.000 1.000 2.000 2.000 |
5406002 | MTL W-BEAM GD FEN (STEEL POST) | LF | 300.000 | 25.00 | 1 2 3 4 5 | 23.960 23.000 23.000 30.000 25.000 |
5406006 | MTL BEAM GD FEN TRANS (THRIE-BEAM) | EA | 4.000 | 1,500.00 | 1 2 3 4 5 | 1,911.460 2,000.000 2,000.000 1,850.000 2,000.000 |
5426001 | REMOVE METAL BEAM GUARD FENCE | LF | 400.000 | 2.50 | 1 2 3 4 5 | 2.660 5.000 2.000 3.000 20.000 |
5426002 | REMOVE TERMINAL ANCHOR SECTION | EA | 4.000 | 250.00 | 1 2 3 4 5 | 197.030 500.000 250.000 500.000 360.000 |
5446001 | GUARDRAIL END TREATMENT (INSTALL) | EA | 4.000 | 2,750.00 | 1 2 3 4 5 | 2,369.630 3,000.000 2,800.000 2,550.000 2,600.000 |
6586014 | INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI) | EA | 4.000 | 35.00 | 1 2 3 4 5 | 25.560 30.000 50.000 100.000 30.000 |
6586062 | INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) | EA | 6.000 | 35.00 | 1 2 3 4 5 | 25.560 35.000 40.000 100.000 30.000 |
61856002 | TMA (STATIONARY) | DAY | 10.000 | 300.00 | 1 2 3 4 5 | 315.000 300.000 400.000 550.000 5,000.000 |