The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.
Text version of this page | |||
County: | WHARTON | Let Date: | 04/06/22 |
Type: | BRIDGE REPLACEMENT | Seq No: | 3019 |
Time: | 184 WORKING DAYS | Project ID: | BR 2020(604) |
Highway: | CR | Contract #: | 04223019 |
Length: | 0.196 | CCSJ: | 0913-09-109 |
Limits: | |||
From: | AT EAGLE BRANCH | Check: | $28,000 |
To: | STR# AA03-56-001 (CR 268) | Misc Cost: |
Estimate | $1,380,359.25 | % Over/Under | Company |
Bidder 1 | $1,626,862.50 | +17.86% | TEXAS STEEL INDUSTRIAL PLACING, LLC |
Bidder 2 | $1,646,466.32 | +19.28% | TREVWAY, INC. |
Bidder 3 | $1,899,961.38 | +37.64% | SB CONTRACTORS LLC |
Bidder 4 | $1,923,908.45 | +39.38% | 3LW CIVIL LLC |
Bidder 5 | $1,941,948.80 | +40.68% | JOHN REED AND COMPANY, LLC |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
1006002 | PREPARING ROW | STA | 9.010 | 3,500.00 | 1 2 3 4 5 | 2,000.000 2,500.000 5,000.000 1,100.000 8,000.000 |
1106001 | EXCAVATION (ROADWAY) | CY | 276.000 | 20.00 | 1 2 3 4 5 | 20.000 16.430 52.100 30.000 80.000 |
1106002 | EXCAVATION (CHANNEL) | CY | 682.000 | 20.00 | 1 2 3 4 5 | 25.000 13.300 30.850 30.000 60.000 |
1326005 | EMBANKMENT (FINAL)(ORD COMP)(TY C) | CY | 1,051.000 | 25.00 | 1 2 3 4 5 | 25.000 25.000 43.190 40.000 80.000 |
1506002 | BLADING | HR | 48.000 | 120.00 | 1 2 3 4 5 | 125.000 100.000 101.950 150.000 120.000 |
1646003 | BROADCAST SEED (PERM) (RURAL) (CLAY) | SY | 5,039.000 | 1.50 | 1 2 3 4 5 | 1.500 1.540 1.770 1.000 2.000 |
1646009 | BROADCAST SEED (TEMP) (WARM) | SY | 1,261.000 | 1.50 | 1 2 3 4 5 | 5.000 1.280 5.960 1.000 2.000 |
1646011 | BROADCAST SEED (TEMP) (COOL) | SY | 1,261.000 | 1.50 | 1 2 3 4 5 | 5.000 1.280 5.960 1.000 2.000 |
1686001 | VEGETATIVE WATERING | MG | 51.500 | 25.00 | 1 2 3 4 5 | 50.000 46.290 85.230 25.000 95.000 |
2476366003 | FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS) | CY | 544.000 | 110.00 | 1 2 3 4 5 | 115.000 180.000 119.560 85.000 120.000 |
2516013 | REWORK BS MTL (TY C) (6") (ORD COMP) | STA | 298.000 | 2.25 | 1 2 3 4 5 | 65.000 25.000 53.610 95.000 200.000 |
3166029002 | ASPH (RC-250) | GAL | 218.000 | 15.00 | 1 2 3 4 5 | 20.000 21.960 21.850 40.000 8.000 |
3166202002 | AGGR(TY-E GR-5 SAC-B) | CY | 8.000 | 120.00 | 1 2 3 4 5 | 1,200.000 1,282.000 1,267.570 700.000 500.000 |
3166249002 | AGGR(TY-PE GR-4 SAC-B) | CY | 8.000 | 120.00 | 1 2 3 4 5 | 1,200.000 1,282.000 1,267.570 600.000 600.000 |
3166400002 | ASPH (AC-15P OR AC-10-2TR OR CRS-2P) | GAL | 369.000 | 20.00 | 1 2 3 4 5 | 20.000 16.440 16.360 20.000 25.000 |
4006005 | CEM STABIL BKFL | CY | 265.000 | 125.00 | 1 2 3 4 5 | 150.000 100.000 225.240 190.000 90.000 |
4096002 | PRESTR CONC PIL (18 IN SQ) | LF | 1,420.000 | 150.00 | 1 2 3 4 5 | 245.000 171.000 157.540 175.000 195.000 |
4206013 | CL C CONC (ABUT) | CY | 68.600 | 1,200.00 | 1 2 3 4 5 | 1,050.000 993.000 1,533.150 1,400.000 1,800.000 |
4226005 | REINF CONC SLAB (BOX BEAM) | SF | 1,701.000 | 21.00 | 1 2 3 4 5 | 20.000 25.000 43.340 19.000 40.000 |
4226007 | REINF CONC SLAB (SLAB BEAM) | SF | 2,600.000 | 25.00 | 1 2 3 4 5 | 20.000 25.000 50.890 24.000 40.000 |
4226023 | SHEAR KEY | CY | 8.600 | 400.00 | 1 2 3 4 5 | 1,850.000 394.000 1,078.400 400.000 160.000 |
4256001 | PRESTR CONC BOX BEAM (4B20) | LF | 258.000 | 215.00 | 1 2 3 4 5 | 325.000 298.000 356.010 255.000 230.000 |
4256002 | PRESTR CONC BOX BEAM (5B20) | LF | 129.000 | 220.00 | 1 2 3 4 5 | 350.000 332.000 341.390 260.000 230.000 |
4256012 | PRESTR CONC SLAB BEAM (5SB15) | LF | 494.910 | 225.00 | 1 2 3 4 5 | 325.000 275.000 361.120 245.000 230.000 |
4326033 | RIPRAP (STONE PROTECTION)(18 IN) | CY | 920.000 | 200.00 | 1 2 3 4 5 | 210.000 295.000 209.660 205.000 150.000 |
4506006001 | RAIL (TY T223) | LF | 410.000 | 100.00 | 1 2 3 4 5 | 125.000 100.000 170.480 155.000 150.000 |
4546004 | ARMOR JOINT (SEALED) | LF | 133.600 | 85.00 | 1 2 3 4 5 | 100.000 88.000 264.630 85.000 140.000 |
4646008001 | RC PIPE (CL III)(36 IN) | LF | 282.000 | 140.00 | 1 2 3 4 5 | 130.000 146.000 0.000 190.000 320.000 |
4676454 | SET (TY II) (36 IN) (RCP) (6: 1) (P) | EA | 3.000 | 4,000.00 | 1 2 3 4 5 | 4,000.000 8,427.000 0.000 5,500.000 3,000.000 |
4966009 | REMOV STR (BRIDGE 0 - 99 FT LENGTH) | EA | 3.000 | 25,000.00 | 1 2 3 4 5 | 20,000.000 25,000.000 15,764.910 14,000.000 30,000.000 |
5006001 | MOBILIZATION | LS | 1.000 | 125,000.00 | 1 2 3 4 5 | 100,000.000 160,000.000 169,000.000 310,000.000 140,000.000 |
5026001008 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 13.000 | 2,000.00 | 1 2 3 4 5 | 1,150.000 1,200.000 1,500.000 20,000.000 6,500.000 |
5066038002 | TEMP SEDMT CONT FENCE (INSTALL) | LF | 1,367.000 | 3.00 | 1 2 3 4 5 | 3.500 3.000 9.910 1.000 5.000 |
5066039002 | TEMP SEDMT CONT FENCE (REMOVE) | LF | 1,367.000 | 1.00 | 1 2 3 4 5 | 1.250 1.000 2.250 1.000 3.000 |
5306016 | DRIVEWAYS (BASE) | SY | 134.000 | 35.00 | 1 2 3 4 5 | 30.000 65.000 98.370 33.000 70.000 |
5406001001 | MTL W-BEAM GD FEN (TIM POST) | LF | 125.000 | 25.00 | 1 2 3 4 5 | 39.000 47.000 47.530 26.000 80.000 |
5406006001 | MTL BEAM GD FEN TRANS (THRIE-BEAM) | EA | 9.000 | 2,000.00 | 1 2 3 4 5 | 2,430.000 2,022.000 2,461.330 2,100.000 3,500.000 |
5406007001 | MTL BEAM GD FEN TRANS (TL2) | EA | 3.000 | 1,500.00 | 1 2 3 4 5 | 1,800.000 1,818.000 1,519.970 1,300.000 3,000.000 |
5406016001 | DOWNSTREAM ANCHOR TERMINAL SECTION | EA | 2.000 | 1,500.00 | 1 2 3 4 5 | 1,700.000 2,474.000 1,757.550 1,450.000 3,000.000 |
5446001 | GUARDRAIL END TREATMENT (INSTALL) | EA | 10.000 | 3,000.00 | 1 2 3 4 5 | 3,750.000 3,298.000 4,074.540 2,950.000 4,000.000 |
6586014 | INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI) | EA | 14.000 | 35.00 | 1 2 3 4 5 | 50.000 55.000 25.540 30.000 80.000 |
6586062 | INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) | EA | 25.000 | 40.00 | 1 2 3 4 5 | 50.000 55.000 38.320 35.000 80.000 |
4676445 | SET (TY II) (36 IN) (HDPE) (6: 1) (P) | EA | 3.000 | 4,000.00 | 1 2 3 4 5 | 0.000 0.000 11,796.770 0.000 0.000 |
41226026 | THERMO PIPE(36")(PP)(TY S)(TY II) | LF | 282.000 | 140.00 | 1 2 3 4 5 | 0.000 0.000 116.740 0.000 0.000 |