Tabulation of Bids for Project BPM - 631242001
Text version of this page | |||
County: | FANNIN | Let Date: | 04/20/17 |
Type: | EROSION REPAIR | Seq No: | 0103 |
Time: | 27 W | Project ID: | BPM - 631242001 |
Highway: | FM0824 | Contract #: | 04170103 |
Length: | 0.000 | CCSJ: | 6312-42-001 |
Limits: | |||
From: | FM 824 BRIDGE AT | Check: | $3,000 |
To: | MCCLURE CREEK | Misc Cost: |
Estimate | $173,013.75 | % Over/Under | Company |
Bidder 1 | $168,515.00 | -2.60% | HARTBEAT CONSTRUCTION |
Bidder 2 | $171,269.00 | -1.01% | SHIRLEY & SONS CONSTRUCTION CO., INC. |
Bidder 3 | $180,814.00 | +4.51% | BXB GROUP INCORPORATION |
Bidder 4 | $190,090.00 | +9.87% | SJ&J CONSTRUCTION, LLC |
Bidder 5 | $217,700.00 | +25.83% | DRS CONSTRUCTION, INC. |
Bidder 6 | $228,390.00 | +32.01% | L.C. JORDAN & SON |
Bidder 7 | $249,479.00 | +44.20% | CHAMPION INFRASTRUCTURE, LLC |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
1006001 | PREPARING ROW | AC | 0.150 | 25,000.00 | 1 2 3 4 5 6 7 | 17,500.000 1,000.000 59,800.000 5,000.000 10,000.000 25,000.000 4,500.000 |
1046009 | REMOVING CONC (RIPRAP) | SY | 22.000 | 35.00 | 1 2 3 4 5 6 7 | 50.000 100.000 96.000 30.000 60.000 40.000 73.000 |
1106002 | EXCAVATION (CHANNEL) | CY | 40.000 | 80.00 | 1 2 3 4 5 6 7 | 32.000 10.000 101.000 22.000 45.000 35.000 85.000 |
1326007 | EMBANKMENT (FINAL)(ORD COMP)(TY D) | CY | 120.000 | 40.00 | 1 2 3 4 5 6 7 | 27.000 35.000 91.000 28.000 30.000 40.000 42.000 |
1326019 | EMBANKMENT (VEHICLE)(ORD COMP)(TY B) | CY | 84.000 | 30.00 | 1 2 3 4 5 6 7 | 27.000 35.000 76.000 30.000 30.000 40.000 62.000 |
4326032 | RIPRAP (STONE PROTECTION)(15 IN) | CY | 522.000 | 185.00 | 1 2 3 4 5 6 7 | 165.000 167.000 156.000 180.000 275.000 275.000 310.000 |
4326045 | RIPRAP (MOW STRIP)(4 IN) | CY | 18.000 | 375.00 | 1 2 3 4 5 6 7 | 654.000 660.000 561.000 700.000 700.000 500.000 845.000 |
5006001 | MOBILIZATION | LS | 1.000 | 19,223.75 | 1 2 3 4 5 6 7 | 28,000.000 30,000.000 13,750.000 40,000.000 20,000.000 20,000.000 15,000.000 |
5026001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 2.000 | 3,500.00 | 1 2 3 4 5 6 7 | 2,200.000 2,000.000 2,800.000 4,000.000 2,000.000 5,000.000 3,200.000 |
5406002 | MTL W-BEAM GD FEN (STEEL POST) | LF | 250.000 | 25.00 | 1 2 3 4 5 6 7 | 26.000 27.500 39.000 38.000 25.000 28.000 32.000 |
5406006 | MTL BEAM GD FEN TRANS (THRIE-BEAM) | EA | 4.000 | 1,500.00 | 1 2 3 4 5 6 7 | 2,125.000 2,090.000 2,188.000 1,200.000 2,000.000 2,500.000 1,800.000 |
5426001 | REMOVE METAL BEAM GUARD FENCE | LF | 370.000 | 3.00 | 1 2 3 4 5 6 7 | 3.000 7.000 11.000 5.000 4.000 5.000 12.000 |
5426002 | REMOVE TERMINAL ANCHOR SECTION | EA | 4.000 | 500.00 | 1 2 3 4 5 6 7 | 250.000 200.000 355.000 400.000 300.000 500.000 750.000 |
5446001 | GUARDRAIL END TREATMENT (INSTALL) | EA | 4.000 | 3,200.00 | 1 2 3 4 5 6 7 | 2,600.000 2,365.000 3,313.000 2,300.000 2,400.000 2,500.000 2,900.000 |
6586014 | INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI) | EA | 2.000 | 15.00 | 1 2 3 4 5 6 7 | 20.000 30.000 33.000 25.000 35.000 100.000 80.000 |
6586062 | INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) | EA | 6.000 | 40.00 | 1 2 3 4 5 6 7 | 25.000 30.000 33.000 60.000 35.000 100.000 120.000 |