TABULATION OF BIDS HWY JOB CTY DIV TEXAS DEPARTMENT OF TRANSPORTATION, AUSTIN US 67 3002 192 48 COUNTY REAGAN CONTROL 0076-08-027 PROJECT STP 2020(652) LENGTH 18.516 TYPE ADD PASSING LANES DATE 03/04/20 CONTRACT NUMBER 03203002 TIME 469 WORKING DAYS CHECK $100,000 LIMITS FROM:SH 137 TO:UPTON COUNTY LINE MISCELLANEOUS COST $25,494,788.80 *****ESTIMATE***** BIDDER 1 $23,698,271.40 REECE ALBERT, INC. BIDDER 2 $29,637,787.55 KIEWIT INFRASTRUCTURE SOUTH CO. BIDDER 3 $30,372,287.94 RK HALL, LLC A L ITEM CODE UNIT T ITM DES SP ITEM DESCRIPTION UNIT QUANTITY ENG EST BIDDER 1 BIDDER 2 BIDDER 3 1006002 PREPARING ROW STA 979.000 350.00 221.540 283.880 281.750 1006003 PREPARING ROW(TREE)(5" TO 12" DIA) EA 16.000 1,000.00 435.620 479.120 1,380.000 1046009 REMOVING CONC (RIPRAP) SY 208.000 22.00 10.890 13.000 139.190 1046017 REMOVING CONC (DRIVEWAYS) SY 549.000 20.00 21.470 194.180 79.220 1046054 REMOVING CONCRETE(MOW STRIP) LF 350.000 12.00 7.240 29.950 11.570 1056002 REMOVING STAB BASE AND ASPH PAV (2") SY 21,209.000 3.50 1.910 1.500 2.640 1056020 REMOVING STAB BASE & ASPH PAV (12") SY 77,329.000 7.00 1.730 2.770 12.080 1056035 REMOVING STAB BASE & ASPH PAV (0-2") SY 489.000 3.00 11.570 11.930 33.240 1056041 REMOVING STAB BASE AND ASPH PAV(8") SY 3,451.000 6.00 5.750 7.950 25.670 1106001 EXCAVATION (ROADWAY) CY 20,594.000 10.00 15.880 14.810 6.580 1326003002 EMBANKMENT (FINAL)(ORD COMP)(TY B) CY 25,936.000 20.00 8.430 7.340 7.110 1346004 BACKFILL (TY A OR B) STA 945.000 150.00 139.510 116.390 304.820 1646035 DRILL SEEDING (PERM) (RURAL) (CLAY) SY 153,623.000 0.20 0.150 0.170 0.150 1646041 DRILL SEEDING (TEMP) (WARM) SY 76,811.000 0.20 0.130 0.140 0.150 1646043 DRILL SEEDING (TEMP) (COOL) SY 76,811.000 0.20 0.130 0.140 0.150 2476041003 FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS) CY 46,306.000 40.00 43.320 46.750 57.240 3106009 PRIME COAT (MC-30) GAL 35,275.000 5.00 4.130 5.490 4.970 3156004001 FOG SEAL (CSS-1H) GAL 5,627.000 3.50 5.130 3.850 5.580 3166126002 AGGR(TY-PB GR-4 SAC-A) CY 6,387.000 115.00 120.520 141.460 138.100 3166405002 ASPH (AC-20-5TR OR AC-20XP) GAL 256,743.000 4.00 3.370 5.240 4.030 3516002 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6") SY 11,040.000 55.00 44.860 112.470 60.100 3546021 PLANE ASPH CONC PAV(0" TO 2") SY 489.000 2.00 7.940 2.780 29.650 3546041 PLANE ASPH CONC PAV (1.5") SY 1,055.000 2.00 4.470 2.910 10.060 3546045 PLANE ASPH CONC PAV (2") SY 21,698.000 2.25 2.000 1.750 1.910 3546051 PLANE ASPH CONC PAV (0" TO 1 1/2") SY 634.000 1.75 6.520 2.720 20.950 4006005 CEM STABIL BKFL CY 77.000 200.00 217.810 260.030 230.000 4296009 CONC STR REPAIR (STANDARD) SF 3.000 300.00 54.450 65.010 57.500 4326029 RIPRAP (STONE COMMON)(GROUT)(8 IN) CY 33.000 255.00 190.590 227.540 201.250 4326045 RIPRAP (MOW STRIP)(4 IN) CY 36.000 600.00 707.890 868.410 747.500 4626046002 CONC BOX CULV (3 FT X 3 FT)(EXTEND) LF 130.000 650.00 735.110 877.620 776.250 4626048002 CONC BOX CULV (4 FT X 3 FT)(EXTEND) LF 6.000 800.00 762.340 910.130 805.000 4626049002 CONC BOX CULV (4 FT X 4 FT)(EXTEND) LF 51.000 850.00 789.570 942.640 833.750 4626053002 CONC BOX CULV (5 FT X 5 FT)(EXTEND) LF 88.000 950.00 871.250 1,040.160 920.000 4626055002 CONC BOX CULV (6 FT X 4 FT)(EXTEND) LF 67.000 900.00 898.470 1,072.650 948.750 4646005001 RC PIPE (CL III)(24 IN) LF 96.000 140.00 108.910 130.020 115.000 4666097 HEADWALL (CH - PW - 0) (DIA= 24 IN) EA 1.000 8,500.00 6,534.340 7,801.140 6,900.000 4666180 WINGWALL (PW - 1) (HW=5 FT) EA 1.000 22,000.00 19,603.030 23,403.430 20,700.000 4676112 SET (TY I)(S=3 FT)(HW= 4 FT)(4:1)(C) EA 18.000 7,000.00 6,534.340 7,801.140 6,900.000 4676144 SET (TY I)(S= 4 FT)(HW= 4 FT)(4:1) (C) EA 1.000 8,000.00 8,167.930 9,751.430 8,625.000 4676150 SET (TY I)(S= 4 FT)(HW= 5 FT)(4:1) (C) EA 1.000 8,500.00 8,712.450 10,401.520 9,200.000 4676186 SET (TY I)(S= 5 FT)(HW= 6 FT)(4:1) (C) EA 11.000 9,000.00 10,346.040 12,351.810 10,925.000 4676219 SET (TY I)(S= 6 FT)(HW= 5 FT)(4:1) (C) EA 17.000 10,000.00 8,712.460 10,401.520 9,200.000 4676249 SET (TY I)(S= 7 FT)(HW= 5 FT)(4:1) (C) EA 3.000 11,000.00 13,068.690 15,602.290 13,800.000 4676390 SET (TY II) (24 IN) (RCP) (4: 1) (C) EA 16.000 1,500.00 2,178.110 2,600.380 2,300.000 4806001 CLEAN EXIST CULVERTS EA 34.000 2,000.00 2,178.110 2,600.380 4,966.760 5006001 MOBILIZATION LS 1.000 2,110,000.00 1,107,558.900 2,791,380.480 1,239,942.550 5026001007 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 27.000 10,000.00 11,808.150 25,000.000 21,958.340 5066004004 ROCK FILTER DAMS (INSTALL) (TY 4) LF 3,060.000 40.00 42.700 46.970 67.060 5066011004 ROCK FILTER DAMS (REMOVE) LF 3,060.000 10.00 12.890 14.180 21.040 5066020004 CONSTRUCTION EXITS (INSTALL) (TY 1) SY 1,638.000 30.00 36.270 39.890 27.390 5066024004 CONSTRUCTION EXITS (REMOVE) SY 1,638.000 10.00 11.340 12.470 21.040 5066035004 SANDBAGS FOR EROSION CONTROL EA 12.000 10.00 35.230 38.750 28.750 5066038004 TEMP SEDMT CONT FENCE (INSTALL) LF 44,620.000 5.00 2.230 2.460 2.360 5066039004 TEMP SEDMT CONT FENCE (REMOVE) LF 44,620.000 1.00 0.460 0.500 0.480 5066040004 BIODEG EROSN CONT LOGS (INSTL) (8") LF 720.000 5.00 5.430 5.980 8.140 5066043004 BIODEG EROSN CONT LOGS (REMOVE) LF 720.000 1.50 2.070 2.280 2.030 5086001 CONSTRUCTING DETOURS SY 4,171.000 80.00 61.040 64.430 73.530 5306004 DRIVEWAYS (CONC) SY 549.000 100.00 130.690 156.030 211.660 5306006 DRIVEWAYS (SURF TREAT) SY 1,371.000 45.00 35.700 25.370 86.930 5336003 RUMBLE STRIPS (SHOULDER) ASPHALT LF 186,032.000 0.15 0.160 0.120 0.170 5336004 RUMBLE STRIPS (CENTERLINE) ASPHALT LF 95,295.000 0.20 0.240 0.130 0.250 5406002001 MTL W-BEAM GD FEN (STEEL POST) LF 475.000 25.00 38.120 34.140 32.780 5406016001 DOWNSTREAM ANCHOR TERMINAL SECTION EA 1.000 1,050.00 3,267.180 1,617.050 1,552.500 5406020001 MTL W - BEAM GD FEN (LOW FILL CULVERT) LF 50.000 80.00 108.910 65.880 63.250 5426001 REMOVE METAL BEAM GUARD FENCE LF 250.000 4.00 10.890 4.790 4.600 5446001 GUARDRAIL END TREATMENT (INSTALL) EA 3.000 2,800.00 4,900.760 3,892.890 3,737.500 5446003 GUARDRAIL END TREATMENT (REMOVE) EA 2.000 325.00 544.530 479.120 460.000 6446001 IN SM RD SN SUP&AM TY10BWG(1)SA(P) EA 77.000 675.00 956.190 1,000.170 960.250 6446004 IN SM RD SN SUP&AM TY10BWG(1)SA(T) EA 27.000 800.00 1,201.230 1,161.880 1,115.500 6446007 IN SM RD SN SUP&AM TY10BWG(1)SA(U) EA 13.000 850.00 1,261.130 1,251.710 1,201.750 6446027 IN SM RD SN SUP&AM TYS80(1)SA(P) EA 1.000 800.00 1,102.130 1,096.000 1,052.250 6446033 IN SM RD SN SUP&AM TYS80(1)SA(U) EA 13.000 1,050.00 1,461.510 1,383.470 1,328.250 6446036 IN SM RD SN SUP&AM TYS80(1)SA(U-BM) EA 9.000 1,150.00 1,599.820 1,479.300 1,420.250 6446076 REMOVE SM RD SN SUP&AM EA 86.000 150.00 98.050 119.780 144.040 6626001 WK ZN PAV MRK NON-REMOV (W)4"(BRK) LF 2,670.000 0.30 0.140 0.160 0.400 6626004 WK ZN PAV MRK NON-REMOV (W)4"(SLD) LF 402,957.000 0.30 0.140 0.160 0.320 6626016 WK ZN PAV MRK NON-REMOV (W)24"(SLD) LF 86.000 2.50 3.270 3.590 13.800 6626034 WK ZN PAV MRK NON-REMOV (Y)4"(SLD) LF 440,557.000 0.30 0.140 0.160 0.320 6626048 WK ZN PAV MRK REMOV (REFL) TY I-C EA 134.000 4.00 2.830 3.110 5.180 6626050 WK ZN PAV MRK REMOV (REFL) TY II-A-A EA 11,364.000 4.00 2.830 3.110 5.180 6626109 WK ZN PAV MRK SHT TERM (TAB)TY W EA 9,813.000 3.00 1.310 2.400 2.590 6626111 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 EA 46,634.000 3.00 1.330 2.400 2.190 6666005007 REFL PAV MRK TY I (W)4"(DOT)(090MIL) LF 2,463.000 0.35 0.380 0.420 1.380 6666035007 REFL PAV MRK TY I (W)8"(SLD)(090MIL) LF 8,552.000 0.85 0.610 0.670 0.980 6666047007 REFL PAV MRK TY I (W)24"(SLD)(090MIL) LF 136.000 8.00 4.440 4.890 13.800 6666167007 REFL PAV MRK TY II (W) 4" (BRK) LF 30,040.000 0.15 0.120 0.130 0.240 6666168007 REFL PAV MRK TY II (W) 4" (DOT) LF 4,926.000 0.15 0.120 0.130 0.320 6666170007 REFL PAV MRK TY II (W) 4" (SLD) LF 393,410.000 0.15 0.120 0.130 0.180 6666178007 REFL PAV MRK TY II (W) 8" (SLD) LF 17,104.000 0.30 0.270 0.300 0.460 6666182007 REFL PAV MRK TY II (W) 24" (SLD) LF 272.000 2.50 3.270 3.590 4.600 6666207007 REFL PAV MRK TY II (Y) 4" (SLD) LF 733,216.000 0.15 0.120 0.130 0.180 6666299007 RE PM W/RET REQ TY I (W)4"(BRK)(090MIL) LF 15,020.000 0.35 0.380 0.420 0.520 6666302007 RE PM W/RET REQ TY I (W)4"(SLD)(090MIL) LF 196,705.000 0.35 0.380 0.420 0.520 6666314007 RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL) LF 366,608.000 0.35 0.380 0.420 0.520 6686077 PREFAB PAV MRK TY C (W) (ARROW) EA 19.000 250.00 299.490 329.400 287.500 6686083 PREFAB PAV MRK TY C (W) (LNDP ARROW) EA 16.000 550.00 707.890 778.580 448.500 6686085 PREFAB PAV MRK TY C (W) (WORD) EA 19.000 300.00 353.940 389.290 322.000 6686092 PREFAB PAV MRK TY C (W) (36")(YLD TRI) EA 24.000 35.00 43.560 47.910 51.750 6726007 REFL PAV MRKR TY I-C EA 1,210.000 4.00 3.270 3.590 3.740 6726009 REFL PAV MRKR TY II-A-A EA 6,185.000 4.00 3.270 3.590 3.450 6726010 REFL PAV MRKR TY II-C-R EA 78.000 4.00 3.270 3.590 2.300 6776001 ELIM EXT PAV MRK & MRKS (4") LF 267,515.000 0.60 0.820 0.900 0.630 7306107003 FULL - WIDTH MOWING CYC 4.000 10,000.00 11,761.820 29,346.380 12,420.000 7346002 LITTER REMOVAL CYC 4.000 5,000.00 11,730.570 18,213.720 10,016.750 30776022 SP MIXES SP-C SAC-A PG70-22 TON 130,557.000 100.00 103.520 114.900 127.720 30776075 TACK COAT GAL 69,337.000 4.00 2.200 3.530 4.570 60016001 PORTABLE CHANGEABLE MESSAGE SIGN DAY 904.000 100.00 44.150 101.720 78.130 61856002002 TMA (STATIONARY) DAY 372.000 200.00 248.840 409.360 399.620 61856005002 TMA (MOBILE OPERATION) DAY 122.000 250.00 525.600 886.610 516.550