Tabulation of Bids for Project BR 2022(565)
This report will no longer be updated, please access links on the Contract Letting page.
The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.
Text version of this page | |||
County: | POLK | Let Date: | 05/03/24 |
Type: | BRIDGE REPLACEMENT | Seq No: | 3221 |
Time: | 405 WORKING DAYS | Project ID: | BR 2022(565) |
Highway: | CR | Contract #: | 05243221 |
Length: | 0.000 | CCSJ: | 0911-04-094 |
Limits: | |||
From: | CARMONA ROAD AT PINEY CREEK | Check: | $72,000 |
To: | AT PINEY CREEK. | Misc Cost: |
Estimate | $3,615,026.50 | % Over/Under | Company |
Bidder 1 | $3,547,062.80 | -1.88% | DCC CONSTRUCTION AND SERVICES, L.L.C. |
Bidder 2 | $4,101,749.32 | +13.46% | LONGVIEW BRIDGE AND ROAD, LTD. |
Bidder 3 | $4,170,340.62 | +15.36% | C. E. BARKER, LTD. |
Bidder 4 | $6,800,088.96 | +88.11% | JAMES CONSTRUCTION GROUP, LLC |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
1006002 | PREPARING ROW | STA | 23.500 | 3,000.00 | 1 2 3 4 | 500.000 8,000.000 17,000.000 28,500.000 |
1056074 | REMOVING STAB BASE AND ASPH PAV (4") | SY | 235.000 | 10.00 | 1 2 3 4 | 2.000 8.500 3.750 10.740 |
1106001 | EXCAVATION (ROADWAY) | CY | 3,113.000 | 25.00 | 1 2 3 4 | 30.000 25.000 43.550 18.870 |
1326003 | EMBANKMENT (FINAL)(ORD COMP)(TY B) | CY | 2,154.000 | 25.00 | 1 2 3 4 | 30.000 35.000 46.580 39.030 |
1606003 | FURNISHING AND PLACING TOPSOIL (4") | SY | 10,764.000 | 3.00 | 1 2 3 4 | 2.000 2.400 3.220 2.630 |
1646054 | BOND FBR MTRX SEED (PERM)(RURAL)(SAND) | SY | 10,764.000 | 2.00 | 1 2 3 4 | 1.000 1.050 2.140 0.980 |
1646055 | BONDED FBR MTRX SEED (TEMP)(WARM) | SY | 5,383.000 | 2.00 | 1 2 3 4 | 1.000 1.050 1.080 0.960 |
1646056 | BONDED FBR MTRX SEED (TEMP)(COOL) | SY | 5,383.000 | 2.00 | 1 2 3 4 | 1.000 1.050 1.080 0.960 |
1686001 | VEGETATIVE WATERING | MG | 430.800 | 25.00 | 1 2 3 4 | 1.000 20.000 74.960 100.000 |
2476467005 | FL BS (CMP IN PLC)(TY D GR 1-2 OR 5)6" | SY | 4,894.000 | 20.00 | 1 2 3 4 | 75.000 40.700 62.910 32.720 |
4006005 | CEM STABIL BKFL | CY | 338.800 | 250.00 | 1 2 3 4 | 80.000 355.000 235.580 190.580 |
4166001 | DRILL SHAFT (18 IN) | LF | 272.000 | 90.00 | 1 2 3 4 | 240.000 250.000 248.660 138.940 |
4166002 | DRILL SHAFT (24 IN) | LF | 996.000 | 275.00 | 1 2 3 4 | 275.000 350.000 277.350 117.890 |
4166004 | DRILL SHAFT (36 IN) | LF | 1,016.000 | 360.00 | 1 2 3 4 | 350.000 450.000 337.490 323.050 |
4206013001 | CL C CONC (ABUT) | CY | 127.900 | 2,000.00 | 1 2 3 4 | 1,500.000 1,540.000 1,329.960 2,500.000 |
4206029001 | CL C CONC (CAP) | CY | 63.700 | 2,200.00 | 1 2 3 4 | 2,500.000 1,540.000 1,858.600 3,000.000 |
4206037001 | CL C CONC (COLUMN) | CY | 21.400 | 2,700.00 | 1 2 3 4 | 2,500.000 1,540.000 1,816.120 4,000.000 |
4226001 | REINF CONC SLAB | SF | 6,630.000 | 40.00 | 1 2 3 4 | 29.000 30.000 23.720 205.150 |
4226007 | REINF CONC SLAB (SLAB BEAM) | SF | 5,850.000 | 40.00 | 1 2 3 4 | 29.000 23.250 23.720 200.000 |
4256012001 | PRESTR CONC SLAB BEAM (5SB15) | LF | 1,109.600 | 350.00 | 1 2 3 4 | 245.000 370.000 317.440 239.230 |
4256035001 | PRESTR CONC GIRDER (TX28) | LF | 1,011.200 | 300.00 | 1 2 3 4 | 255.000 290.000 327.420 274.000 |
4326033 | RIPRAP (STONE PROTECTION)(18 IN) | CY | 740.700 | 250.00 | 1 2 3 4 | 175.000 300.000 277.070 195.400 |
4506019001 | RAIL (TY T631LS) | LF | 1,132.000 | 85.00 | 1 2 3 4 | 100.000 70.000 32.120 78.500 |
4546021 | TYPE A JOINT | LF | 420.000 | 115.00 | 1 2 3 4 | 50.000 78.000 37.480 109.870 |
4966009 | REMOV STR (BRIDGE 0 - 99 FT LENGTH) | EA | 4.000 | 25,000.00 | 1 2 3 4 | 50,000.000 33,000.000 32,124.750 100,000.000 |
4966016 | REMOV STR (PIPE) | EA | 1.000 | 5,000.00 | 1 2 3 4 | 200.000 1,000.000 1,499.160 3,378.400 |
5006001 | MOBILIZATION | LS | 1.000 | 171,000.00 | 1 2 3 4 | 300,000.000 400,000.000 400,000.000 660,000.000 |
5026001008 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 36.000 | 2,500.00 | 1 2 3 4 | 1,000.000 3,000.000 3,212.480 1,322.350 |
5066002005 | ROCK FILTER DAMS (INSTALL) (TY 2) | LF | 280.000 | 50.00 | 1 2 3 4 | 20.000 50.000 37.480 42.000 |
5066011005 | ROCK FILTER DAMS (REMOVE) | LF | 280.000 | 10.00 | 1 2 3 4 | 1.000 11.000 13.390 12.000 |
5066034005 | CONSTRUCTION PERIMETER FENCE | LF | 419.000 | 5.00 | 1 2 3 4 | 20.000 5.500 4.690 10.000 |
5066038005 | TEMP SEDMT CONT FENCE (INSTALL) | LF | 2,757.000 | 5.00 | 1 2 3 4 | 15.000 3.300 4.280 4.250 |
5066039005 | TEMP SEDMT CONT FENCE (REMOVE) | LF | 2,757.000 | 1.00 | 1 2 3 4 | 1.000 1.100 1.080 0.650 |
5406001001 | MTL W-BEAM GD FEN (TIM POST) | LF | 930.500 | 35.00 | 1 2 3 4 | 35.000 30.250 32.120 24.500 |
5406016001 | DOWNSTREAM ANCHOR TERMINAL SECTION | EA | 8.000 | 1,700.00 | 1 2 3 4 | 1,550.000 1,540.000 1,284.990 1,550.000 |
5446001 | GUARDRAIL END TREATMENT (INSTALL) | EA | 8.000 | 3,500.00 | 1 2 3 4 | 3,500.000 3,135.000 3,212.480 3,100.000 |
5526003 | WIRE FENCE (TY C) | LF | 642.000 | 20.00 | 1 2 3 4 | 15.000 34.000 21.420 20.000 |
5526008 | WIRE FENCE (WATER GAP) | LF | 229.000 | 50.00 | 1 2 3 4 | 20.000 190.000 149.920 65.000 |
5606003 | MAILBOX INSTALL-M (TWG-POST) TY 1 | EA | 1.000 | 750.00 | 1 2 3 4 | 250.000 687.500 535.410 750.000 |
6446076 | REMOVE SM RD SN SUP&AM | EA | 16.000 | 100.00 | 1 2 3 4 | 50.000 137.500 128.500 162.000 |
6586016 | INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BI) | EA | 24.000 | 35.00 | 1 2 3 4 | 50.000 27.500 21.420 25.000 |
6586062 | INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) | EA | 8.000 | 30.00 | 1 2 3 4 | 45.000 41.250 32.120 35.000 |