Tabulation of Bids for Project C 918-22-157
Text version of this page | |||
County: | ELLIS | Let Date: | 06/06/18 |
Type: | REPLACE TURNDOWNS AND GUARDRAIL | Seq No: | 3222 |
Time: | 246 WORKING DAYS | Project ID: | C 918-22-157 |
Highway: | VA | Contract #: | 06183222 |
Length: | 8.379 | CCSJ: | 0918-22-157 |
Limits: | |||
From: | Check: | $94,000 | |
To: | Misc Cost: | $115,574.00 |
Estimate | $4,614,168.52 | % Over/Under | Company |
Bidder 1 | $4,527,134.12 | -1.89% | DBI SERVICES, LLC |
Bidder 2 | $4,569,489.00 | -0.97% | IIPL USA LLC |
Bidder 3 | $5,637,755.50 | +22.18% | FNH CONSTRUCTION, LLC |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
1006002 | PREPARING ROW | STA | 492.080 | 800.00 | 1 2 3 | 689.000 500.000 1,100.000 |
1046009 | REMOVING CONC (RIPRAP) | SY | 4.000 | 30.00 | 1 2 3 | 59.000 250.000 1,000.000 |
1326005 | EMBANKMENT (FINAL)(ORD COMP)(TY C) | CY | 20,626.000 | 35.00 | 1 2 3 | 28.000 38.000 25.000 |
1626002 | BLOCK SODDING | SY | 5,494.000 | 3.25 | 1 2 3 | 11.000 5.000 5.500 |
1646023 | CELL FBR MLCH SEED(PERM)(RURAL)(CLAY) | SY | 54,938.000 | 0.32 | 1 2 3 | 1.000 0.500 0.500 |
1646029 | CELL FBR MLCH SEED(TEMP)(WARM) | SY | 27,469.000 | 0.34 | 1 2 3 | 1.000 1.000 0.500 |
1646031 | CELL FBR MLCH SEED(TEMP)(COOL) | SY | 27,469.000 | 0.34 | 1 2 3 | 1.000 1.000 0.500 |
1686001 | VEGETATIVE WATERING | MG | 7,492.000 | 18.00 | 1 2 3 | 11.000 28.000 38.000 |
4326045 | RIPRAP (MOW STRIP)(4 IN) | CY | 2,136.000 | 439.92 | 1 2 3 | 401.000 400.000 550.000 |
5006001 | MOBILIZATION | LS | 1.000 | 384,015.32 | 1 2 3 | 183,063.000 400,000.000 560,000.000 |
5026001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 13.000 | 30,000.00 | 1 2 3 | 6,973.000 5,000.000 12,500.000 |
5066020003 | CONSTRUCTION EXITS (INSTALL) (TY 1) | SY | 200.000 | 22.52 | 1 2 3 | 48.000 20.000 30.000 |
5066024003 | CONSTRUCTION EXITS (REMOVE) | SY | 200.000 | 7.66 | 1 2 3 | 12.000 10.000 15.000 |
5066038003 | TEMP SEDMT CONT FENCE (INSTALL) | LF | 4,950.000 | 1.45 | 1 2 3 | 7.000 4.000 4.000 |
5066039003 | TEMP SEDMT CONT FENCE (REMOVE) | LF | 4,950.000 | 0.35 | 1 2 3 | 3.000 2.000 2.000 |
5406001 | MTL W-BEAM GD FEN (TIM POST) | LF | 32,325.000 | 17.50 | 1 2 3 | 20.000 20.000 20.500 |
5406006 | MTL BEAM GD FEN TRANS (THRIE-BEAM) | EA | 80.000 | 1,000.00 | 1 2 3 | 2,075.000 1,500.000 1,850.000 |
5406008 | MTL BEAM GD FEN TRANS (T101) | EA | 52.000 | 950.00 | 1 2 3 | 2,241.000 1,000.000 1,850.000 |
5406014 | SHORT RADIUS | LF | 773.000 | 27.50 | 1 2 3 | 35.000 25.000 35.000 |
5406015 | DRIVEWAY TERMINAL ANCHOR SECTION | EA | 4.000 | 875.00 | 1 2 3 | 912.000 1,000.000 1,850.000 |
5406016 | DOWNSTREAM ANCHOR TERMINAL SECTION | EA | 61.000 | 850.00 | 1 2 3 | 1,621.000 1,000.000 1,850.000 |
5406017 | MTL BM GD FEN (LONG SPAN SYSTEM) | LF | 100.000 | 30.00 | 1 2 3 | 26.000 20.000 35.000 |
5426001 | REMOVE METAL BEAM GUARD FENCE | LF | 38,683.000 | 2.00 | 1 2 3 | 5.000 1.000 3.000 |
5426002 | REMOVE TERMINAL ANCHOR SECTION | EA | 322.000 | 150.00 | 1 2 3 | 254.000 300.000 500.000 |
5426004 | RM MTL BM GD FENCE TRANS (THRIE-BEAM) | EA | 132.000 | 200.00 | 1 2 3 | 254.000 300.000 500.000 |
5446001 | GUARDRAIL END TREATMENT (INSTALL) | EA | 256.000 | 2,100.00 | 1 2 3 | 2,374.000 2,500.000 2,550.000 |
5456013 | CRASH CUSH ATTEN (INSTL)(R)(N)(TL3) | EA | 5.000 | 9,500.00 | 1 2 3 | 16,114.000 14,000.000 15,000.000 |
6586016 | INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BI) | EA | 625.000 | 19.00 | 1 2 3 | 17.000 20.000 50.000 |
6586062 | INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) | EA | 625.000 | 32.38 | 1 2 3 | 17.000 20.000 50.000 |
61856002 | TMA (STATIONARY) | DAY | 246.000 | 150.00 | 1 2 3 | 351.000 200.000 325.000 |