Tabulation of Bids for Project NH 2018(960)
Text version of this page | |||
County: | HARRIS | Let Date: | 06/06/18 |
Type: | LANDSCAPE ENHNACEMENTS | Seq No: | 3238 |
Time: | 30 WORKING DAYS | Project ID: | NH 2018(960) |
Highway: | IH 10 | Contract #: | 06183238 |
Length: | 17.627 | CCSJ: | 0271-07-318 |
Limits: | |||
From: | SH 6 | Check: | $11,000 |
To: | HOGAN STREET | Misc Cost: | $5,000.00 |
Estimate | $531,492.75 | % Over/Under | Company |
Bidder 1 | $496,320.36 | -6.62% | BOYER, INC. |
Bidder 2 | $648,591.00 | +22.03% | APEX LANDSCAPE & IRRIGATION, LLC |
Bidder 3 | $679,174.44 | +27.79% | YELLOWSTONE LANDSCAPE - CENTRAL, INC. |
Bidder 4 | $794,927.00 | +49.56% | CENTRAL NORTH CONSTRUCTION, LLC |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
1006009 | PREPARING ROW (TREE) (6" TO 24" DIA) | EA | 1.000 | 750.00 | 1 2 3 4 | 777.000 2,500.000 2,500.000 28,000.000 |
1006013 | PREP ROW (TREE) (2" TO 12" DIA) | EA | 30.000 | 200.00 | 1 2 3 4 | 60.000 350.000 361.111 1,200.000 |
1616009 | EROSION CONTROL COMPOST | CY | 313.000 | 28.00 | 1 2 3 4 | 18.000 30.000 38.492 50.000 |
1616012 | GENERAL USE COMPOST | CY | 16.000 | 30.00 | 1 2 3 4 | 33.000 30.000 275.977 100.000 |
1926003001 | PLANT MATERIAL (3-GAL) | EA | 324.000 | 15.00 | 1 2 3 4 | 10.250 30.000 18.004 19.000 |
1926030001 | PLANT MATERIAL (3 GAL) (SHRUB) | EA | 930.000 | 15.00 | 1 2 3 4 | 10.700 30.000 24.194 22.000 |
1926065001 | PLANT BED PREP (TYPE III) | SY | 292.000 | 1.00 | 1 2 3 4 | 1.250 5.000 0.656 10.000 |
1926066001 | PLANT BED PREP (TYPE IV) | SY | 165.000 | 0.25 | 1 2 3 4 | 1.350 5.000 0.211 25.000 |
1936002 | PLANT MAINTENANCE | CYC | 9.000 | 25,000.00 | 1 2 3 4 | 24,767.000 25,000.000 28,600.000 25,000.000 |
5006001 | MOBILIZATION | LS | 1.000 | 35,200.00 | 1 2 3 4 | 49,182.000 70,000.000 46,666.667 275,000.000 |
5026001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 2.000 | 1,500.00 | 1 2 3 4 | 512.000 10,000.000 2,916.667 4,000.000 |
5066038003 | TEMP SEDMT CONT FENCE (INSTALL) | LF | 200.000 | 3.50 | 1 2 3 4 | 3.000 1.000 0.567 18.000 |
5066039003 | TEMP SEDMT CONT FENCE (REMOVE) | LF | 200.000 | 3.50 | 1 2 3 4 | 1.300 1.000 1.134 2.000 |
7516010 | PLANT BED MAINTENANCE | CYC | 1.000 | 95,000.00 | 1 2 3 4 | 28,075.000 65,000.000 7,086.667 35,000.000 |
7516011 | PRUNING | CYC | 1.010 | 105,000.00 | 1 2 3 4 | 72,836.000 55,000.000 143,970.308 65,000.000 |
10006002 | SHRUB PLANTING AND REMOVAL | EA | 428.000 | 8.00 | 1 2 3 4 | 80.200 65.000 28.042 48.000 |
10006006 | PRUNING AND TRIMMING TREES AND SHRUBS | CYC | 1.000 | 24,000.00 | 1 2 3 4 | 62,127.000 115,000.000 143,970.308 25,000.000 |
10066001 | LANDSCAPE SOIL AMENDMENT (TYPE I) | SY | 457.000 | 0.25 | 1 2 3 4 | 0.550 2.000 0.274 8.000 |
10066002 | LANDSCAPE SOIL AMENDMENT (TYPE II) | SY | 457.000 | 0.25 | 1 2 3 4 | 0.550 4.000 0.802 8.000 |
10066005 | LANDSCAPE SOIL AMENDMENT (TYPE V) | SY | 951.000 | 3.00 | 1 2 3 4 | 0.450 4.000 0.876 10.000 |
61856002 | TMA (STATIONARY) | DAY | 1.000 | 200.00 | 1 2 3 4 | 730.000 500.000 783.500 5,000.000 |