Tabulation of Bids for Project C 924-6-663
Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months.
The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.
Text version of this page | |||
County: | EL PASO | Let Date: | 06/30/22 |
Type: | LANDSCAPE DEVELOPMENT | Seq No: | 3636 |
Time: | 80 WORKING DAYS | Project ID: | C 924-6-663 |
Highway: | VA | Contract #: | 06223636 |
Length: | 7.880 | CCSJ: | 0924-06-663 |
Limits: | |||
From: | EL PASO COUNTYWIDE | Check: | $17,000 |
To: | . | Misc Cost: |
Estimate | $849,609.70 | % Over/Under | Company |
Bidder 1 | $995,591.48 | +17.18% | HORIZONE CONSTRUCTION I, LTD |
Bidder 2 | $1,076,406.50 | +26.69% | DOUBLE H CONTRACTING INC. |
Bidder 3 | $1,080,911.15 | +27.22% | ALLIED PAVING CO. |
Bidder 4 | $1,648,742.88 | +94.06% | MARTINEZ BROS. CONTRACTORS, LLC |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
1006001 | PREPARING ROW | AC | 1.040 | 6,800.00 | 1 2 3 4 | 68,644.860 10,000.000 155,540.000 19,000.000 |
1046011 | REMOVING CONC (MEDIANS) | SY | 2,543.000 | 20.00 | 1 2 3 4 | 13.100 20.000 16.680 28.000 |
1106003 | EXCAVATION (SPECIAL) | CY | 1,280.000 | 50.00 | 1 2 3 4 | 28.660 65.000 18.460 28.000 |
1346005 | BACKFILL TY A | CY | 1,129.000 | 70.00 | 1 2 3 4 | 26.940 65.000 16.640 35.000 |
1616011 | GENERAL USE COMPOST (1") | SY | 18,275.000 | 4.00 | 1 2 3 4 | 2.010 3.000 1.970 4.000 |
1686001 | VEGETATIVE WATERING | MG | 4.000 | 50.00 | 1 2 3 4 | 267.500 1,000.000 262.500 185.420 |
1706001 | IRRIGATION SYSTEM | LS | 1.000 | 75,000.00 | 1 2 3 4 | 383,155.470 135,000.000 364,443.680 817,360.000 |
1926004 | PLANT MATERIAL (5-GAL) | EA | 1,476.000 | 39.00 | 1 2 3 4 | 38.630 60.000 49.720 61.440 |
1926014 | PLANT SOIL MIX | CY | 371.000 | 65.00 | 1 2 3 4 | 64.690 50.000 63.480 61.930 |
1926016 | PLANT BED PREPARATION | SY | 18,275.000 | 2.10 | 1 2 3 4 | 2.000 3.500 1.960 3.270 |
1926017 | VEGETATION BARRIER | SY | 7,598.000 | 1.90 | 1 2 3 4 | 2.820 3.000 2.770 3.710 |
1926031 | PLANT MATERIAL (5 GAL) (SHRUB) | EA | 1,457.000 | 45.00 | 1 2 3 4 | 33.050 60.000 32.430 61.430 |
1936001 | PLANT MAINTENANCE | MO | 12.000 | 1,500.00 | 1 2 3 4 | 1,690.600 2,250.000 1,659.000 1,020.000 |
1936005 | PLANT REPLACEMENT (5-GAL) | EA | 440.000 | 45.00 | 1 2 3 4 | 44.940 60.000 38.850 61.430 |
1936006 | VEGETATIVE WATERING | MG | 12.000 | 100.00 | 1 2 3 4 | 267.500 2,500.000 262.500 185.420 |
1936007 | IRRIGATION SYSTEM OPER AND MAINT | MO | 12.000 | 700.00 | 1 2 3 4 | 470.800 2,250.000 462.000 780.000 |
5006001 | MOBILIZATION | LS | 1.000 | 75,000.00 | 1 2 3 4 | 28,997.810 98,000.000 23,000.000 45,000.000 |
5026001008 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 4.000 | 7,550.00 | 1 2 3 4 | 6,339.540 10,000.000 8,000.000 8,125.000 |
5066040005 | BIODEG EROSN CONT LOGS (INSTL) (8") | LF | 220.000 | 5.00 | 1 2 3 4 | 6.690 10.000 5.000 12.000 |
5066043005 | BIODEG EROSN CONT LOGS (REMOVE) | LF | 220.000 | 2.00 | 1 2 3 4 | 2.610 10.000 2.000 5.000 |
10056001 | LOOSE AGGR FOR GROUNDCOVER (TYPE I) | CY | 865.000 | 110.00 | 1 2 3 4 | 75.920 90.000 90.630 119.630 |
10056002 | LOOSE AGGR FOR GROUNDCOVER (TYPE II) | CY | 320.000 | 90.00 | 1 2 3 4 | 76.650 90.000 89.490 101.360 |
60016001 | PORTABLE CHANGEABLE MESSAGE SIGN | DAY | 60.000 | 120.00 | 1 2 3 4 | 50.720 150.000 100.000 125.000 |
61856002002 | TMA (STATIONARY) | DAY | 60.000 | 250.00 | 1 2 3 4 | 285.280 250.000 275.000 410.000 |