Tabulation of Bids for Project RMC - 636300001
Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months.
The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.
Text version of this page | |||
County: | HOPKINS | Let Date: | 07/08/20 |
Type: | SITE SPECIFIC FULL DEPTH CONCRETE REPAIR | Seq No: | 4014 |
Time: | 75 W | Project ID: | RMC - 636300001 |
Highway: | IH0030 | Contract #: | 07204014 |
Length: | 0.001 | CCSJ: | 6363-00-001 |
Limits: | |||
From: | VARIOUS LOCATIONS IN | Check: | $32,000 |
To: | PARIS DISTRICT | Misc Cost: | $10,000.00 |
Estimate | $1,611,687.50 | % Over/Under | Company |
Bidder 1 | $1,413,270.10 | -12.31% | O. TREVINO CONSTRUCTION, LLC |
Bidder 2 | $1,487,711.00 | -7.69% | WINDING ROAD CONSTRUCTION, INC. |
Bidder 3 | $2,056,300.00 | +27.59% | FNH CONSTRUCTION, LLC |
Bidder 4 | $2,367,256.00 | +46.88% | SOUTHERN ROAD & BRIDGE, LLC |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
3616052 | FULL - DEPTH REPAIR CRCP (8"-14") | SY | 1,943.000 | 250.00 | 1 2 3 4 | 237.220 245.000 300.000 350.000 |
3616053 | FULL - DEPTH REPAIR CPCD (8"-14") | SY | 3,672.000 | 250.00 | 1 2 3 4 | 200.620 223.000 325.000 398.000 |
5006001 | MOBILIZATION | LS | 1.000 | 143,562.50 | 1 2 3 4 | 140,000.000 134,695.000 200,000.000 200,000.000 |
5026001007 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 5.000 | 5,000.00 | 1 2 3 4 | 9,135.000 7,500.000 8,500.000 5,000.000 |
60016001 | PORTABLE CHANGEABLE MESSAGE SIGN | DAY | 75.000 | 125.00 | 1 2 3 4 | 200.000 125.000 150.000 5.000 |
61856002002 | TMA (STATIONARY) | DAY | 75.000 | 400.00 | 1 2 3 4 | 200.000 150.000 350.000 5.000 |