Tabulation of Bids for Project STP 1802(324)
Text version of this page | |||
County: | CASS | Let Date: | 07/10/18 |
Type: | PAVEMENT MARKINGS | Seq No: | 3016 |
Time: | 40 WORKING DAYS | Project ID: | STP 1802(324) |
Highway: | VA | Contract #: | 07183016 |
Length: | 52.621 | CCSJ: | 0919-00-078 |
Limits: | |||
From: | VARIOUS LOCATIONS | Check: | $7,000 |
To: | VARIOUS LOCATIONS | Misc Cost: | $6,000.00 |
Estimate | $350,000.00 | % Over/Under | Company |
Bidder 1 | $378,300.30 | +8.09% | STRIPING TECHNOLOGY, L.P. |
Bidder 2 | $436,410.85 | +24.69% | STRIPE-A-ZONE, INC. |
Bidder 3 | $449,366.30 | +28.39% | TOTAL HIGHWAY MAINTENANCE, LLC |
Bidder 4 | $573,613.10 | +63.89% | TRP CONSTRUCTION GROUP, LLC |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
5006001 | MOBILIZATION | LS | 1.000 | 15,980.50 | 1 2 3 4 | 20,000.000 21,500.000 5,500.000 50,000.000 |
5026001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 3.000 | 500.00 | 1 2 3 4 | 3,000.000 97.000 100.000 2,500.000 |
6666036007 | REFL PAV MRK TY I (W)8"(SLD)(100MIL) | LF | 4,930.000 | 0.75 | 1 2 3 4 | 1.000 2.000 0.760 0.750 |
61496001 | REFL PAV MRK AWT (W) 4" (SLD) (100MIL) | LF | 471,290.000 | 0.30 | 1 2 3 4 | 0.320 0.390 0.440 0.500 |
61496002 | REFL PAV MRK AWT (W) 4" (BRK) (100MIL) | LF | 2,160.000 | 0.35 | 1 2 3 4 | 1.000 0.480 0.470 0.530 |
61496004 | REFL PAV MRK AWT (W) 6" (SLD) (100MIL) | LF | 77,940.000 | 0.42 | 1 2 3 4 | 0.470 0.540 0.630 0.700 |
61496005 | REFL PAV MRK AWT (W) 6" (BRK) (100MIL) | LF | 7,440.000 | 0.52 | 1 2 3 4 | 0.650 0.645 0.670 0.730 |
61496007 | REFL PAV MRK AWT (Y) 4" (SLD) (100MIL) | LF | 292,870.000 | 0.32 | 1 2 3 4 | 0.320 0.390 0.440 0.500 |
61496008 | REFL PAV MRK AWT (Y) 4" (BRK) (100MIL) | LF | 38,010.000 | 0.38 | 1 2 3 4 | 0.460 0.480 0.470 0.530 |
61496010 | REFL PAV MRK AWT (Y) 6" (SLD) (100MIL) | LF | 28,650.000 | 0.42 | 1 2 3 4 | 0.470 0.680 0.630 0.700 |
61496011 | REFL PAV MRK AWT (Y) 6" (BRK) (100MIL) | LF | 17,810.000 | 0.42 | 1 2 3 4 | 0.520 0.645 0.670 0.730 |
61856003 | TMA (MOBILE OPERATION) | HR | 640.000 | 35.00 | 1 2 3 4 | 25.000 15.000 1.000 25.000 |