The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.

Text version of this page
County:CULBERSONLet Date:08/02/23
Type:INFRASTRUCTURE IMPROVEMENTSSeq No:3044
Time:80 WORKING DAYSProject ID:F 2B23(126)
Highway:VAContract #:08233044
Length:7.000CCSJ:0924-08-007
Limits: 
From:CULBERSON COUNTYWIDE (ITS)Check:$13,000
To:.Misc Cost:
Estimate$657,328.47% Over/UnderCompany
Bidder 1$752,598.00+14.49%TRI STATE ELECTRIC, LTD.
Item CodeDescriptionUnitQuantityUnit Est.BidderUnit Bid
1006001PREPARING ROWAC0.30040,000.001
10,000.000
1106003EXCAVATION (SPECIAL)CY1.000150.001
1,800.000
4166005DRILL SHAFT (42 IN)LF63.000495.391
986.000
4166006DRILL SHAFT (48 IN)LF60.000540.001
1,036.000
4326001RIPRAP (CONC)(4 IN)CY7.500442.491
1,100.000
4326045RIPRAP (MOW STRIP)(4 IN)CY26.000486.911
750.000
5006001MOBILIZATIONLS1.00035,000.001
50,000.000
5026001008BARRICADES, SIGNS AND TRAFFIC HANDLINGMO4.00010,000.001
14,500.000
5406002001MTL W-BEAM GD FEN (STEEL POST)LF300.00038.811
95.000
5406016001DOWNSTREAM ANCHOR TERMINAL SECTIONEA2.0001,517.541
6,500.000
5446001GUARDRAIL END TREATMENT (INSTALL)EA2.0003,536.361
7,500.000
6186023CONDT (PVC) (SCH 40) (2")LF2,080.00028.981
32.000
6186024CONDT (PVC) (SCH 40) (2") (BORE)LF465.00036.351
38.000
6206016ELEC CONDR (NO.2) INSULATEDLF8,440.0004.861
3.500
6246002GROUND BOX TY A (122311)W/APRONEA9.0001,683.141
1,250.000
6506028INS OH SN SUP(30 FT BAL TEE)EA2.00053,379.131
53,000.000
60016001PORTABLE CHANGEABLE MESSAGE SIGNDAY10.000140.001
550.000
60106011CCTV FIELD EQUIP (DIGITAL) (INSTL ONLY)EA3.0003,124.041
2,250.000
60286001INSTALL DMS (POLE MTD CABINET)EA2.00035,588.241
4,000.000
60646046001ITS POLE (55 FT)(90 MPH)EA3.00026,173.381
26,000.000
60646084001ITS POLE MNT CAB (TY 2)(CONF 2)EA3.0008,334.621
8,500.000
61856002002TMA (STATIONARY)DAY80.000190.001
425.000
63776001001SYSTEM INTEGRATIONLS1.00010,000.001
30,000.000
63866001INSTALLATION OF CELLULAR MODEMEA5.0003,612.221
2,500.000