The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.
Text version of this page | |||
County: | COLLIN | Let Date: | 08/02/23 |
Type: | INTERSECTION IMPROVEMENT | Seq No: | 3069 |
Time: | 142 WORKING DAYS | Project ID: | F 2B23(265) |
Highway: | SH 78 | Contract #: | 08233069 |
Length: | 6.600 | CCSJ: | 0281-01-037 |
Limits: | |||
From: | BS 78F | Check: | $92,000 |
To: | US 380 IN COLLIN | Misc Cost: |
Estimate | $4,609,086.29 | % Over/Under | Company |
Bidder 1 | $3,966,360.02 | -13.94% | AUSTIN BRIDGE & ROAD SERVICES, LP |
Bidder 2 | $4,427,767.92 | -3.93% | FOUTSCO PAVING COMPANY, LLC |
Bidder 3 | $4,763,227.78 | +3.34% | PEACHTREE CONSTRUCTION, LTD. |
Bidder 4 | $4,935,962.50 | +7.09% | FNH CONSTRUCTION, LLC |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
1006002 | PREPARING ROW | STA | 84.710 | 1,000.00 | 1 2 3 4 | 4,682.280 25.000 2,500.000 5,500.000 |
1056019 | REMOVING STAB BASE & ASPH PAV(14") | SY | 19,217.000 | 11.00 | 1 2 3 4 | 17.000 25.000 17.250 20.000 |
1106001 | EXCAVATION (ROADWAY) | CY | 610.000 | 21.00 | 1 2 3 4 | 6.910 20.000 72.000 20.000 |
1326006 | EMBANKMENT (FINAL)(DENS CONT)(TY C) | CY | 363.000 | 21.00 | 1 2 3 4 | 24.850 20.000 9.000 50.000 |
1506001 | BLADING | STA | 84.710 | 200.00 | 1 2 3 4 | 1,450.420 10.000 750.000 250.000 |
1646035 | DRILL SEEDING (PERM) (RURAL) (CLAY) | SY | 61,539.000 | 0.20 | 1 2 3 4 | 0.220 0.200 0.300 0.500 |
1646051 | DRILL SEED (TEMP)(WARM OR COOL) | SY | 61,539.000 | 0.20 | 1 2 3 4 | 0.090 0.010 0.200 0.500 |
1686001 | VEGETATIVE WATERING | MG | 18,244.000 | 11.00 | 1 2 3 4 | 0.140 0.010 1.000 30.000 |
3546045 | PLANE ASPH CONC PAV (2") | SY | 1,858.000 | 4.00 | 1 2 3 4 | 20.250 40.000 36.000 20.000 |
4646003001 | RC PIPE (CL III)(18 IN) | LF | 30.000 | 85.00 | 1 2 3 4 | 100.000 100.000 126.000 150.000 |
4676363 | SET (TY II) (18 IN) (RCP) (6: 1) (P) | EA | 2.000 | 1,000.00 | 1 2 3 4 | 1,500.000 1,500.000 2,000.000 1,650.000 |
4966007 | REMOV STR (PIPE) | LF | 30.000 | 23.00 | 1 2 3 4 | 50.000 50.000 28.000 50.000 |
5006001 | MOBILIZATION | LS | 1.000 | 333,049.00 | 1 2 3 4 | 396,636.010 450,000.000 450,000.000 400,000.000 |
5026001008 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 9.000 | 18,000.00 | 1 2 3 4 | 10,000.000 30,000.000 35,000.000 8,500.000 |
5066020005 | CONSTRUCTION EXITS (INSTALL) (TY 1) | SY | 720.000 | 23.00 | 1 2 3 4 | 40.050 1.000 52.000 40.000 |
5066024005 | CONSTRUCTION EXITS (REMOVE) | SY | 720.000 | 8.00 | 1 2 3 4 | 11.000 1.000 15.000 20.000 |
5066038005 | TEMP SEDMT CONT FENCE (INSTALL) | LF | 15,336.000 | 3.60 | 1 2 3 4 | 3.650 1.000 4.000 4.000 |
5066039005 | TEMP SEDMT CONT FENCE (REMOVE) | LF | 15,336.000 | 0.75 | 1 2 3 4 | 0.690 1.000 1.000 2.000 |
5306005 | DRIVEWAYS (ACP) | SY | 129.000 | 75.00 | 1 2 3 4 | 264.790 200.000 155.000 45.000 |
5406001001 | MTL W-BEAM GD FEN (TIM POST) | LF | 12,137.500 | 25.00 | 1 2 3 4 | 19.500 20.000 22.500 25.000 |
5406008001 | MTL BEAM GD FEN TRANS (T101) | EA | 8.000 | 1,600.00 | 1 2 3 4 | 875.750 900.000 1,000.000 500.000 |
5426001 | REMOVE METAL BEAM GUARD FENCE | LF | 12,137.500 | 3.00 | 1 2 3 4 | 2.250 2.250 2.600 3.000 |
5446001 | GUARDRAIL END TREATMENT (INSTALL) | EA | 4.000 | 3,100.00 | 1 2 3 4 | 2,775.000 2,500.000 3,100.000 3,250.000 |
5446003 | GUARDRAIL END TREATMENT (REMOVE) | EA | 4.000 | 275.00 | 1 2 3 4 | 225.000 300.000 260.000 1,500.000 |
6586062 | INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) | EA | 160.000 | 27.00 | 1 2 3 4 | 25.500 26.000 29.000 100.000 |
6626111 | WK ZN PAV MRK SHT TERM (TAB)TY Y-2 | EA | 870.000 | 2.00 | 1 2 3 4 | 1.550 1.000 4.000 6.000 |
6666036007 | REFL PAV MRK TY I (W)8"(SLD)(100MIL) | LF | 6,160.000 | 1.10 | 1 2 3 4 | 0.880 1.000 1.850 3.000 |
6666048007 | REFL PAV MRK TY I (W)24"(SLD)(100MIL) | LF | 114.000 | 6.75 | 1 2 3 4 | 8.000 8.000 6.750 20.000 |
6666054007 | REFL PAV MRK TY I (W)(ARROW)(100MIL) | EA | 32.000 | 130.00 | 1 2 3 4 | 130.000 130.000 170.000 250.000 |
6666078007 | REFL PAV MRK TY I (W)(WORD)(100MIL) | EA | 32.000 | 150.00 | 1 2 3 4 | 130.000 130.000 188.000 250.000 |
6666225007 | PAVEMENT SEALER 6" | LF | 17,167.000 | 0.20 | 1 2 3 4 | 0.270 0.300 0.300 1.000 |
6666226007 | PAVEMENT SEALER 8" | LF | 2,833.000 | 0.35 | 1 2 3 4 | 0.350 0.300 0.350 1.000 |
6666231007 | PAVEMENT SEALER (ARROW) | EA | 14.000 | 40.00 | 1 2 3 4 | 20.000 20.000 20.000 250.000 |
6666232007 | PAVEMENT SEALER (WORD) | EA | 14.000 | 40.00 | 1 2 3 4 | 20.000 20.000 25.000 250.000 |
6666309007 | RE PM W/RET REQ TY I (W)6"(SLD)(100MIL) | LF | 13,811.000 | 0.68 | 1 2 3 4 | 0.820 1.000 0.880 1.000 |
6666321007 | RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL) | LF | 23,051.000 | 0.76 | 1 2 3 4 | 0.790 0.800 1.100 1.000 |
6726007 | REFL PAV MRKR TY I-C | EA | 328.000 | 4.80 | 1 2 3 4 | 3.880 4.000 4.750 6.000 |
6726009 | REFL PAV MRKR TY II-A-A | EA | 2,220.000 | 5.65 | 1 2 3 4 | 3.880 4.000 4.750 6.000 |
30776001 | SP MIXES SP-B PG64-22 | TON | 14,554.000 | 170.00 | 1 2 3 4 | 111.000 153.000 143.000 125.000 |
30776023 | SP MIXES SP-C SAC-B PG70-22 | TON | 2,353.000 | 180.00 | 1 2 3 4 | 150.000 173.000 199.000 135.000 |
30776075 | TACK COAT | GAL | 3,827.000 | 7.00 | 1 2 3 4 | 0.150 0.010 3.050 10.000 |
60016002 | PORTABLE CHANGEABLE MESSAGE SIGN | EA | 2.000 | 15,000.00 | 1 2 3 4 | 7,306.880 30,000.000 19,000.000 16,500.000 |
61856002002 | TMA (STATIONARY) | DAY | 173.000 | 180.00 | 1 2 3 4 | 410.210 1.000 280.000 250.000 |
61856003002 | TMA (MOBILE OPERATION) | HR | 153.000 | 150.00 | 1 2 3 4 | 83.570 1.000 85.000 65.000 |