Tabulation of Bids for Project STP 2B20(072)HES
Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months.
The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.
Text version of this page | |||
County: | COOKE | Let Date: | 08/05/20 |
Type: | INSTALL SAFETY LIGHTING | Seq No: | 3055 |
Time: | 37 WORKING DAYS | Project ID: | STP 2B20(072)HES |
Highway: | US 82 | Contract #: | 08203055 |
Length: | 0.000 | CCSJ: | 0044-08-072 |
Limits: | |||
From: | 0.121 MI W OF FM 1199 | Check: | $6,000 |
To: | 0.121 MI E OF FM 1199 | Misc Cost: |
Estimate | $295,963.00 | % Over/Under | Company |
Bidder 1 | $281,867.55 | -4.76% | MICA CORPORATION |
Bidder 2 | $287,677.10 | -2.80% | HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. |
Bidder 3 | $301,551.01 | +1.89% | AMERICAN LIGHTING AND SIGNALIZATION, LLC |
Bidder 4 | $472,161.75 | +59.53% | BT CONSTRUCTORS, LLC |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
4166029 | DRILL SHAFT (RDWY ILL POLE) (30 IN) | LF | 180.000 | 230.00 | 1 2 3 4 | 164.000 233.500 292.250 207.000 |
4326006 | RIPRAP (CONC)(CL B) | CY | 6.300 | 850.00 | 1 2 3 4 | 1,731.000 1,027.000 1,549.320 295.000 |
5006001 | MOBILIZATION | LS | 1.000 | 37,039.00 | 1 2 3 4 | 25,600.000 29,072.410 30,398.080 45,000.000 |
5026001007 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 3.000 | 4,000.00 | 1 2 3 4 | 8,515.000 5,580.580 3,687.500 5,500.000 |
6106321 | IN RD IL (TY ST) 50T-10-10(400W EQ)LED | EA | 18.000 | 4,500.00 | 1 2 3 4 | 4,215.000 4,238.300 3,898.820 11,661.000 |
6186023 | CONDT (PVC) (SCH 40) (2") | LF | 3,580.000 | 8.50 | 1 2 3 4 | 9.210 9.320 13.250 10.450 |
6186047 | CONDT (PVC) (SCH 80) (2") (BORE) | LF | 855.000 | 20.00 | 1 2 3 4 | 23.450 21.300 15.570 22.000 |
6206009 | ELEC CONDR (NO.6) BARE | LF | 1,065.000 | 1.50 | 1 2 3 4 | 1.510 1.580 2.070 1.570 |
6206010 | ELEC CONDR (NO.6) INSULATED | LF | 2,130.000 | 1.75 | 1 2 3 4 | 1.660 1.700 1.820 1.540 |
6206011 | ELEC CONDR (NO.4) BARE | LF | 3,465.000 | 2.00 | 1 2 3 4 | 1.830 2.120 2.070 1.440 |
6206012 | ELEC CONDR (NO.4) INSULATED | LF | 6,930.000 | 1.80 | 1 2 3 4 | 1.930 2.190 1.830 1.980 |
6246002 | GROUND BOX TY A (122311)W/APRON | EA | 17.000 | 1,230.00 | 1 2 3 4 | 1,294.000 1,055.750 1,040.870 3,465.000 |
6286131 | ELC SRV TY D 120/240 060(NS)GS(N)SP(O) | EA | 1.000 | 7,500.00 | 1 2 3 4 | 6,530.000 5,248.000 5,266.140 13,828.000 |
61856002002 | TMA (STATIONARY) | DAY | 74.000 | 250.00 | 1 2 3 4 | 108.350 195.600 241.920 122.000 |