Tabulation of Bids for Project C 917-00-51
This report will no longer be updated, please access links on the Contract Letting page.
The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.
Text version of this page | |||
County: | BRAZOS | Let Date: | 08/05/21 |
Type: | ADVANCED TRAFFIC MANAGEMENT SYSTEM CONNECTION | Seq No: | 3260 |
Time: | 45 WORKING DAYS | Project ID: | C 917-00-51 |
Highway: | VA | Contract #: | 08213260 |
Length: | 0.000 | CCSJ: | 0917-00-051 |
Limits: | |||
From: | VARIOUS | Check: | $5,000 |
To: | VARIOUS | Misc Cost: |
Estimate | $230,300.00 | % Over/Under | Company |
Bidder 1 | $183,906.00 | -20.15% | TRAF-TEX, INC. |
Bidder 2 | $217,250.00 | -5.67% | THIRD COAST SERVICES LLC |
Bidder 3 | $227,313.99 | -1.30% | HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. |
Bidder 4 | $232,797.02 | +1.08% | ALLSTATE SIGNAL & CONSTRUCTION, LLC |
Bidder 5 | $247,066.00 | +7.28% | BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC. |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
5006001 | MOBILIZATION | LS | 1.000 | 20,000.00 | 1 2 3 4 5 | 4,362.000 21,000.000 20,125.690 3,000.000 24,000.000 |
5026001008 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 3.000 | 2,500.00 | 1 2 3 4 5 | 2,784.000 1,000.000 2,962.500 934.340 2,656.000 |
6906042 | REPLACE OF CONTROL CABINET(POLE MNT) | EA | 6.000 | 20,000.00 | 1 2 3 4 5 | 19,211.000 17,500.000 19,585.750 20,880.000 19,135.000 |
6906142 | REPLACE CABINET LOCK | EA | 114.000 | 700.00 | 1 2 3 4 5 | 429.000 750.000 526.700 866.000 792.000 |
61856002002 | TMA (STATIONARY) | DAY | 10.000 | 180.00 | 1 2 3 4 5 | 412.000 175.000 179.750 199.000 250.000 |
64306001 | INSTALL CELLULAR ROUTER | EA | 10.000 | 120.00 | 1 2 3 4 5 | 290.000 100.000 1,894.500 100.000 750.000 |