Tabulation of Bids for Project STP 1702(599)HES
Text version of this page | |||
County: | HOWARD | Let Date: | 08/08/17 |
Type: | INSTALL MEDIAN BARRIER | Seq No: | 3040 |
Time: | 93 WORKING DAYS | Project ID: | STP 1702(599)HES |
Highway: | IH 20 | Contract #: | 08173040 |
Length: | 11.661 | CCSJ: | 0005-06-119 |
Limits: | |||
From: | LOCUST ST | Check: | $47,000 |
To: | EASTLAND COUNTY LINE | Misc Cost: | $30,000.00 |
Estimate | $2,368,600.25 | % Over/Under | Company |
Bidder 1 | $1,664,669.16 | -29.72% | MASSANA CONSTRUCTION INC. |
Bidder 2 | $1,681,043.95 | -29.03% | SILVER CREEK CONSTRUCTION, INC. |
Bidder 3 | $1,742,760.10 | -26.42% | GRATIOT CONSTRUCTION, LTD. |
Bidder 4 | $2,087,662.50 | -11.86% | MIJELUM |
Bidder 5 | $2,239,694.64 | -5.44% | SCR CIVIL CONSTRUCTION, LLC |
Bidder 6 | $2,492,045.10 | +5.21% | HJC FARMS, INC. |
Bidder 7 | $2,534,168.65 | +6.99% | VANN/ELLI, INC. |
Bidder 8 | $3,000,277.15 | +26.67% | FNH CONSTRUCTION, LLC |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
1046009 | REMOVING CONC (RIPRAP) | SY | 405.300 | 12.00 | 1 2 3 4 5 6 7 8 | 10.000 20.000 15.000 100.000 90.000 15.000 35.000 38.000 |
1046019 | REMOVING CONC (OTHER APPURTENANCES) | SY | 1.000 | 500.00 | 1 2 3 4 5 6 7 8 | 100.000 30.000 60.000 2,000.000 200.000 100.000 1,000.000 1,000.000 |
1106001 | EXCAVATION (ROADWAY) | CY | 63.000 | 18.00 | 1 2 3 4 5 6 7 8 | 50.000 50.000 60.000 40.000 47.200 15.000 125.000 20.000 |
1106003 | EXCAVATION (SPECIAL) | CY | 2,114.000 | 11.00 | 1 2 3 4 5 6 7 8 | 20.000 15.000 29.500 50.000 47.200 15.000 45.000 20.000 |
1326011 | EMBANKMENT (ORIGINAL)(ORD COMP)(TY B) | CY | 1,549.000 | 55.00 | 1 2 3 4 5 6 7 8 | 10.000 24.000 40.000 55.000 32.600 15.000 45.000 40.000 |
1646035 | DRILL SEEDING (PERM) (RURAL) (CLAY) | SY | 82,093.000 | 0.15 | 1 2 3 4 5 6 7 8 | 0.120 0.150 0.400 1.500 0.180 0.200 0.250 0.750 |
3146010 | EMULS ASPH (EROSN CONT)(SS-1) | GAL | 12,323.000 | 4.00 | 1 2 3 4 5 6 7 8 | 3.000 3.000 4.800 4.000 6.700 4.000 6.500 10.000 |
4326001 | RIPRAP (CONC)(4 IN) | CY | 6.200 | 585.00 | 1 2 3 4 5 6 7 8 | 500.000 700.000 650.000 1,000.000 1,000.000 600.000 650.000 650.000 |
4326045 | RIPRAP (MOW STRIP)(4 IN) | CY | 2,114.000 | 561.00 | 1 2 3 4 5 6 7 8 | 400.000 368.000 385.000 400.000 427.000 550.000 550.000 625.000 |
4796002 | ADJUSTING INLETS | EA | 2.000 | 4,400.00 | 1 2 3 4 5 6 7 8 | 2,000.000 1,200.000 1,800.000 1,000.000 8,700.000 1,500.000 4,500.000 1,500.000 |
5006001 | MOBILIZATION | LS | 1.000 | 207,296.70 | 1 2 3 4 5 6 7 8 | 142,000.000 165,000.000 105,000.000 50,000.000 188,000.000 25,000.000 275,000.000 300,000.000 |
5026001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 5.000 | 10,500.00 | 1 2 3 4 5 6 7 8 | 4,000.000 10,000.000 11,000.000 5,000.000 8,000.000 5,000.000 12,000.000 15,000.000 |
5066041003 | BIODEG EROSN CONT LOGS (INSTL) (12") | LF | 780.000 | 4.25 | 1 2 3 4 5 6 7 8 | 5.000 5.000 10.000 7.000 8.000 10.000 5.500 12.000 |
5066043003 | BIODEG EROSN CONT LOGS (REMOVE) | LF | 780.000 | 1.25 | 1 2 3 4 5 6 7 8 | 1.000 1.000 5.000 2.000 2.400 2.250 1.500 8.000 |
5306024 | TURNOUTS (RAP) | SY | 480.000 | 50.00 | 1 2 3 4 5 6 7 8 | 20.000 10.000 30.000 200.000 109.000 35.000 42.000 42.000 |
5436002 | CABLE BARRIER SYSTEM (TL-4) | LF | 56,828.000 | 10.00 | 1 2 3 4 5 6 7 8 | 7.000 7.750 7.500 9.500 11.250 17.500 9.300 12.000 |
5436020 | CABLE BARRIER TERMINAL SECTION (TL-4) | EA | 34.000 | 2,500.00 | 1 2 3 4 5 6 7 8 | 3,000.000 2,500.000 1,950.000 2,800.000 1,800.000 3,000.000 4,000.000 6,000.000 |
6446030 | IN SM RD SN SUP&AM TYS80(1)SA(T) | EA | 4.000 | 1,075.00 | 1 2 3 4 5 6 7 8 | 1,000.000 250.000 600.000 600.000 1,300.000 1,000.000 1,200.000 650.000 |
60016002 | PORTABLE CHANGEABLE MESSAGE SIGN | EA | 4.000 | 12,000.00 | 1 2 3 4 5 6 7 8 | 5,000.000 4,000.000 3,500.000 2,500.000 8,000.000 4,500.000 10,000.000 16,500.000 |