Tabulation of Bids for Project NH 1802(607)
Text version of this page | |||
County: | HARRIS | Let Date: | 08/08/18 |
Type: | LANDSCAPE ENHANCEMENTS | Seq No: | 3234 |
Time: | 45 WORKING DAYS | Project ID: | NH 1802(607) |
Highway: | IH 610 | Contract #: | 08183234 |
Length: | 10.243 | CCSJ: | 0271-16-144 |
Limits: | |||
From: | NORTH BRAESWOOD BOULEVARD | Check: | $10,000 |
To: | REVEILLE STEET | Misc Cost: | $5,000.00 |
Estimate | $495,517.20 | % Over/Under | Company |
Bidder 1 | $614,672.00 | +24.05% | CHAMPION INFRASTRUCTURE, LLC |
Bidder 2 | $799,358.30 | +61.32% | CENTRAL NORTH CONSTRUCTION, LLC |
Bidder 3 | $965,996.87 | +94.95% | YELLOWSTONE LANDSCAPE - CENTRAL, INC. |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
1606005 | FURNISHING AND PLACING TOPSOIL | CY | 10.000 | 180.00 | 1 2 3 | 60.000 150.000 122.807 |
1616009 | EROSION CONTROL COMPOST | CY | 111.000 | 24.00 | 1 2 3 | 28.000 50.000 79.026 |
1626002 | BLOCK SODDING | SY | 150.000 | 3.18 | 1 2 3 | 2.800 25.000 7.018 |
1706002 | IRRIGATION SYSTEM (TY I) | LS | 1.000 | 10,000.00 | 1 2 3 | 220,000.000 293,000.000 96,491.228 |
1926023 | PLANT MATERIAL (15 GAL) (TREE) | EA | 4.000 | 180.00 | 1 2 3 | 50.000 85.000 100.877 |
1926024 | PLANT MATERIAL (30 GAL) (TREE) | EA | 25.000 | 300.00 | 1 2 3 | 160.000 125.000 247.018 |
1926030 | PLANT MATERIAL (3 GAL) (SHRUB) | EA | 3,276.000 | 20.00 | 1 2 3 | 15.000 18.000 28.705 |
1936002 | PLANT MAINTENANCE | CYC | 9.000 | 25,000.00 | 1 2 3 | 21,000.000 2,800.000 33,138.402 |
5006001 | MOBILIZATION | LS | 0.910 | 40,000.00 | 1 2 3 | 42,000.000 260,000.000 98,245.614 |
5026001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 3.000 | 1,500.00 | 1 2 3 | 3,500.000 3,000.000 3,567.251 |
5066038003 | TEMP SEDMT CONT FENCE (INSTALL) | LF | 200.000 | 4.00 | 1 2 3 | 4.000 10.000 12.281 |
5066039003 | TEMP SEDMT CONT FENCE (REMOVE) | LF | 200.000 | 1.00 | 1 2 3 | 2.000 10.000 0.239 |
7516011 | PRUNING | CYC | 1.020 | 105,000.00 | 1 2 3 | 45,000.000 50,000.000 241,562.491 |
10006006 | PRUNING AND TRIMMING TREES AND SHRUBS | CYC | 1.010 | 24,000.00 | 1 2 3 | 36,000.000 65,000.000 103,508.772 |
10066001 | LANDSCAPE SOIL AMENDMENT (TYPE I) | SY | 2,398.000 | 0.50 | 1 2 3 | 1.000 2.220 0.278 |
10066002 | LANDSCAPE SOIL AMENDMENT (TYPE II) | SY | 2,398.000 | 0.40 | 1 2 3 | 1.000 1.250 0.278 |
10066003 | LANDSCAPE SOIL AMENDMENT (TYPE III) | SY | 206.000 | 3.00 | 1 2 3 | 3.000 5.000 1.277 |
10066004 | LANDSCAPE SOIL AMENDMENT (TYPE IV) | SY | 206.000 | 4.00 | 1 2 3 | 3.000 5.000 0.247 |
10066005 | LANDSCAPE SOIL AMENDMENT (TYPE V) | SY | 9,592.000 | 0.50 | 1 2 3 | 1.000 2.220 0.409 |
61856002001 | TMA (STATIONARY) | DAY | 1.000 | 200.00 | 1 2 3 | 400.000 10,000.000 473.684 |