Tabulation of Bids for Project RMC - 633362001
Text version of this page | |||
County: | LAMAR | Let Date: | 09/20/18 |
Type: | ON CALL METAL BEAM GUARD FENCE REPAIR | Seq No: | 0101 |
Time: | 365 CALENDAR DAYS | Project ID: | RMC - 633362001 |
Highway: | US0082 | Contract #: | 09180101 |
Length: | 0.000 | CCSJ: | 6333-62-001 |
Limits: | |||
From: | VARIOUS LOCATIONS IN LAMAR, DELTA, | Check: | $5,000 |
To: | AND RED RIVER COUNTIES | Misc Cost: |
Estimate | $265,360.00 | % Over/Under | Company |
Bidder 1 | $262,851.65 | -0.95% | JE CASEY, LLC |
Bidder 2 | $326,691.50 | +23.11% | SOUTHERN CROSS CONTRACTORS, LLC |
Bidder 3 | $327,983.00 | +23.60% | CATOCON, INC. |
Bidder 4 | $379,574.00 | +43.04% | ELITE CASTLE RESOURCES LLC |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
5006033 | MOBILIZATION (CALLOUT) | EA | 24.000 | 500.00 | 1 2 3 4 | 100.000 1.000 1.000 1.000 |
5406002 | MTL W-BEAM GD FEN (STEEL POST) | LF | 750.000 | 18.00 | 1 2 3 4 | 21.640 20.000 35.000 26.000 |
5406022 | MTL THRIE-BEAM GD FEN (STEEL POST) | EA | 15.000 | 1,800.00 | 1 2 3 4 | 1,510.530 1,700.000 1,300.000 1,500.000 |
5426001 | REMOVE METAL BEAM GUARD FENCE | LF | 750.000 | 2.50 | 1 2 3 4 | 3.640 2.000 1.000 8.000 |
5426002 | REMOVE TERMINAL ANCHOR SECTION | EA | 4.000 | 250.00 | 1 2 3 4 | 208.240 200.000 1.000 500.000 |
5456001 | CRASH CUSH ATTEN (INSTL) | EA | 1.000 | 9,500.00 | 1 2 3 4 | 7,957.650 8,000.000 14,000.000 15,000.000 |
5456005 | CRASH CUSH ATTEN (REMOVE) | EA | 2.000 | 500.00 | 1 2 3 4 | 728.830 750.000 900.000 2,000.000 |
5456024 | CRASH CUSHION ATTEN (INSTALL) (TRACC) | EA | 1.000 | 14,500.00 | 1 2 3 4 | 12,357.650 13,000.000 14,000.000 12,000.000 |
6586001 | INSTL DEL ASSM (D-SW)SZ 1(FLX)GND | EA | 40.000 | 5.00 | 1 2 3 4 | 44.680 30.000 20.000 40.000 |
6586002 | INSTL DEL ASSM (D-SW)SZ 1(FLX)GND(BI) | EA | 50.000 | 5.00 | 1 2 3 4 | 44.920 30.000 20.000 40.000 |
6586048 | INSTL OM ASSM (OM-2Z)(FLX)GND | EA | 90.000 | 5.00 | 1 2 3 4 | 47.720 30.000 20.000 40.000 |
7706001 | REPAIR RAIL ELEMENT (W - BEAM) | LF | 2,600.000 | 15.00 | 1 2 3 4 | 13.530 15.000 18.000 20.000 |
7706002 | REPAIR RAIL ELEMENT (THRIE - BEAM) | LF | 80.000 | 22.00 | 1 2 3 4 | 15.770 18.000 18.000 5.000 |
7706003 | REP RAIL ELMNT(THRIE-BM TRANS TO W -BM) | LF | 80.000 | 18.00 | 1 2 3 4 | 27.930 30.000 28.000 5.000 |
7706004 | REPAIR RAIL ELEMENT (CURVED RAIL) | LF | 80.000 | 22.00 | 1 2 3 4 | 23.650 28.000 20.000 35.000 |
7706006 | RAISE RAIL ELEMENT | LF | 750.000 | 5.00 | 1 2 3 4 | 3.640 9.000 4.000 10.000 |
7706012 | REM / REPL TIMBER POST W / O CONC FND | EA | 250.000 | 37.00 | 1 2 3 4 | 35.200 60.000 40.000 50.000 |
7706013 | REM / REPL STEEL POST W / O CONC FND | EA | 50.000 | 35.00 | 1 2 3 4 | 59.200 80.000 41.000 50.000 |
7706014 | REM / REPL TIMBER POST W / CONC FND | EA | 5.000 | 20.00 | 1 2 3 4 | 34.000 60.000 40.000 50.000 |
7706015 | REM / REPL STEEL POST W / CONC FND | EA | 5.000 | 20.00 | 1 2 3 4 | 63.000 80.000 41.000 50.000 |
7706017 | REALIGN POSTS | EA | 250.000 | 15.00 | 1 2 3 4 | 9.720 25.000 14.000 50.000 |
7706019 | REMOVE & REPLACE BLOCKOUT | EA | 50.000 | 18.00 | 1 2 3 4 | 14.960 25.000 19.000 50.000 |
7706021 | REPLACE SINGLE GDRAIL TERMINAL RAIL | LF | 250.000 | 25.00 | 1 2 3 4 | 94.330 24.750 37.000 60.000 |
7706022 | REPLACE SINGLE GDRAIL TERMINAL POST | EA | 40.000 | 50.00 | 1 2 3 4 | 33.720 80.000 83.000 200.000 |
7706027 | REMOVE GDRAIL END TRT / REPL WITH SGT | EA | 50.000 | 2,000.00 | 1 2 3 4 | 1,848.880 2,700.000 2,900.000 3,000.000 |
7706028 | REPL SINGLE GDRAIL TERM IMPACT HEAD | EA | 5.000 | 950.00 | 1 2 3 4 | 736.880 850.000 1,000.000 880.000 |
7706029 | REM & RESET SGT IMPACT HEAD | EA | 5.000 | 75.00 | 1 2 3 4 | 72.880 500.000 120.000 250.000 |
7706031 | REPLACE SGT CABLE ANCHOR | EA | 5.000 | 75.00 | 1 2 3 4 | 82.000 65.000 50.000 50.000 |
7706032 | REPLACE SGT STRUT | EA | 5.000 | 75.00 | 1 2 3 4 | 70.000 55.000 50.000 50.000 |
7746011 | REPAIR (CATCB - FRNT SECT) | EA | 2.000 | 1,000.00 | 1 2 3 4 | 291.530 5,000.000 3,000.000 2,500.000 |
7746012 | REPAIR (CATCB - REAR SECT) | EA | 2.000 | 1,000.00 | 1 2 3 4 | 291.530 4,000.000 2,000.000 800.000 |
61856002 | TMA (STATIONARY) | DAY | 24.000 | 100.00 | 1 2 3 4 | 242.940 300.000 100.000 500.000 |