Tabulation of Bids for Project RMC - 633158001
Text version of this page | |||
County: | BELL | Let Date: | 09/27/18 |
Type: | TREE TRIMMING AND TREE REMOVAL | Seq No: | 0901 |
Time: | 47 W | Project ID: | RMC - 633158001 |
Highway: | FM0487 | Contract #: | 09180901 |
Length: | 0.000 | CCSJ: | 6331-58-001 |
Limits: | |||
From: | INDIAN CREEK RD | Check: | $2,000 |
To: | HUNT JONES RD | Misc Cost: |
Estimate | $78,375.00 | % Over/Under | Company |
Bidder 1 | $54,500.00 | -30.46% | VIKOTA SERVICES LLC |
Bidder 2 | $67,250.01 | -14.19% | JENKINS AND JENKINS CONSTRUCTION, LLC |
Bidder 3 | $100,005.00 | +27.60% | BOEN LANDSCAPING & IRRIGATION, LLC |
Bidder 4 | $101,865.00 | +29.97% | WESTGATE GROUP, LLC |
Bidder 5 | $107,445.00 | +37.09% | ROAD SOLUTIONS L.L.C. |
Bidder 6 | $110,627.30 | +41.15% | ALL IN CONSTRUCTION, L.L.C. |
Bidder 7 | $134,388.00 | +71.47% | CROSS PLUS CONSTRUCTION, LLC |
Bidder 8 | $141,750.00 | +80.86% | KASPARIAN UNDERGROUND, LLC |
Bidder 9 | $155,017.46 | +97.79% | K 5 SERVICES, LLC |
Bidder 10 | $237,405.00 | +202.91% | DRC EMERGENCY SERVICES, LLC |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
5006033 | MOBILIZATION (CALLOUT) | EA | 3.000 | 1,425.00 | 1 2 3 4 5 6 7 8 9 10 | 500.000 0.001 500.000 1.000 500.000 5,500.000 1.000 1,000.000 1,393.630 10,000.000 |
5006034 | MOBILIZATION (EMERGENCY) | EA | 2.000 | 1,425.00 | 1 2 3 4 5 6 7 8 9 10 | 100.000 0.001 1,000.000 1.000 510.000 5,500.000 1.000 1,000.000 864.020 20,000.000 |
7526003 | TREE TRIMMING / BRUSH REMOVAL | MI | 30.000 | 1,500.00 | 1 2 3 4 5 6 7 8 9 10 | 700.000 1,500.000 2,200.000 1,820.000 2,100.000 1,355.000 2,800.000 3,000.000 2,800.000 3,000.000 |
7526004 | TREE TRIMMING / BRUSH REMOVAL(CHANNELS) | AC | 8.000 | 1,500.00 | 1 2 3 4 5 6 7 8 9 10 | 700.000 1,000.000 1,500.000 780.000 1,950.000 2,300.000 2,800.000 2,000.000 2,600.000 7,500.000 |
7526005 | TREE REMOVAL (4" - 12" DIA) | EA | 90.000 | 50.00 | 1 2 3 4 5 6 7 8 9 10 | 90.000 75.000 50.000 180.000 45.000 111.000 100.000 100.000 169.080 55.000 |
7526006 | TREE REMOVAL (12" - 18" DIA) | EA | 30.000 | 75.00 | 1 2 3 4 5 6 7 8 9 10 | 200.000 95.000 95.000 180.000 125.000 118.500 100.000 175.000 314.780 95.000 |
7526007 | TREE REMOVAL (18" - 24" DIA) | EA | 30.000 | 100.00 | 1 2 3 4 5 6 7 8 9 10 | 300.000 115.000 150.000 180.000 250.000 115.210 200.000 250.000 318.220 135.000 |
7526008 | TREE REMOVAL (24" - 30" DIA) | EA | 4.000 | 200.00 | 1 2 3 4 5 6 7 8 9 10 | 200.000 100.000 220.000 180.000 450.000 172.000 400.000 350.000 359.610 195.000 |
7526009 | TREE REMOVAL (30" - 36" DIA) | EA | 3.000 | 250.00 | 1 2 3 4 5 6 7 8 9 10 | 200.000 100.000 275.000 600.000 600.000 172.000 500.000 450.000 502.490 245.000 |
7526010 | TREE REMOVAL (36" - 42" DIA) | EA | 2.000 | 350.00 | 1 2 3 4 5 6 7 8 9 10 | 200.000 100.000 350.000 1,500.000 750.000 220.000 500.000 600.000 731.690 275.000 |
7526011 | TREE REMOVAL (42" - 48" DIA) | EA | 2.000 | 450.00 | 1 2 3 4 5 6 7 8 9 10 | 200.000 100.000 500.000 1,500.000 1,000.000 225.000 1,400.000 800.000 620.380 350.000 |
7526012 | TREE REMOVAL (48" - 60" DIA) | EA | 1.000 | 500.00 | 1 2 3 4 5 6 7 8 9 10 | 200.000 100.000 1,000.000 1,500.000 1,500.000 240.000 1,234.000 1,000.000 969.680 425.000 |
7526013 | TREE REMOVAL (60" - 72" DIA) | EA | 1.000 | 600.00 | 1 2 3 4 5 6 7 8 9 10 | 200.000 0.001 2,000.000 1,500.000 2,000.000 242.000 1,234.000 1,200.000 606.600 615.000 |
7526018 | STUMP REMOVAL (GREATER THAN 12") | EA | 5.000 | 50.00 | 1 2 3 4 5 6 7 8 9 10 | 100.000 0.001 50.000 500.000 85.000 900.000 123.000 250.000 575.000 350.000 |