Tabulation of Bids for Project RMC - 632015001
Text version of this page | |||
County: | BRAZORIA | Let Date: | 10/04/17 |
Type: | BRIDGE JOINT CLEANING | Seq No: | 4207 |
Time: | 365 CALENDAR DAYS | Project ID: | RMC - 632015001 |
Highway: | SH0288 | Contract #: | 10174207 |
Length: | 0.001 | CCSJ: | 6320-15-001 |
Limits: | |||
From: | VARIOUS LOCATIONS IN BRAZORIA CTY | Check: | $9,000 |
To: | VARIOUS LOCATIONS IN BRAZORIA CTY | Misc Cost: | $4,300.00 |
Estimate | $449,100.00 | % Over/Under | Company |
Bidder 1 | $433,000.00 | -3.58% | ISI CONTRACTING, INC. |
Bidder 2 | $452,600.00 | +0.78% | MAIN LANE INDUSTRIES LTD. |
Bidder 3 | $480,000.00 | +6.88% | CHAMPION INFRASTRUCTURE, LLC |
Bidder 4 | $538,700.00 | +19.95% | SCR CIVIL CONSTRUCTION, LLC |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
4386001 | CLEANING AND SEALING EXISTING JOINTS | LF | 10,000.000 | 31.49 | 1 2 3 4 | 33.000 34.200 32.000 40.000 |
4386009 | CLEANING EXISTING JOINTS | LF | 10,000.000 | 12.22 | 1 2 3 4 | 10.000 11.000 10.000 13.750 |
5006033 | MOBILIZATION (CALLOUT) | EA | 12.000 | 1,000.00 | 1 2 3 4 | 250.000 50.000 5,000.000 100.000 |