Tabulation of Bids for Project BPM - 643158001
Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months.
The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.
Text version of this page | |||
County: | HUDSPETH | Let Date: | 10/05/23 |
Type: | BRIDGE PREVENTATIVE MAINTENANCE | Seq No: | 4011 |
Time: | 100 W | Project ID: | BPM - 643158001 |
Highway: | IH0010 | Contract #: | 10234011 |
Length: | 0.010 | CCSJ: | 6431-58-001 |
Limits: | |||
From: | VARIOUS LOCATION | Check: | $30,000 |
To: | VARIOUS LOCATIONS | Misc Cost: |
Estimate | $1,477,372.82 | % Over/Under | Company |
Bidder 1 | $1,643,286.62 | +11.23% | SPARTAN CONSTRUCTION OF TEXAS, INC. |
Bidder 2 | $1,830,878.00 | +23.93% | HAWK CONSTRUCTION |
Bidder 3 | $2,801,705.00 | +89.64% | DAN WILLIAMS COMPANY |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
1046009 | REMOVING CONC (RIPRAP) | SY | 1,019.000 | 15.25 | 1 2 3 | 44.712 50.000 40.000 |
1046021 | REMOVING CONC (CURB) | LF | 44.000 | 8.00 | 1 2 3 | 31.050 50.000 45.000 |
1326005 | EMBANKMENT (FINAL)(ORD COMP)(TY C) | CY | 141.000 | 11.58 | 1 2 3 | 155.250 85.000 275.000 |
3546004 | PLAN & TEXT ASPH CONC PAV(0" TO 4") | SY | 963.000 | 2.55 | 1 2 3 | 18.630 22.000 25.000 |
3546021 | PLANE ASPH CONC PAV(0" TO 2") | SY | 2,326.000 | 6.10 | 1 2 3 | 24.840 20.000 20.000 |
4206141 | CL C CONC (CURB) | CY | 2.000 | 2,118.60 | 1 2 3 | 2,484.000 2,000.000 5,000.000 |
4296003 | CONC STR REPAIR(DECK REP(PART DEPTH)) | SF | 78.000 | 270.00 | 1 2 3 | 248.400 215.000 520.000 |
4296007 | CONC STR REPAIR (VERTICAL & OVERHEAD) | SF | 2,062.000 | 237.05 | 1 2 3 | 155.250 165.000 350.000 |
4326001 | RIPRAP (CONC)(4 IN) | CY | 26.000 | 571.86 | 1 2 3 | 1,614.600 2,000.000 2,400.000 |
4426035001 | STR STEEL (NBIS) | LB | 728.000 | 21.43 | 1 2 3 | 22.356 25.000 20.000 |
4546009 | JOINT SEALANT | LF | 369.000 | 25.00 | 1 2 3 | 62.100 23.000 75.000 |
4596008 | GABION MATTRESSES (GALV)(18 IN) | SY | 216.000 | 115.81 | 1 2 3 | 329.130 200.000 350.000 |
4596009 | GABIONS (3' X 3')(GALV) | CY | 396.000 | 204.94 | 1 2 3 | 683.100 250.000 550.000 |
4806001 | CLEAN EXIST CULVERTS | EA | 1.000 | 2,984.21 | 1 2 3 | 24,840.000 20,000.000 20,000.000 |
5006001 | MOBILIZATION | LS | 1.000 | 126,706.53 | 1 2 3 | 172,276.200 40,000.000 280,000.000 |
5026001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 5.000 | 7,000.00 | 1 2 3 | 8,726.400 20,000.000 40,000.000 |
5066040 | BIODEG EROSN CONT LOGS (INSTL) (8") | LF | 200.000 | 4.33 | 1 2 3 | 9.936 20.000 11.000 |
5066043 | BIODEG EROSN CONT LOGS (REMOVE) | LF | 200.000 | 1.08 | 1 2 3 | 3.726 4.000 3.500 |
7606001 | DITCH CLEANING AND RESHAPING (FOOT) | LF | 250.000 | 5.67 | 1 2 3 | 49.680 200.000 60.000 |
7806002 | CNC CRACK REPAIR (DISCRETE)(INJECT) | LF | 18.000 | 108.55 | 1 2 3 | 217.350 500.000 200.000 |
7856001 | BRIDGE JOINT REPAIR (CONCRETE) | LF | 1,290.000 | 390.00 | 1 2 3 | 229.770 475.000 450.000 |
7856011 | BRIDGE JOINT REPLACEMENT (SEJ) | LF | 372.000 | 250.00 | 1 2 3 | 304.290 550.000 900.000 |
61856002002 | TMA (STATIONARY) | DAY | 100.000 | 180.00 | 1 2 3 | 621.000 750.000 425.000 |