Tabulation of Bids for Project F 2024(302)
This report will no longer be updated, please access links on the Contract Letting page.
The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.
Text version of this page | |||
County: | TAYLOR | Let Date: | 11/01/23 |
Type: | PREVENTIVE MAINTENANCE | Seq No: | 3017 |
Time: | 106 WORKING DAYS | Project ID: | F 2024(302) |
Highway: | US 277 | Contract #: | 11233017 |
Length: | 3.990 | CCSJ: | 0407-06-047 |
Limits: | |||
From: | SOUTH END OF BNSF BRIDGE | Check: | $62,000 |
To: | 3.7 MI SW OF FM 1235 | Misc Cost: |
Estimate | $3,090,887.33 | % Over/Under | Company |
Bidder 1 | $2,639,408.32 | -14.61% | FOUTSCO PAVING COMPANY, LLC |
Bidder 2 | $3,173,156.60 | +2.66% | CK NEWBERRY, LLC |
Bidder 3 | $3,282,544.06 | +6.20% | DUININCK, INC. |
Bidder 4 | $3,672,473.74 | +18.82% | REECE ALBERT, INC. |
Bidder 5 | $3,888,838.00 | +25.82% | FNH CONSTRUCTION, LLC |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
1106001 | EXCAVATION (ROADWAY) | CY | 218.000 | 32.00 | 1 2 3 4 5 | 10.000 65.000 48.500 84.570 50.000 |
1326001 | EMBANKMENT (FINAL)(ORD COMP)(TY A) | CY | 218.000 | 55.00 | 1 2 3 4 5 | 10.000 65.000 97.000 93.050 100.000 |
1346002 | BACKFILL (TY B) | STA | 462.000 | 35.00 | 1 2 3 4 5 | 100.000 140.000 100.000 325.590 200.000 |
3106005 | PRIME COAT (AE-P) | GAL | 1,000.000 | 5.00 | 1 2 3 4 5 | 0.100 7.000 8.250 7.650 10.000 |
3516013 | FLEXIBLE PAVEMENT STRUCTURE REPAIR(4") | SY | 5,631.000 | 45.05 | 1 2 3 4 5 | 30.000 45.000 48.000 65.200 50.000 |
3546041 | PLANE ASPH CONC PAV (1.5") | SY | 112,615.000 | 3.00 | 1 2 3 4 5 | 1.500 1.500 2.300 3.100 5.000 |
4646005001 | RC PIPE (CL III)(24 IN) | LF | 13.000 | 200.00 | 1 2 3 4 5 | 360.000 260.000 430.000 338.970 150.000 |
4676005 | SET (TY I) (24 IN) (3: 1) (C) | EA | 7.000 | 4,196.00 | 1 2 3 4 5 | 1,300.000 10,000.000 1,600.000 3,954.710 3,000.000 |
4676296 | SET (TY I)(S= 9 FT)(HW= 4 FT)(3:1) (C) | EA | 2.000 | 5,200.00 | 1 2 3 4 5 | 13,000.000 40,000.000 16,500.000 16,383.790 30,000.000 |
4676307 | SET (TY I)(S= 9 FT)(HW= 7 FT)(3:1) (C) | EA | 2.000 | 13,000.00 | 1 2 3 4 5 | 15,000.000 50,000.000 19,500.000 28,247.910 40,000.000 |
5006001 | MOBILIZATION | LS | 1.000 | 280,989.76 | 1 2 3 4 5 | 242,000.000 300,000.000 325,000.000 181,693.690 365,000.000 |
5026001008 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 6.000 | 8,000.00 | 1 2 3 4 5 | 30,000.000 4,000.000 32,500.000 8,642.170 8,500.000 |
5066002005 | ROCK FILTER DAMS (INSTALL) (TY 2) | LF | 120.000 | 44.00 | 1 2 3 4 5 | 20.000 55.000 48.000 120.900 50.000 |
5066011005 | ROCK FILTER DAMS (REMOVE) | LF | 120.000 | 9.30 | 1 2 3 4 5 | 5.000 12.000 12.000 51.310 20.000 |
5066038005 | TEMP SEDMT CONT FENCE (INSTALL) | LF | 325.000 | 4.40 | 1 2 3 4 5 | 5.000 10.000 9.600 17.950 4.000 |
5066039005 | TEMP SEDMT CONT FENCE (REMOVE) | LF | 325.000 | 2.15 | 1 2 3 4 5 | 1.000 5.000 1.200 8.000 2.000 |
5066041005 | BIODEG EROSN CONT LOGS (INSTL) (12") | LF | 840.000 | 5.76 | 1 2 3 4 5 | 8.000 12.000 9.600 19.340 18.000 |
5066043005 | BIODEG EROSN CONT LOGS (REMOVE) | LF | 840.000 | 1.21 | 1 2 3 4 5 | 1.000 5.000 1.200 6.290 9.000 |
5296008 | CONC CURB & GUTTER (TY II) | LF | 26.000 | 82.00 | 1 2 3 4 5 | 250.000 75.000 360.000 90.390 200.000 |
5336003 | RUMBLE STRIPS (SHOULDER) ASPHALT | LF | 42,236.000 | 0.16 | 1 2 3 4 5 | 0.200 0.250 0.120 0.240 0.500 |
5336004 | RUMBLE STRIPS (CENTERLINE) ASPHALT | LF | 21,118.000 | 0.14 | 1 2 3 4 5 | 0.200 0.450 0.140 0.400 0.500 |
5406001001 | MTL W-BEAM GD FEN (TIM POST) | LF | 200.000 | 30.00 | 1 2 3 4 5 | 30.000 60.000 33.000 31.430 50.000 |
5406017001 | MTL BM GD FEN (LONG SPAN SYSTEM) | LF | 200.000 | 50.00 | 1 2 3 4 5 | 30.000 85.000 36.000 34.290 50.000 |
5446001 | GUARDRAIL END TREATMENT (INSTALL) | EA | 8.000 | 2,934.00 | 1 2 3 4 5 | 3,000.000 4,500.000 4,000.000 3,772.180 3,500.000 |
6626111 | WK ZN PAV MRK SHT TERM (TAB)TY Y-2 | EA | 3,712.000 | 1.17 | 1 2 3 4 5 | 0.100 2.500 1.700 1.970 6.000 |
6666306007 | RE PM W/RET REQ TY I (W)6"(BRK)(100MIL) | LF | 2,200.000 | 0.75 | 1 2 3 4 5 | 0.490 0.850 0.590 0.790 2.000 |
6666309007 | RE PM W/RET REQ TY I (W)6"(SLD)(100MIL) | LF | 41,468.000 | 0.75 | 1 2 3 4 5 | 0.490 0.750 0.590 0.770 2.000 |
6666318007 | RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL) | LF | 2,460.000 | 0.75 | 1 2 3 4 5 | 0.490 0.800 0.590 0.790 2.000 |
6666321007 | RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL) | LF | 29,810.000 | 0.75 | 1 2 3 4 5 | 0.490 0.750 0.590 0.770 2.000 |
6686076 | PREFAB PAV MRK TY C (W) (24") (SLD) | LF | 94.000 | 22.60 | 1 2 3 4 5 | 20.000 35.000 24.000 22.150 20.000 |
6726007 | REFL PAV MRKR TY I-C | EA | 115.000 | 3.61 | 1 2 3 4 5 | 5.000 10.000 6.000 7.340 6.000 |
6726009 | REFL PAV MRKR TY II-A-A | EA | 517.000 | 3.30 | 1 2 3 4 5 | 5.000 10.000 6.000 7.340 6.000 |
30776023 | SP MIXES SP-C SAC-B PG70-22 | TON | 12,388.000 | 150.00 | 1 2 3 4 5 | 133.000 145.000 145.900 173.690 155.000 |
30776075 | TACK COAT | GAL | 11,262.000 | 4.00 | 1 2 3 4 5 | 0.100 5.250 6.850 3.200 8.000 |
61856002002 | TMA (STATIONARY) | DAY | 80.000 | 311.00 | 1 2 3 4 5 | 1.000 315.000 360.000 323.670 250.000 |
61856005002 | TMA (MOBILE OPERATION) | DAY | 4.000 | 625.00 | 1 2 3 4 5 | 1.000 615.000 1,200.000 861.560 550.000 |