Tabulation of Bids for Project NH 2021(099)

Last Update: Tuesday, January 26, 2021

Bid Tabulations Dashboard

Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months.

The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.

Text version of this page
County:CASSLet Date:11/04/20
Type:INSTALL MEDIAN BARRIERSeq No:3011
Time:276 WORKING DAYSProject ID:NH 2021(099)
Highway:US 59Contract #:11203011
Length:35.765CCSJ:0062-04-050
Limits: 
From:1.46 MI S. OF SH 155Check:$100,000
To:MARION COUNTY LINEMisc Cost:
Estimate$7,472,559.20% Over/UnderCompany
Bidder 1$4,434,952.65-40.65%H. V. CAVER, INC.
Bidder 2$4,624,951.77-38.11%COLLINS & HERMANN, INC.
Bidder 3$4,986,345.55-33.27%R & G CONSTRUCTION, LLC
Bidder 4$5,035,703.60-32.61%SCR CIVIL CONSTRUCTION, LLC
Bidder 5$5,480,327.54-26.66%CROSS PLUS CONSTRUCTION, LLC
Bidder 6$6,238,191.77-16.52%ALTUS CONSTRUCTION LLC
Bidder 7$6,612,498.50-11.51%FNH CONSTRUCTION, LLC
Bidder 8$6,772,154.45-9.37%GRATIOT CONSTRUCTION, LTD.
Bidder 9$7,104,771.25-4.92%HARRISON, WALKER AND HARPER, LP
Bidder 10$7,414,065.42-0.78%LONGVIEW BRIDGE AND ROAD, LTD.
Bidder 11$8,352,365.36+11.77%EAST TEXAS BRIDGE, INC.
Item CodeDescriptionUnitQuantityUnit Est.BidderUnit Bid
1606003FURNISHING AND PLACING TOPSOIL (4")SY17,737.0001.501
2
3
4
5
6
7
8
9
10
11
2.000
5.610
3.000
6.400
3.000
1.420
15.000
27.000
6.000
2.500
3.000
1646071BROADCAST SEED (TEMP)(WARM OR COOL)SY17,737.0000.101
2
3
4
5
6
7
8
9
10
11
0.250
3.080
0.150
0.400
0.420
0.290
0.500
0.500
0.200
0.160
0.280
1686001VEGETATIVE WATERINGMG286.00010.001
2
3
4
5
6
7
8
9
10
11
1.000
25.080
2.000
31.000
20.000
35.520
100.000
37.500
27.450
10.000
13.000
4326045RIPRAP (MOW STRIP)(4 IN)CY5,911.000450.001
2
3
4
5
6
7
8
9
10
11
345.000
356.210
400.000
380.000
423.000
465.630
550.000
413.750
428.650
420.000
550.000
5006001MOBILIZATIONLS1.000581,000.001
2
3
4
5
6
7
8
9
10
11
262,000.000
385,101.390
300,000.000
410,000.000
700,000.000
617,984.070
650,000.000
626,250.000
679,400.000
650,000.000
800,000.000
5026001008BARRICADES, SIGNS AND TRAFFIC HANDLINGMO18.0006,000.001
2
3
4
5
6
7
8
9
10
11
5,970.000
1.020
2,000.000
6,000.000
5,000.000
30,986.020
8,500.000
2,500.000
13,550.000
3,500.000
15,000.000
5436001CABLE BARRIER SYSTEM (TL-3)LF159,630.00015.001
2
3
4
5
6
7
8
9
10
11
7.780
8.560
8.000
9.000
9.000
10.330
7.500
15.140
13.700
13.500
14.000
5436019CABLE BARRIER TERMINAL SECTION (TL-3)EA276.0006,000.001
2
3
4
5
6
7
8
9
10
11
2,695.000
2,028.950
3,450.000
2,176.000
2,299.000
1,911.600
3,500.000
2,675.000
4,320.000
7,200.000
6,000.000
61856002002TMA (STATIONARY)DAY262.000160.001
2
3
4
5
6
7
8
9
10
11
1.000
177.650
1.000
400.000
200.000
355.160
350.000
6.250
575.000
100.000
300.000