Tabulation of Bids for Project STP 2019(189)TAPS
Text version of this page | |||
County: | CHAMBERS | Let Date: | 11/06/18 |
Type: | INSTALL ILLUMINATION | Seq No: | 3007 |
Time: | 71 WORKING DAYS | Project ID: | STP 2019(189)TAPS |
Highway: | VA | Contract #: | 11183007 |
Length: | 2.600 | CCSJ: | 0920-39-024 |
Limits: | |||
From: | FM 565,EAGLE DR TO FISHER'S LANDING | Check: | $21,000 |
To: | EAGLE DR,CHERRY PT TO FM 565 | Misc Cost: | $10,000.00 |
Estimate | $1,061,384.79 | % Over/Under | Company |
Bidder 1 | $1,080,400.10 | +1.79% | THIRD COAST SERVICES LLC |
Bidder 2 | $1,263,567.64 | +19.05% | FLORIDA TRAFFIC CONTROL DEVICES, INC. |
Bidder 3 | $1,278,959.81 | +20.50% | PFEIFFER & SON LTD. |
Bidder 4 | $1,338,032.25 | +26.06% | HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. |
Bidder 5 | $1,604,243.00 | +51.15% | LUDCO, INC. |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
1646030 | CELL FBR MLCH SEED(TEMP)(WARM) | AC | 0.890 | 1,378.00 | 1 2 3 4 5 | 1,700.000 2,020.040 20,540.000 3,253.760 3,000.000 |
1686001 | VEGETATIVE WATERING | MG | 24.260 | 20.11 | 1 2 3 4 5 | 690.000 104.390 621.600 82.000 250.000 |
5006001 | MOBILIZATION | LS | 1.000 | 100,000.00 | 1 2 3 4 5 | 100,000.000 21,976.210 38,900.000 127,458.920 100,000.000 |
5026001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 5.000 | 5,895.00 | 1 2 3 4 5 | 950.000 6,786.820 8,800.000 7,059.000 4,000.000 |
6186016 | CONDT (PVC) (SCH 40) (1") | LF | 12,486.000 | 8.00 | 1 2 3 4 5 | 5.250 8.490 15.130 8.900 22.000 |
6186017 | CONDT (PVC) (SCH 40) (1") (BORE) | LF | 408.000 | 15.00 | 1 2 3 4 5 | 8.900 18.120 53.670 19.630 22.000 |
6186018 | CONDT (PVC) (SCH 40) (1") (CONC ENCSE) | LF | 485.000 | 25.00 | 1 2 3 4 5 | 19.000 15.480 38.760 19.030 44.000 |
6206006 | ELEC CONDR (NO.10) INSULATED | LF | 103,000.000 | 1.25 | 1 2 3 4 5 | 0.850 0.810 0.690 0.950 1.500 |
6206008 | ELEC CONDR (NO.8) INSULATED | LF | 16,250.000 | 1.45 | 1 2 3 4 5 | 1.000 1.010 0.925 1.100 2.000 |
6286266 | ELC SRV TY D 120/240 125(NS)SS(N)SF(U) | EA | 4.000 | 7,500.00 | 1 2 3 4 5 | 10,875.000 11,927.750 13,735.000 33,924.350 7,500.000 |
41286001 | PRECAST LIGHT POLE FOUNDATION | EA | 190.000 | 550.00 | 1 2 3 4 5 | 785.000 1,081.150 834.210 817.000 1,500.000 |
63336001 | IN RD IL AM (55W LED ARRAY)(ORNAMENTAL) | EA | 191.000 | 2,750.00 | 1 2 3 4 5 | 3,050.000 3,819.100 3,317.010 3,326.580 3,500.000 |