Tabulation of Bids for Project STP 1809(759)
This report will no longer be updated, please access links on the Contract Letting page.
The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.
Text version of this page | |||
County: | BEXAR | Let Date: | 12/03/20 |
Type: | TRAFFIC SIGNAL COMMUNICATION UPGRADES | Seq No: | 3223 |
Time: | 105 WORKING DAYS | Project ID: | STP 1809(759) |
Highway: | VA | Contract #: | 12203223 |
Length: | 0.001 | CCSJ: | 0915-00-199 |
Limits: | |||
From: | VARIOUS LOCATIONS DISTRICTWIDE | Check: | $6,000 |
To: | . | Misc Cost: |
Estimate | $291,350.00 | % Over/Under | Company |
Bidder 1 | $282,660.55 | -2.98% | THE LEVY COMPANY, INC. |
Bidder 2 | $358,234.84 | +22.96% | HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. |
Bidder 3 | $362,250.00 | +24.33% | E-Z BEL CONSTRUCTION, LLC |
Bidder 4 | $376,152.00 | +29.11% | K-BAR SERVICES, INC. |
Bidder 5 | $451,000.00 | +54.80% | LIGHT IT UP ELECTRIC |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
5006001 | MOBILIZATION | LS | 1.000 | 26,200.00 | 1 2 3 4 5 | 28,266.050 63,153.840 40,000.000 37,352.000 65,000.000 |
5026001008 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 7.000 | 2,950.00 | 1 2 3 4 5 | 2,407.950 5,201.750 5,000.000 4,000.000 3,000.000 |
6906038 | REMOVAL OF CONTROL CABINET(GRND MNT) | EA | 5.000 | 1,100.00 | 1 2 3 4 5 | 356.000 2,847.500 900.000 560.000 500.000 |
6906040 | INSTALL OF CONTROL CABINET(GRND MNT) | EA | 5.000 | 1,600.00 | 1 2 3 4 5 | 1,790.520 4,086.250 1,800.000 4,100.000 6,500.000 |
61856002002 | TMA (STATIONARY) | DAY | 200.000 | 30.00 | 1 2 3 4 5 | 50.000 57.500 150.000 250.000 275.000 |
63016002 | INSTALL TRAF SIGNAL CONT EQUIP (PKG 2) | EA | 125.000 | 1,800.00 | 1 2 3 4 5 | 1,734.450 1,700.000 1,950.000 1,900.000 2,200.000 |