Tabulation of Bids for Project RMC - 637398001
Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months.
The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.
Text version of this page | |||
County: | GRAY | Let Date: | 12/16/20 |
Type: | TREE REMOVAL | Seq No: | 0401 |
Time: | 60 W | Project ID: | RMC - 637398001 |
Highway: | US0060 | Contract #: | 12200401 |
Length: | 0.000 | CCSJ: | 6373-98-001 |
Limits: | |||
From: | SEE PLAN SHEETS | Check: | $6,000 |
To: | SEE PLAN SHEETS | Misc Cost: |
Estimate | $282,775.00 | % Over/Under | Company |
Bidder 1 | $193,580.00 | -31.54% | CROSS PLUS CONSTRUCTION, LLC |
Bidder 2 | $233,164.00 | -17.54% | FOWLER CONSTRUCTION |
Bidder 3 | $236,489.00 | -16.37% | EASTGATE SERVICES |
Bidder 4 | $237,660.00 | -15.95% | BOEN LANDSCAPING & IRRIGATION, LLC |
Bidder 5 | $239,960.00 | -15.14% | TERRY ENTERPRISES |
Bidder 6 | $270,200.00 | -4.45% | PATHFIELD INVESTMENTS LLC |
Bidder 7 | $273,700.00 | -3.21% | J-MEN CONCRETE CONSTRUCTION |
Bidder 8 | $274,365.00 | -2.97% | ROAD SOLUTIONS L.L.C. |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
5006001 | MOBILIZATION | LS | 1.000 | 20,000.00 | 1 2 3 4 5 6 7 8 | 20,220.000 1.000 1.000 80,000.000 41,000.000 20,000.000 65,000.000 20,000.000 |
5026001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 3.000 | 2,500.00 | 1 2 3 4 5 6 7 8 | 5,000.000 1.000 1.000 1,000.000 2,000.000 500.000 750.000 3,500.000 |
7526005 | TREE REMOVAL (4" - 12" DIA) | EA | 38.000 | 600.00 | 1 2 3 4 5 6 7 8 | 200.000 300.000 200.000 600.000 120.000 100.000 425.000 250.000 |
7526006 | TREE REMOVAL (12" - 18" DIA) | EA | 93.000 | 675.00 | 1 2 3 4 5 6 7 8 | 300.000 400.000 225.000 300.000 300.000 300.000 500.000 395.000 |
7526007 | TREE REMOVAL (18" - 24" DIA) | EA | 64.000 | 725.00 | 1 2 3 4 5 6 7 8 | 400.000 700.000 475.000 450.000 500.000 500.000 575.000 525.000 |
7526008 | TREE REMOVAL (24" - 30" DIA) | EA | 46.000 | 800.00 | 1 2 3 4 5 6 7 8 | 800.000 700.000 950.000 500.000 700.000 1,000.000 650.000 985.000 |
7526009 | TREE REMOVAL (30" - 36" DIA) | EA | 25.000 | 900.00 | 1 2 3 4 5 6 7 8 | 800.000 700.000 1,000.000 600.000 1,000.000 1,000.000 800.000 1,400.000 |
7526010 | TREE REMOVAL (36" - 42" DIA) | EA | 16.000 | 1,000.00 | 1 2 3 4 5 6 7 8 | 1,000.000 2,500.000 1,800.000 700.000 1,300.000 2,000.000 1,100.000 2,000.000 |
7526011 | TREE REMOVAL (42" - 48" DIA) | EA | 2.000 | 1,500.00 | 1 2 3 4 5 6 7 8 | 1,200.000 3,000.000 5,000.000 900.000 1,500.000 4,000.000 1,400.000 2,500.000 |
7526012 | TREE REMOVAL (48" - 60" DIA) | EA | 11.000 | 2,000.00 | 1 2 3 4 5 6 7 8 | 1,200.000 3,000.000 5,000.000 1,100.000 2,500.000 4,000.000 1,600.000 3,000.000 |
7526013 | TREE REMOVAL (60" - 72" DIA) | EA | 2.000 | 2,500.00 | 1 2 3 4 5 6 7 8 | 1,900.000 3,000.000 5,000.000 2,500.000 3,500.000 4,000.000 1,800.000 4,000.000 |
7526019 | TREE REMOVAL (72" - 84" DIA) | EA | 1.000 | 3,000.00 | 1 2 3 4 5 6 7 8 | 5,000.000 5,000.000 5,000.000 7,000.000 4,000.000 4,000.000 2,000.000 5,000.000 |
61856002002 | TMA (STATIONARY) | DAY | 60.000 | 250.00 | 1 2 3 4 5 6 7 8 | 1.000 1.000 1.000 1.000 150.000 300.000 225.000 12.000 |